HomeMy WebLinkAboutWPO201800076 Plan - E&S Erosion Control Plan 2018-11-26SCOPE OF WORD: THIS PLAN SERVES AS AN EROSION AND SEDIMENT CONTROL PLAN AND GRADING PLAN ASSOCIATED WITH MAINTENANCE WORK TO RESTORE ACAMPSITE FIELD AND GRAVEL ACCESS ROAD TO A PROPERLY DRAINING CONDITION. WORK INCLUDES INSTALLING A CULVERT AND GRADING ACTIVITIES. ASMALL PORTION OF THE FLOODPLAIN AND WATER PROTECTION ORDINANCE BUFFER WILL BE IMPACTED BY THIS WORK. THIS IS ALLOWED BY -RIGHT FORTH IS USE, AND THE SPECIAL USE PERMIT ASSOCIATED WITH THIS PROPERTY. PLEASE SEETHE LETTER OF NO -RISE AND FLOODPLAIN IMPACT NARRATIVE ACCOMPANYING THIS SUBMISSION FOR MORE DETAILS- PROJECT ETAILS. PROJECT INFORMATION: UTILITY OWNERS: OWNER: MOUNTAIN DREAM, LLC 56 MISTY MOUNTAIN ROAD GREENWOOD, VIRGINIA 22943 CONTACT: MICHAEL LEO PHONE: 540.456.6409 ENGINEER: LINE + GRADE I CIVIL ENGINEERS 113 4TH STREET NE CHARLOTTESVILLE, VA 22902 CONTACT: DANIEL C. HYER, PE PHONE: 434.262.0169 SURVEYOR: MERIDIAN PLANNING GROUP, LLC 440 PREMIER CIRCLE, SUITE 200 CHARLOTTESVILLE, VA 22901 CONTACT: TIMOTHY R. MILLER PHONE: 434.882.0121 PARCEL INFO: PARCEL #: 07100-00-00-00300 56 MISTY MOUNTAIN ROAD GREENWOOD, VIRGINIA 22943 ZONED: RURAL AREAS LEGAL AREA: 47.11 ACRES ADDT'L INFORMATION: DISTURBANCE AREA: 1.60 AC (69,786 SF) 12 DIGIT HUC CODE: 020802040101 i i t• i111kyj U1111 e i i ELECTRIC: DOMINION WATER: PRIVATE WELL STORM SEWER: PRIVATE SANITARY SEWER: PRIVATE SEPTIC BC BACK OF CURB ID INSIDE DIAMETER R&D REMOVE AND DISPOSE ABAN ABANDON LA LANDSCAPED AREA R&R R'.EMOVEAND RESET AC ACRES LF LIN EAR FEET R&S R' EM OVE AND STACK ADJ ADJUST LOD LIMITS OF DISTURBANCE SB SOUTHBOUND APPROX APPROXIMATE LT LEFT SF SQUARE FEET ASPH ASPHALT MAX MAXIMUM SSD STOPPING SIGHT DISTANCE It BASELINE MIN MINIMUM STA S>TATION BLDG BUILDING ME MATCH EXISTING SW SiIDEWALK BM BENCHMARK NIC NOT IN CONTRACT TEMP TEMPORARY (L CENTERLINE N.T.S. NOT TO SCALE TRANS TRANSITION CF CUBIC FEET NB NORTHBOUND TYP TYPICAL CG CURB AND GUTTER OC ON CENTER WB V'VESTBOUND CONC CONCRETE OD OUTSIDE DIAMETER WSEL V'VATER SURFACE ELEVATION CONST CONSTRUCTION PRKG PARKING DI DROP INLET PROJ PROJECT LP LOW POINT DND DO NOT DISTURB PROP PROPOSED SP SADDLE POINT EB EASTBOUND PVMT PAVEMENT q EL ELEVATION PM PAVEMENT MARKING EX EXISTING REM REMOVE FND FOUNDATION ROW RIGHT-OF-WAY GRVL GRAVEL RT RIGHT HC HANDICAP BC BACK OF CURB PCC POINT OF COMPOUND CURVATURE BR BOTTOM