COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832
Dear Mr. Hurt,
Fax (434) 972-4126
Date: December 7, 2018
We received your road bond inspection request with fees paid for the Buffalo Hills Road (Westview Subdivision)
project on 11/27/2018. The current bond amount is $51,670. This amount is not going to be reduced or released at
this time. The reasons are outlined in the attached checklist and email from VDOT. Also, please ensure items from
letter dated June 2001 have been addressed.
For your reference, below are links to Albemarle County procedures for public road acceptance:
http://www.albemarle.org/upload/images/forms center/departments/Community Development/forms/Engineering
and WPO Forms/Road Inspections & Acceptance - Public Road Acceptance Procedure 07-26-2012.pdf
http://www.albemarle.org/upload/images/forms center/departments/Community Development/forms/Engineering
and WPO Forms/Road Inspections & Acceptance - Certificate of Completion for Subdivision 03-16-09.pdf
Please contact me if you have any questions.
Sincerely,
Emily Cox
County of Albemarle
(434) 296-5832 ext 3565
ALgE
�rRCll31A
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
Road Bond Inspection
Bond Title: Westview Subdivsion
File Number: Project 2032, SUB1999-257, bond 2000-1
Date of inspection: 12/5/18 Original Bond Amount: $193,900
Reviewer: Emily Cox Current Bond Amount: $51,670
Phone: (434) 296-5832 Updated Bond Amount: $51,670 (no change)
Your bond inspection request has been processed. This list contains an update on the items received and
approved.
Received
Approved
Y
N
Y
N
N/A VDOT
■
❑
Completed inspection request and fee
■
❑
❑
❑
■
❑
As -built plan, updated, sealed to current date, per As -built policy
❑
■
❑
■
■
❑
Copies of recorded plats for right-of-way, easements
❑
■
❑
■
❑
■
VDOT approval AM-4.3, or partial completion via punchlist
❑
■
❑
■
❑
■
Letter from P.E. certifying improvements are built to plan
❑
■
❑
❑
❑
■
Current certification form completed by owner/developer
❑
■
❑
❑
■
❑
CBR test reports for each road
❑
■
❑
■
■
❑
Stone depth and material inspection reports (or core tests)
❑
■
❑
■
■
❑
Pavement depth and material inspection reports (or core tests)
❑
■
❑
■
■
❑
Compaction test reports for fill areas under road
❑
■
❑
■
■
❑
Pipe trench inspection reports
❑
■
❑
■
■
❑
Pipe interior inspections reports and video
❑
■
❑
■
❑
❑
Concrete test reports for structural concrete, curbing, aprons, etc.
❑
❑
■
❑
❑
❑
Structural inspection reports for any bridges or box culverts
❑
❑
■
❑
■
❑
County road name signs and posts, or a sign agreement for alt. posts ❑
■
❑
Please refer to on-line content at http://www.albemarle.org/deptforms.asp?departtnent=cdengmTo for checklists
and procedures.
Emily Cox
From: Kauppila, Joel <joel.kauppila@vdot.virginia.gov>
Sent: Wednesday, December 05, 2018 3:52 PM
To: Emily Cox
Subject: Re: westview subdivision - buffalo hills road
Attachments: image001 jpg
Hello Emily,
Based on a preliminary field and inspection report review, it appears the following is necessary prior to VDOT
acceptance;
• Asphalt
o Severe cracking showing evidence of base failure. Approximately 1800 LF (width varies) of base repair
on shoulders, isolated areas, and full width. A repair plan should be submitted and approved and then a
joint field inspection to mark out all of the repair areas.
o The areas of intact surface course without any deficiencies are too short and few. The entire surface
course will need to be mill and overlaid. Seal repair any isolated cracks after milling.
• CMP Pipes Across Road
o It appears each pipe has reached the end of it's service life and needs to be
lined/repaired/replaced. There are five cross pipes. A repair plan should be submitted and approved.
o All easements and drainage areas need to be free of trees, brush, and long grass
• Guardrail
o Appears in good condition. The terminal end is not correct and doesn't have a tension cable. A GR 11
needs to be installed here.
• Private Entrances
o One driveway is completely failed and needs to be re -done.
o There are a few that need to be cleaned out and minor repair at the end
o Need to verify some field entrances are per standard
• One 25 mph speed limit will need to be installed approximately 100' from the entrance.
• Asbuilts and plats still need to be reviewed
• All repairs will need testing reports performed and notification for VDOT inspection
• Utility IPPs and quit claims need to be submitted if they haven't been already
• After all of the major repairs a 45-day inspection can be performed.
Please let me know if there is anything I missed. Any questions let me know.
Thanks,
Joel
On Mon, Dec 3, 2018 at 11:06 AM Emily Cox <ecox@albemarle.org> wrote:
Joel -
I received information regarding westview subdivision and buffalo hills road. I believe they are trying to get it accepted
as a public road. Are you aware of this? Would you like me to scan the documents and send to you? Would you like to
come meet to discuss/review or meet on site?
1
r, 6-*ao3a.
Yam.
COUNTY OF ALBEMARLE
Department of Engineering & Public Works
401 McIntire Road, Room 211
Charlottesville, Virginia 22902-4596
(434) 296 - 5861
Fax (434) 972 - 4035
18 June 2001
Mr. Roger Ray
Roger W. Ray & Associates, Inc.
1717-2B Allied Street
Charlottesville, Virginia 22903
Re: Westview, as -built road plans
Dear Mr. Ray:
Thank you for the as -built road plans received on 11 June 2UU1. These plans have received afield
review with VDOT. The following items will need to be addressed by the developer:
1. Because of the significant variations from the approved design plans, the horizontal and vertical
centerline must be evaluated as a new design. Please provide the actual centerline curves and sight
distances or design values for review. Should areas fall short of the design standards, reconstruction
may be necessary.
2. The lots and road right-of-way must be revised and re -platted so that the road centerline is the right-
of-way centerline.
3. Shoulders and ditch lines may need reconstruction to match the plan typical section. Areas pointed
out by VDOT are stations 11 to 19, 25 to 27, 37 to 41, 30+50 to 34, 45-60 to the cul-de-sac.
4. All drainage ditches leaving the right-of-way must be within easements to a natural stream or
drainage swale. Some areas noted during the inspection: ditch lines on lot 2, 8, 9, 12, outlet on lot 7.
Sincerely,
Glenn Brooks
Senior Engineer
GEB/ybv
Copy: file 2032
C. W. Hurt Contractors
Charles Baber, VDOT
File; Brooks/Westview ab (t).doc