HomeMy WebLinkAboutWPO201600035 Other 2018-12-20 (3)North Pointe Section 1 1992 TEMPORARY SEDIMENT BASIN DESIGN DATA SHEET (With or without emergency Spillway) Project North Pointe Section 1 Basin # 1 (SWM/BMP 1) Total area draining to basin: 24.63 acres. Basin Volume Design Wet Storage: 3 Minimum required volume = 67 cu. yds. x Total Drainage Area (acres). 67 cu. yds. x 24.63 acres = 1650 cu. yds. 2 Available basin volume = 3281 cu. yds. at elevation (From storage - elevation curve) 3 Excavate 3281 cu, yds. to obtain required volume *. * Elevation corresponding to required volume = invert of the dewatering orifice. 445.00 dewatering device elevation 4 Available volume before cleanout required. 33 cu. yds. x 24.63 acres = 813 cu. yds. 5 Elevation corresponding to cleanout level = 444.00 (From Storage - Elevation Curve) 6 Distance from invert of the dewatering orifice to cleanout level (ft)= (Min. = 1.0 ft.) 445.00 441.50 Dry Storage: 7 Minimum required volume = 67 cu. yds. x Total Drainage Area (acres). 67cu.yds.X 24.63 acres = 1650 cu. yds. 3.14 1.00 1992 Total available basin volume at 2ND Stage * = 6104 elevation 447.30 . (From Storage - Elevation Curve) * Minimum = 134 cu. yds./acre of total drainage area. 9 Diameter of dewatering orifice = 19 INCH 10 Diameter of flexible tubing = 21 INCH plus 2 inches). Preliminary Design Elevations 11 Crest of Riser = 447.30 Top of Dam = 450.00 Upstream Toe of Dam = 436.00 Basin Shape 12 Length of Flow L = Effective Width We 3.43 If > 2, baffles are not required Not Required If < 2, baffles are required Runoff 3.14 cu. yds. at 13 Q2 = 21.67 cfs (From Chapter 5) 14 Q25 = 35.96 cfs (From Chapter 5) Principal Spillway Design cfs. 15 With emergency spillway, required spillway capacity Qp=Q2 21.67 (riser and barrel) Without emergency spillway, required spillway capacity Qp=Q25 35.96 (riser and barrel) III - 113 North Pointe Section 1 1992 3.14 203 With emergency spillway: Assumed available head (h) = N/A ft. (Using Q2) h = Crest of Emergency Spillway Elevation - Crest of Riser Elevation 87.72 Without emergency spillway: Assumed available head (h) = 2.7 ft. (Using Q25) h = Design High Water Elevation - Crest of Riser Elevation 17 Riser diameter (Dr) = 48 in. Actual head (h) = 0.9 ft. (From Plate 3.14-8.) Note: Avoid orifice flow conditions. 18 Barrel Length (1) = 90 ft. Head (H) on barrel through embankment = 12.20 ft. (From Plate 3.14-7). 19 Barrel diameter = 42 in. (From Plate 3.14-B [concrete pipe] or Plate 3.14-A [corrugated pipe]). 20 Trash rack and anti -vortex device Diameter = 72 inches. Thickness gage 16 ga. Corrugated Height = 21 inches. (From Table 3.14-D) USE: 1-1/4"pipe or 1-1/4 x 1-1/4x1/4angle Emergency Spillway Design "Emergency Spillway is being designed for the ultimate SWM/BMP. See SWM/BMP 4 sheet for Emergency Spillway details" 21 Required spillway capacity Q. = Q25 - Qp = N/A cfs. 22 Bottom width (b) = - ft.; the slope of the exit channel (s) _ - ft./foot; and the minimum length of the exit channel (x) _ - ft. (From Table 3.14-C). III - 114 North Pointe Section 1 1992 3.14 23 Depth of water at principal spillway crest (Y) _ Slope of upstream face of embankment (Z)= Slope of principal spillway barrel (Sb) _ Length of barrel in saturated zone (Ls) _ 7.30 ft. 2 :1. 3.67 % 38.50 ft. 24 Number of collars required = 3 dimensions = (From Plate 3.14-12) 25 Top of Dam = 450.00 Design High Water = 448.20 Emergency Spillway Crest = N/A Principal Spillway Crest = 447.30 Dewatering Orifice Invert = 445.00 Cleanout Elevation = 444.00 Elevation of Upstream Toe of Dam of Excavated Bottom of "Wet Storage Area" (if excavation was performed) = 440.00 III - 115 North Pointe Section 1 1992 TEMPORARY SEDIMENT BASIN DESIGN DATA SHEET (With or without emergency Spillway) Project North Pointe Section 1 Basin # 2 (SWM/BMP 3) Total area draining to basin: 45.74 acres. Basin Volume Design Wet Storage: 3 Minimum required volume = 67 cu. yds. x Total Drainage Area (acres). 