OF RAMP PI POINT OF INTERSECTION SVCS BEGIN VERTICAL CURVE STATION PNT POINT BVCE BEGIN VERTICAL CURVE ELEVATION PR PROPOSED ELEVATION BW BOTTOM OF WALL PRG POINT OF REVERSE CURVATURE D OR A DELTA ANGLE PT POINT OF TANGENCY EG EXISTING GRADE PVC POINT OF VERTICAL CURVATURE EP EDGE OF PAVEMENT RVI POINT OF VERTICAL INTERSECTION EROSION & SEDIMENT CONTROL PLAN - PHASE II PVT POINT OF VERTICAL TANGENCY EVCS END VERTICAL CURVE STATION C1.3 EVCE END VERTICAL CURVE ELEVATION R RADIUS TAN TANGENT DISTANCE FG FINISHED GRADE d+ STORMWATER COMPUTATIONS w TC TOP OF CURB FL FLOWLINE Or THT THROAT HP HIGH POINT is Af TR TOP OF RAMP INV INVERT ? N TW TOP OF WALL L LENGTH STA STATION LP LOW POINT LVC LENGTH OF VERTICAL CURVATURE SP SADDLE POINT PC POINT OF CURVATURE OFF OFFSET VICINITY MAP SCALE: 1" = 30,000' ft�E 25�. LOCATION MAP SCALE: 1" = 1,000' PROJECT LOCATION Description Recipient APPROVED 1 IST SUBMISSION COUNTY OF ALBEMARLE by the J l!bemarle County 2 2ND SUBMISSION Community LL)Ejl elgp7,ienr Department SHEET INDEX { LU t 3 a ✓ Q j5 CO.O TITLE SHEET x CO.1 GENERAL NOTES C1.0 EROSION & SEDIMENT CONTROL PLAN - PHASE I PROJECT_ C1.1 EROSION & SEDIMENT CONTROL PLAN - PHASE II 4.f� C1.2 � LOCAT I o N C1.3 EROSION & SEDIMENT CONTROL DETAILS t.. '� r - `did �Jl 4§' � {�Y a S" .n. ✓ &L f b`' rt{ l }-. {_a ���£.�t 4 s iq Y 1 d+ STORMWATER COMPUTATIONS w LI � , .x Or q v is Af 41 Jj ? N y rF f �. ¢ �✓ r zK q t VICINITY MAP SCALE: 1" = 30,000' ft�E 25�. LOCATION MAP SCALE: 1" = 1,000' PROJECT LOCATION SUBMITTAL LOC Submission Description Recipient APPROVED 1 IST SUBMISSION COUNTY OF ALBEMARLE by the J l!bemarle County 2 2ND SUBMISSION Community LL)Ejl elgp7,ienr Department SHEET INDEX FileDate, ` - a �. ---------- _�vC? _ � # —,,r � I --__ - SHEETNUMBER SHEETTITLE CO.O TITLE SHEET CO.1 GENERAL NOTES C1.0 EROSION & SEDIMENT CONTROL PLAN - PHASE I C1.1 EROSION & SEDIMENT CONTROL PLAN - PHASE II C1.2 EROSION & SEDIMENT CONTROL NOTES C1.3 EROSION & SEDIMENT CONTROL DETAILS C2.0 GRADING & DRAINAGE PLAN C2.1 SITE SECTIONS AND DETAILS 02.2 STORMWATER COMPUTATIONS TOTAL SHEETS = 9 SUBMITTAL LOC Submission Description Recipient Submittal Date 1 IST SUBMISSION COUNTY OF ALBEMARLE 10/18/2018 2 2ND SUBMISSION COUNTY OF ALBEMARLE 11/9/2018 3 SIGNATURE SUBMISSION COUNTY OF ALBEMARLE 11/26/2018 U W z 10 q . , q r1L I if 0� ., k 1 P 26/2 9--� DANT C1 1 Y E R L is No. IAC 4 ;596 qdL �\7 