VSMP Permit Plan Review
Project title: Woolen Mills Redevelopment
Project file number: WPO201700077
Plan preparer: Timmons Group [CRAIG.KOTARSKI@TIMMONS.COM]
Owner or rep.: Brian Roy [brianhroy@gmail.com]
Plan received date: 4 December 2017
(Rev. 1) 9 March 2018
(Rev. 2) 23 May 2018
(Rev. 3) 15 August 2018
(Rev. 4) 16 October 2018
Date of comments: 20 December 2017
(Rev. 1) 17 April 2018
(Rev. 2) 8 June 2018
(Rev. 3) 29 August 2018
(Rev. 4) 18 October 2018
Reviewers: Matt Wentland
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is approved. The
rationale is given in the comments below. The VSMP application content requirements can be
found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan(SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain(1)a PPP,(2)an ESCP,(3)a SWMP, and(4)any TMDL measures necessary.
1. Please provide signed copies of the registration statement and the certification. (Rev. 1)Comment
partially addressed. Please provide a copy of the signed Certification. (Rev. 2)Comment not
addressed. (Rev.3)Comment addressed.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. The PPP appears to be acceptable at this time.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is approved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. Please submit a Floodplain Development Permit application(Link). (Rev. 1)Response noted.
(Rev. 2)Comment not addressed. (Rev.3)FDP is currently under review. (Rev.4)The FDP
NIS engineering Review Comments
Page 2 of 3
has been approved.
2. The'1.351ba 4.141bs of nutrient credits will need to be purchased prior to plan approval. We
recommend waiting until site plan comments have been issued to ensure that no major changes to
the site design are required. (Rev. 1)Response noted. (Rev. 2)Please contact Ana Kilmer prior
to purchasing credits. (Rev.3)Response noted. (Rev.4) Comment addressed.
3. The VRRM worksheet was difficult to read. Please provide a larger copy(or email me the excel
file). (Rev. 1) Comment addressed.
4. Add a note to the plans and calculations stating the total drainage area of Moore's Creek at each
outfall versus the drainage to that outfall to show Channel Protection compliance(1%rule).
Entering a floodplain does not provide compliance under 9VAC25-870-66.B.4. (Rev. 1)
Comment addressed.
5. Provide more detailed depictions of the proposed outfalls showing how the endwalls and riprap
will be set into the bank and verification from the Army Corps(ViniPero)that they are acceptable.
(Rev. 1)Comment not addressed. Per emails with Timmons,the next submittal should
address this. (Rev. 2)Comment addressed.
D. Erosion and Sediment Control Plan(ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. To prevent erosion, the sediment basin outfall should not release the flow at the top of the slope. If
possible,the proposed permanent storm pipe should be installed first and used as the basin's
outlet. (Rev. 1) Comment addressed.
2. (Rev.2 comment) Show the proposed Level Spreader on the plans. Provide a detail/narrative on
the plans stating that the basin will be tied into the storm system as soon as possible per email to
Andrew on 6/7/18. (Rev.3)Comment addressed
E. Mitigation Plan
1. Provide a planting plan for the mitigation. Please refer to the Mitigation Plan checklist here. (Rev.
1)Comment addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re-submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval,plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms,which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
Sim"' Skitngineering Review Comments
Page 3 of 3
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time,the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing,this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued,via the coverage letter, the County can hold a pre-construction conference.
Applicants will need to complete the request for a pre-construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre-construction
conference will be scheduled with the County inspector. At the pre-construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;