HomeMy WebLinkAboutSDP201800003 Review Comments Final Site Plan and Comps. 2018-10-12
County of Albemarle
Department of Community Development
Memorandum
To: Patricia Saternye
From: Emily Cox
Date: 07 Feb 2018
Rev 1: 04 June 2018
Rev. 2: 12 Oct 2018
Subject: Hansen Road Church – Final Site Development Plan (SDP201800003)
The final site development plan for Hansen Road Church has been reviewed by Engineering. The
following comments will need to be addressed before approval:
1. WPO Plan must be submitted and approved before final site plan can be approved. Rev. 1:
Comment still valid. Rev. 2: Comment still valid. Rev. 3: Comment still valid.
2. Please ensure the professional seal is signed and dated. Rev. 1: Comment addressed.
3. Provide details for the proposed retaining walls. Rev. 1: Comment still valid. Rev. 2:
Comment addressed.
4. Provide drainage easements for all pipes carrying water offsite. Easements will n eed to be
recorded before plan can be approved. Rev. 1: Comment still valid – Plat is under review.
Rev. 2: Deed must be provided with drainage easement plat.
5. Parallel parking spaces should be 9’x20’, not 8’x20’. (County Code Chapter 18- 4.12.16) Rev. 1:
Comment addressed.
6. Show pavement markings required throughout the site (stop bars, one-way at the drop-off area,
etc.) Rev. 1: Comment addressed.
7. Provide a road section detail. Pavement sections were provided, but not road sections. Rev. 1:
Road cross section not provided. Pavement section detail was provided. Rev. 2: Comment
addressed.
8. Ensure proposed tree protection locations are shown on the demolition sheet. Rev. 1: Comment
addressed.
9. 2:1 Slopes should be avoided wherever possible. The landscape plan does properly specify the
required ground cover, but please ensure the WPO Plan also specifies this. Rev. 1: Comment
addressed.
10. Please show the acreage and c-factors for each drainage area on sheet C-11. Rev. 1: Comment
addressed.
11. Where is Ex. DI-7? The note on Sheet C-11 says concrete flume to Ex. DI-7, but it is not labeled.
Rev. 1: Comment addressed.
12. Velocity in storm drains should be kept below 10 ft/s if possible.( Per the VDOT drainage manual,
section 9.4.8.7, velocities in excess of 10ft/s should be avoided) Rev. 1: Provide specification or
recommendation showing that pipes/system can handle such excess velocity. Rev. 2:
Comment addressed.
13. Trees should not be above storm pipes or in easements. When necessary, move trees at least
5ft from the center of the utility. If not possible, move trees as far from utility as feasible.