APPROVED DCH SUBMITTAL NO. 8 I PROJECT 1809400 1 T11-1 E VJ0 R K OF L.1N'E + ORAD GENERAL CONSTRUCTION NOTES: 1. ALL CONSTRUCTION METHODS AND MATERIALS SHALL BE IN ACCORDANCE WITH THE CURRENT VIRGINIA DEPARTMENT OF TRANSPORTATION ROAD AND BRIDGE STANDARDS AND SPECIFICATIONS (VDOT RBS&S), VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK, THE RULES AND REGULATIONS WATER AND SANITARY SEWER CONSTRUCTION SPECIFICATIONS AND STANDARDS FOR THE PLAN APPROVING AUTHORITY AND ANY OTHER APPLICABLE FEDERAL, STATE, OR LOCAL ORDINANCES, CODES, AND LAWS. 2. CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING ALL CONDITIONS, MATERIALS, DIMENSIONS LOCATIONS AND EXISTING ELEMENTS TO REMAIN IN THE FIELD BEFORE PROCEEDINGS WITH ANY WORK. IF CONDITIONS VARY FROM WHAT IS REPRESENTED IN THE DRAWINGS, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE ENGINEER. 3. EXISTING CONSTRUCTION SHOWN IN THESE DRAWINGS SHALL BE USED AS RELATIVE REFERENCES AND ARE TO BE VERIFIED IN THE FIELD BY THE CONTRACTOR IF DEEMED CRITICAL FOR PROPER EXECUTION OFTHE WORK. 4. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL DUST CONTROL MEASURES. 5. PROVIDE ADEQUATE PROTECTION FOR THE EXISTING BUILDINGS, BUILDING OCCUPANTS, VEHICLES AND PEDESTRIANS AT ALL TIMES IN ACCORDANCE WITH OSHA AND ALL APPLICABLE STATE AND LOCAL CODES. 6. MATERIALS AND EQUIPMENT SHALL BE STORED IN APPROVED AREAS TO PREVENT IMPACTS ON VEHICLES AND PEDESTRIANS. CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR MEASURES TAKEN TO ENSURE VEHICULAR AND PEDESTRIAN SAFETY THROUGH THE ENTIRE DURATION OF THE WORK. SAFETY IS PARAMOUNT. 7. EQUIPMENT AND MATERIALS SHALL BE STORED IN DESIGNATED AREAS AND SHALL NOT ENCUMBER THE OWNER'S OPERATIONS, SURROUNDING RIGHT OF WAY, OR ADJOINING GROUNDS. 8. ALL WORK AREAS SHALL BE CLEANED DAILY. 9. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTION OF BUILDINGS ADJACENT TO WORK AREAS. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL COSTS OF DAMAGES RESULTING FROM CONSTRUCTION ACTIVITIES. 10. SECTION CUTS AND DETAIL CALLOUTS INDICATED IN THE DRAWINGS ARE TYPICAL FOR THE PROJECT. THEY ARE TO BE CONSIDERED TYPICAL FOR SIMILAR CONDITIONS AND HAVE NOT BEEN SHOWN EVERYWHERE THEY APPLY. 11, CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR JOB SITE SAFETY. 12. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF ALL CONSTRUCTION. 13. SYMBOLS IN THE DRAWINGS ARE NOT TO SCALE. 