67 cu. yds. x 45.74 acres = 3065 cu. yds. 2 Available basin volume = 6455 cu. yds. at elevation (From storage - elevation curve) 3 Excavate 6455 cu, yds. to obtain required volume *. * Elevation corresponding to required volume = invert of the dewatering orifice. 434.00 dewatering device elevation 4 Available volume before cleanout required. 33 cu. yds. x 45.74 acres = 1509 cu. yds. 5 Elevation corresponding to cleanout level = 433.00 (From Storage - Elevation Curve) 6 Distance from invert of the dewatering orifice to cleanout level (ft)= (Min. = 1.0 ft.) 434.00 427.69 Dry Storage: 7 Minimum required volume = 67 cu. yds. x Total Drainage Area (acres). 67cu.yds.X 45.74 acres = 3065 cu. yds. 3.14 1.00 North Pointe Section 1 1992 Total available basin volume at 2ND Stage * = 12767 elevation 438.80 . (From Storage - Elevation Curve) * Minimum = 134 cu. yds./acre of total drainage area. 9 Diameter of dewatering orifice = 26 INCH 10 Diameter of flexible tubing = 28 INCH plus 2 inches). Preliminary Design Elevations 11 Crest of Riser = Top of Dam = Upstream Toe of Dam = Basin Shape 441.50 421.00 12 Length of Flow L = Effective Width We 2.25 If > 2, baffles are not required Not Required If < 2, baffles are required Runoff 13 Q2 = 53.06 cfs 14 Q25 = 83.25 cfs Principal Sgillwav Desian (From Chapter 5) (From Chapter 5) 3.14 cu. yds. at cfs. 15 With emergency spillway, required spillway capacity Qp=Q2 53.06 (riser and barrel) Without emergency spillway, required spillway capacity Qp=Q25 83.25 (riser and barrel) North Pointe Section 1 1992 3.14 203 With emergency spillway: Assumed available head (h) = 0.45 ft. (Using Q2) h = Crest of Emergency Spillway Elevation - Crest of Riser Elevation 87.72 Without emergency spillway: Assumed available head (h) = N/A ft. (Using Q25) h = Design High Water Elevation - Crest of Riser Elevation 17 Riser diameter (Dr) = 60 in. Actual head (h) = 1.0 ft. (From Plate 3.14-8.) Note: Avoid orifice flow conditions. 18 Barrel Length (1) = 120 ft. Head (H) on barrel through embankment = 19.05 ft. (From Plate 3.14-7). 19 Barrel diameter = 42 in. (From Plate 3.14-B [concrete pipe] or Plate 3.14-A [corrugated pipe]). 20 Trash rack and anti -vortex device Diameter = Winches. Thickness gage 12 ga. Corrugated Height = 29 inches. (From Table 3.14-D) USE: 1-1/2"pipe or 1-1/2 x 1-1/2x1/4 angle Emergency Spillway Design "Emergency Spillway is being designed for the ultimate SWM/BMP. See SWM/BMP 4 sheet for Emergency Spillway details" 21 Required spillway capacity Qe = Q25 - Qp = 30.19 cfs. 22 Bottom width (b) = - ft.; the slope of the exit channel (s) _ - ft./foot; and the minimum length of the exit channel (x) _ - ft. (From Table 3.14-C). III - 114 North Pointe Section 1 1992 23 Depth of water at principal spillway crest (Y) _ Slope of upstream face of embankment (Z)= Slope of principal spillway barrel (Sb) _ Length of barrel in saturated zone (Lj _ 17.80 ft. 2 :1. 6.67 % 109.23 ft. 24 Number of collars required = 4 dimensions = (From Plate 3.14-12) 25 Top of Dam = 441.50 Design High Water = 440.05 Emergency Spillway Crest = 439.25 Principal Spillway Crest = 438.80 Dewatering Orifice Invert = 434.00 Cleanout Elevation = 433.00 Elevation of Upstream Toe of Dam of Excavated Bottom of "Wet Storage Area" (if excavation was performed) = 421.00 III - 115 3.14 6.7 X 6.7