HomeMy WebLinkAboutARB201900005 Review Comments Architectural Review Board Approval 2019-01-29COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4176
January 29, 2019
Mark Kestner
Henningsen Kestner Architects
1108 E. High Street
Charlottesville, VA 22902
RE: ARB-2019-5: 2300 Hunter's Way, Major Amendment (TMP 07800-00-00-049A0)
Dear Mr. Kestner,
We have received the above -referenced application. We cannot accept your application for review because
your submittal is not complete. The following items were missing from your submittal:
1. 8 collated copies of a site plan set that provide all of the information requested in Sections B., C., and D.
of the Final Review of a Site Development Plan Submittal Requirements Checklist.
2. The correct and a completed submittal requirements checklist for a Final Review of a Site Development
Plan (this application is not a County -wide Certificate of Appropriateness for Structures 750' or more from
the EC and no taller than 5 stories).
3.One set of material and color samples.
4. A complete architectural drawings submission that is produced at a verifiable scale of 1/8" = 1'.
Within 15 days of the date of this letter, you may resubmit the application with all of the information
required by the ARB Checklist for Final Review ofa Site Development Plan. The date of the next submittal
deadline following the date that the revised submittal is received by the County will be considered the new
submittal date. Please consult the attached Submittal and Meeting Schedule for the corresponding ARB
meeting date.
If you fail to resubmit within the 15 day period, the application shall be denied and a new fee shall be
required to submit the new application.
If you have any questions about this process, feel free to contact me.
Sincerely,*��"
AA I����
polk�
Heather McMahon, Senior Planner
434-296-5832 x3278
hmcmahon&albemarle. org
cc: File ARB-2019-5
Heartrock Farm LLC
2521 Summit Ridge Trail
Charlottesville, VA 22911
2019 Submission and Review Schedule
Architectural
Review Board
Deadline for Filing
(3 P.M.)
Architectural Review Board
Meeting Date
Monday
Monday
Nov 26 2018
Jan 7
Dec 10 and 17 2018
Tue Jan 22
Wed Dec 26 2018
Feb 4
Jan 7
Tue Feb 19
Tue Jan 22
Mar 4
Feb 4
Mar 18
Tue Feb 19
Apr 1
Mar 4
Apr 15
Mar 25
May 6
Apr 8
May 20
Apr 22
Jun 3
May 6
Jun 17
May 20
Jul
Jun 3
Jul 15
Jun 24
Aug5
Jul 8
Aug19
Jul 22
Tue Sep 3
Aug5
Sep 16
Aug 26
Oct 7
Sep 9
Oct 21
Sep 23
Nov 4
Oct 7
Nov 18
Oct 21
Dec 2
Nov 4
Dec 16
Nov 25
Jan 6 2020
Dec 9
Tue Jan 212020
Dec 30
Feb 3 2020
Jan 6 2020
Tue Feb 18 2020
ARB meets 1 st and 3rd day unless the day is a holiday or if otherwise noted.
Bold italics = submittal/meeting day is different due to a holiday.
Dates with shaded background are not 2019.
2020 dates are tentative.
Architectural Review Board
Final Review of a Site Development Plan Checklist for Completeness
❑I 8 collated copies
set of color/material
A. Written description of the proposal
Commented [HM 1]: 8 collated copies of an 8-page architectural
drawing set were submitted; no accompanying site plan set was
submitted and 8 copies are required
Commented [HM2]: Not submitted; furthermore, materials
"board" on ARB.02 Sheet is incomplete and missing color, brand,
and technical information
® Written description of the proposal.
❑ Explain how the proposal is compatible with the surrounding area and the Entrance Corridor. — Commented [HM3]: Not provided
B. $lte plan Showing the following (drawn to the scale of 1 "=20', clearly legible and folded):
❑ Location(s) of proposed building(s) on the site.
❑ Location of proposed parking, travelways, walkways and other improvements.
❑ Mechanical equipment, trash containers, loading and service areas, other similar features and
improvements, and associated screening.
❑ Existing and proposed topography drawn with contour intervals of 5-feet or less, and with sufficient
off -site topography to describe prominent and pertinent off -site features and physical characteristics,
but in no case less than 50-feet outside of the site.
❑ Location and size of existing and proposed utilities and easements. Identify type of utility and extent
of easement.
❑ Stormwater management plan.
❑ Location of retaining walls indicating top and bottom elevations, maximum wall height, and proposed
materials, with material and color samples.
❑ Sheet number, total number of sheets, date of the drawing, date and description of the latest revision, and
contact information for the firm preparing the drawings in the title block on all drawings. For revised
drawings, clearly identify revisions made.
— Commented [HM4]: Not provided
C. ILandscape plan Showing the following (drawn to the scale of 1 "=20' orlarger, clearly legible and folded): — Commented [HMS]: Not provided
❑ Proposed landscaping that meets or exceeds the requirements outlined in the ARB guidelines.
❑ Existing landscaping to be removed. Include the location, size, and species.
❑ Landscape key including all landscape symbols and a description of what they represent.
❑ Location of existing and proposed tree lines and tree save areas.
❑ Location of existing natural features.
❑ Location of individual trees of 6-inch caliper or greater and all significant groups of trees indicated by
botanical name and caliper.
❑ Location and height of above -ground utilities and associated easements, and location of below -
ground utilities and associated easements.
❑ Stormwater facilities.
❑ Provide a signed, tree conservation checklist with all checklist items drawn on the landscape plans.
❑ Include tree protection fencing and limits of work on the landscape, grading and E&S plans.
I
OVER
D. Lighting plan showing the following (drawn to the scale of 1'=20' or larger, clearly legible and folded): _ - Commented [HM6]: Not provided
❑ Location of all proposed building and site lighting.
❑ Lighting schedule identifying all proposed light fixtures, poles and brackets.
❑ Manufacturer's cut sheets illustrating proposed lighting fixtures and information on illumination type,
intensity, style, shielding, color, finish, and installation height.
❑ Photometric plan addressing all fixtures and indicating that lighting does meet the requirements of
Section 4.17 of the Zoning Ordinance.
❑ Coordination of lighting with landscaping and other site elements.
E. Appearance of the building(s) (architectural elevations, color perspective sketches, site sections):
❑ Dimensioned architectural elevations of the proposed buildin s . Elevations must be drawn to the — Commented [HM7]: The submitted drawings are dimensioned
scale of 11/8"=V-0". Include a building materials schedule and key on the elevation drawings. at1/8"=r,however, reproduced onllxl7size paper, the scale is
Submittal of elevations that are not visible from the Entrance Corridor may be required to clarify the reduced and is not" to scale" or verifiable when using an architect's
overall building design. scale to measure given dimensions
❑ Color perspective sketches that show the proposed development as seen from the Entrance Corridor. Commented [HMS]: Details s and 4 on ARs.03 sheet are mis-
labeled as Y" = 1' when the scale is 1/8" = 1' on all other details
❑ Site sections that clarify proposed changes in topography and illustrate the visibility of the proposed Commented [HM9]: Notprovided
development from the Entrance Corridor. Site sections shall indicate the finish floor elevation(s) and
roof height(s) relative to the natural elevations along the Entrance Corridor. Commented [HM10]: Not provided
❑ One set of all building materials / colors. Commented [HM11]: Not provided
❑ A floor plan adequate to show exterior walls windows and doors. — Commented [HM12]: Not provided
F. Additional material
® Provide labeled, color, 8-'/2" x 11" photographs of the site as seen from both directions on the
Entrance Corridor.
® Signatures
2
OVER