14. ALL WORK SHALL BE LAID -OUT PRIOR TO INSTALLATION OF NEW WORK BASED ON MEASUREMENT OF EXISTING CONSTRUCTION AND EXISTING CONSTRUCTION DESIGNATED TO REMAIN AS PART OF THE PROJECT. DO NOT START INSTALLATION OF WORK UNTIL LAY -OUT IS COMPLETE AND POTENTIAL CONFLICTS HAVE BEEN IDENTIFIED AND ADDRESSED. 15. THE CONTRACTOR SHALL BE HELD RESPONSIBLE FOR ALL DAMAGE TO THE EXISTING BUILDINGS AND ADJACENT GROUNDS AND PROPERTY CAUSE BY THE CARELESSNESS OR NEGLECT OF HIS WORKMEN. DAMAGE TO PORTIONS OFTHE PROPERTY NOT SUBJEC i TO WORK UNDER THE CONTRACT SHALL BE REPAIRED TO THE FULL SATISFACTION OFTHE OWNER AND ENGINEER, AT THE CONTRACTOR'S EXPENSE. 16. PROTECTION OF THE WORK: PROTECT EFFECTIVELY ALL MATERIALS AND EQUIPMENT DURING THE ENTIRE PERIOD OF CONSTRUCTION. REPLACE MATERIALS AND EQUIPMENT DAMAGED, LOST OR STOLEN WITHOUT ADDITIONAL COST TO THE OWNER. 17. PROTECT EXISTING MATERIALS DURING INSTALLATION OF TEMPORARY PROTECTION AND CONSTRUCTION. DO NOT DEFACE OR REMOVE EXISTING MATERIALS IF INTENDED TO STAY. ATTACHMENTS OF TEMPORARY PROTECTION TO EXISTING CONSTRUCTION SHALL BE APPROVED BY THE ENGINEER PRIOR TO INSTALLATION. 18. OBTAIN ENGINEER REVIEW AND WRITTEN APPROVAL IN THE FORM OF A CONSTRUCTION CHANGE DIRECTIVE OR SUPPLEMENTAL INSTRUCTION BEFORE MAKING CHANGES OR ADDITIONS TO CONSTRUCTION OR REMOVING MATERIALS THAT WERE INTENDED TO REMAIN. 19. NOTIFY ENGINEER OF VISIBLE CHANGES IN THE INTEGRITY OF MATERIALS OR COMPONENTS WHETHER DUE TO ENVIRONMENTAL CAUSES INCLUDING BIOLOGICAL ATTACK, UV DEGRADATION, FREEZING OR THAWING OR DUE TO STRUCTURAL DEFECTS, INCLUDING CRACKS, MOVEMENT OR DISTORTION. DO NOT PROCEED WITH WORK IN QUESTION UNTIL DIRECTED BY THE ENGINEER. 20. WHERE MISSING FEATURES ARE INDICATED TO BE REPAIRED OR REPLACED, PROVIDE FEATURES WHOSE DESIGNS ARE BASED ON ACCURATE DUPLICATIONS RATHER THAN ON CONJECTURAL DESIGNS, SUBJ ECT TO APPROVAL OF THE ENGINEER. 21. WHERE WORK REQUIRES EXISTING FEATURES TO BE REMOVED, CLEANED AND REUSED, PERFORM THESE OPERATIONS WITHOUT DAMAGE TO THE MATERIALS THEMSELVES, TO ADJACENT MATERIALS, OR TO THE SUBSTRATE. WHEN CLEANING, MATCH SAMPLES OF EXISTING MATERIALS THAT HAVE BEEN CLEANED AND IDENTIFIED FOR ACCEPTABLE CLEANING LEVELS. AVOID OVER CLEANING TO PREVENT DAMAGE TO EXISTING MATERIALS DURING CLEANING. 22. TEMPORARY MATERIALS MAY BE NEW OR USED, BUT MUST BE ADEQUATE IN FOR REQUIRED USAGE, MUST NOT CREATE UNSAFE CONDITIONS AND MUST NOT VIOLATE REQUIREMENTS OFAPPLICABLE CODES AND STANDARDS. 23. CONTRACTOR SHALL PROVIDE AND MAINTAIN ADEQUATE FIRE PROTECTION IN THE FORM OF FIRE EXTINGUISHER OR OTHER EFFECTIVE MEANS OF EXTINGUISHING FIRE, READY FOR INSTANT USE, DISTRIBUTED AROUND THE PROJECT AND IN ASND ABOUT TEMPORARY, INFLAMMABLE STRUCTURES DURING CONSTRUCTION OF WORK. EXISTING FIRE HOSE CONNECTIONS SHALL BE ACCESSIBLE AT ALL TIMES BY FIRE DEPARTMENT PERSONNEL. MATERIAL SAND DEBRIS SHALL NOT BE STORED IN FRONT OF THE CONNECTION, THUS PREVENTING ACCESS. THE CONTRACTOR SHALL COORDINATE ACCESS PROCEDURES WITH THE FIRE MARSHALL. 24. GASOLINE AND OTHER FLAMMABLE LIQUIDS SHALL BE STORED AND DISPENSED FROM UL LISTED SAFETY CONTAINERS IN CONFORMANCE WITH THE NATIONAL BOARD OF FIRE UNDERWRITERS' RECOMMENDATIONS. 25. SUBMITTALS ARE NOT REQUIRED IF CONTRACTOR ELECTS TO USE THE PROPRIETARY PRODUCTS LISTED. SUBMITTALS WILL BE REQUIRED IF CONTRACTOR WISHES TO USE ALTERNATE PRODUCTS. ALL ALTERNATE PRODUCTS ARE SUBJECT TO REVIEW AND APPROVAL BY THE ENGINEER AND OWNER. 26. CONTRACTOR SHALL CALL MISS UTILITY AT 1-800-552-7001 BEFORE CONSTRUCTION COMMENCES. 27. TREE AND PLANT ROOTS OR BRANCHES THAT MAY INTERFERE WITH THE WORK SHALL BE TRIMM ED OR CUT ONLY WITH THE APPROVAL OF THE OWNER AND ENGINEER. ANY TREES OR PLANTS WHICH ARE SHOWN TO REMAIN THAT DO NOT INTERFERE WITH THE WORK, BUT ARE DAMAGED BY CONTRACTOR OR HIS SUB -CONTRACTORS, SHALL BE REPLACED BY CONTRACTOR AT NO ADDITIONAL COST. FIRE PREVENTION: 1. SMOKING SHALL ONLY BE ALLOWED IN DESIGNATED SPACES WITH PROPER RECEPTACLES. "NO SMOKING" SIGNS SHALL BE POSTED AT EACH BUILDING SITE AND WITHIN EACH BUILDING DURING CONSTRUCTION PER VIRGINIA STATEWIDE FIRE PREVENTION CODE. 2. OVERHEAD WIRING OR OTHER OVERHEAD OBSTRUCTIONS SHALL NOT BE LOWER THAN 13 FEET 6 INCHES OVER A PUBLIC STREET PER THE VIRGINIA STATEWIDE FIRE PREVENTION CODE. 3. CONTRACTOR SHALL ENSURE THAT BUILDING STREET NUMBERS ARE PLAINLY VISIBLE FROM THE FRONTAGE STREET AT ALL TIMES DURING CONSTRUCTION FOR EMERGENCY RESPONDERS, PER VIRGINIA STATEWIDE FIRE PREVENTION CODE. 4. WASTE AND COMBUSTIBLE DEBRIS SHALL BE REMOVED FROM THE BUILDING AT THE END OF EACH DAY AND DISPOSED OF IN ACCORDANCE WITH VIRGINIA STATEWIDE FIRE PREVENTION CODE. 5. OPERATIONS INVOLVING THE USE OF CUTTING AND WELDING SHALL BE DONE IN ACCORDANCE, WITH CHAPTER 35 OF THE VIRGINIA STATEWIDE FIRE PREVENTION CODE. 6. FIRE EXTINGUISHERS SHALL BE PROVIDED WITH NOT LESS THAN ONE APPROVED PORTABLE FIRE EXTINGUISHER AT EACH STAIRWAY ON ALL FLOOR LEVELS WHERE COMBUSTIBLE MATERIALS HAVE ACCUMULATED IN ACCORDANCE WITH THE VIRGINJIIASTATEWIDE FIRE PREVENTION CODE. 7. VEHICULAR ACCESS FOR FIRE FIGHTING SHALL BE PROVIDED AT ALL CONSTRUCTION AND DEMOLITION SITES AND TO WITHIN 100 FEET OF TEMPORARY OR PERMANENT FIRE DEPARTMENT CONNECTIONS. VEHICULAR ACCESS SHALL BE CAPABLE OF SUPPORTING FIRE APPURTENANCE AND VEHICLE LOADING UNDER ALL WEATHER CONDITIONS IN ACCORDANCE WITH THE VIRGINIA STATEWIDE FIRE PREVENTION CODE. CONCRETE AND ASPHALT: 1. ALL MATERIAL INSIDE FORMS SHALL BE CLEAN AND FREE OF ALL ROCKS AND OTHER LOOSE DEBRIS. SUB -BASE MATERIAL SHALL BE COMPACTED BY MECHANICAL MEANS. 2. CONCRETE SHALL NOT BE PLACED UNLESS THE AIR TEMPERATURE IS AT LEAST 40 DEGREES FAHRENHEIT (F) IN THE SHADE AND RISING. 3. CONCRETE SHALL NOT BE PLACED UNTIL STEEL DOWELS HAVE BEEN INSTALLED IN EXISTING CONCRETE IN ACCORDANCE WITH ALBEMARLE COUNTY STANDARDS. 4. 1/2 " PREMOLDED EXPANSION JOINT MATERIAL SHALL BE PLACED AT A MAXIMUM OF 30' INTERVALS ON NEW SIDEWALK, CURB, CURB & GUTTER, AT EACH END OF DRIVEWAY ENTRANCES, AT EACH END OF HANDICAP RAMPS, SOME POINT ON ENTRANCE VVALKS AND STEPS ADJUSTMENTS, AND ALONG BUILDINGS AND WALLS WHERE NEW CONCRETE SIDEWALKS ARE PLACED AGAINST THEM. 5. ALL EXISTING CURBS, CURB & GUTTER, SIDEWALK AND STEPS TO BE REMOVED SHALL BE TAKEN OUT TO THE NEAREST JOINT. DEMOLITION AND DISPOSAL COST TO BE INCLUDED IN OTHER UNIT BID ITEMS. NO SEPARATE PAYMENT WILL BE MADE FOR THIS WORK. 6. EXISTING ASPHALT CONCRETE PAVEMENT SHALL BE SAW CUT AND REMOVED AS PER THE SPECIFICATIONS. REMOVAL SHALL BE DONE IN SUCH A MANNER AS TO NOT TEAR, BULGE OR DISPLACE ADJACENT PAVEMENT. EDGES SHALL BE CLEAN AND VERTICAL, ALL CUTS SHALL BE PARALLEL OR PERPENDICULAR TO THE DIRECTION OFTRAFFIC. 7. DISPOSAL OF ALL EXCESS AND DEMOLITION MATERIAL IS THE RESPONSIBILITY OFTHE CONTRACTOR. UTI LITI ES: ALBEMARLE COUNTY GENERAL CONSTRUCTION NOTES: 1. PRIOR TO CONSTRUCTION OR EXCAVATION, THE CONTRACTOR SHALL ASSUME RESPONSIBILITY OF LOCATING ANY AND ALL UNDERGROUND UTILITIES 1. PRIOR TO ANY CONSTRUCTION WITHIN ANY EXISTING PUBLIC RIGHT-OF-WAY, INCLUDING CONNECTION TO ANY EXISTING ROAD, A PERMIT SHALL BE uj (PUBLIC OR PRIVATE) THAT MAY EXIST WITHIN OR CROSS THROUGH THE AREA OF CONSTRUCTION WHETHER OR NOT THEY ARE SHOWN ON THE PLANS. OBTAINED FROM THE VIRGINIA DEPARTMENT OF TRANSPORTATION (VDOT). THIS PLAN AS DRAWN MAY NOT ACCURATELY REFLECT THE REQUIREMENTS PRIOR TO ANY CONSTRUCTION ACTIVITY, THE CONTRACTOR SHALL CALL 'MISS UTILITY OF VIRGINIA' AT 1-800-552-7001. THE CONTRACTOR SHALL BE OF THE PERMIT. WHERE ANY DISCREPANCIES OCCUR THE REQUIREMENTS OF THE PERMIT SHALLGOVERN. RESPONSIBLE FOR REPAIRING, AT HIS SOLE EXPENSE, ANY EXISTING UTILITY DAMAGED DURING CONSTRUCTION. 2. ALL MATERIALS AND CONSTRUCTION) METHODS SHALL CONFORM TO CURRENT SPECIFICATIONS AND STANDARDS OF VDOT UNLESS OTHERWISE NOTED. 2. THE PLAN DOES NOT GUARANTEE THE EXISTENCE, NONEXISTENCE, SIZE, TYPE, LOCATION, ALIGNMENT, OR DEPTH OF ANY OR ALL UNDERGROUND UTILITIES 3. ERASION AND SILTATION CONTROL MEASURES SHALL BE PROVIDED IN ACCORDANCE WITH THE APPROVED EROSION CONTROL PLAN AND SHALL BE OR OTHER FACILITIES. WHERE SURFACE FEATURES (MANHOLES, CATCH BASINS, VALVES, ETC.) ARE UNAVAILABLE OR INCONCLUSIVE. INFORMATION SHOWN INSTALLED PRIOR TO ANY CLEARING, GRADING OR OTHER CONSTRUCTION. MAY BE FROM UTILITY OWNER'S RECORDS AND/QR ELECTRONIC LINE TRACING, THE RELIABILITY OF WHICH IS UNCERTAIN. THE CONTRACTOR SHALL PERFORM TEST EXCAVATIONS OR OTHER INVESTIGATION AS NECESSARY TO VERIFY LOCATION AND CLEARANCES. 4. ALLSLOPES AND DISTURBED AREAS ARE TO BE FERTILIZED, SEEDED AND MULCHED. 3. WHEN THE WORK CROSSES EXISTING UTILITIES, THE EXISTING UTILITIES SHALL BE ADEQUATELY SUPPORTED AND PROTECTED FROM THE DAMAGE DUE TO 5, THE MAXIMUM ALLOWABLE SLOPE IS 2:1 (H ORI ZONTAL:VERTICAL). WHERE REASONABLY OBTAINABLE, LESSER SLOPES OF 3:1 OR BETTER ARE TO BE THE WORK. ALL METHODS FOR SUPPORTING AND MAINTAINING THE EXISTING UTILITIES SHALL BE APPROVED BY THE RESPECTIVE UTILITY COMPANY ACHIEVED. AND/OR THE ENGINEER. CONTRACTOR SHALL EXERCISE CARE TO INSURE THAT THE GRADE AND ALIGNMENT OF EXISTING UTILITIES ARE MAINTAINED AND 6. PAVED, RIP -RAP OR STABILIZATION MAT LINED DITCH MAY BE REQUIRED WHEN IN THE OPINION OF THE COUNTY ENGINEER, OR DESIGNEE, IT IS DEEMED THAT NO JOINTS OR CONNECTIONS ARE DISPLACED. BACKFILL SHALL BE CAREFULLY PLACED AND COMPACTED TO PREVENT FUTURE DAMAGE OR SETTLEMENT TO EXISTING UTILITIES. ANY UTILITIES REMOVED AS PART OF THE WORK, AND NOT INDICATED TO BE REMOVED OR ABANDONED, SHALL BE NECESSARY IN ORDER TO STABILIZE A DRAINAGE CHANNEL. RESTORED USING MATERIALS AND INSTALLATION EQUAL TO THE UTIDTY'S STANDARDS. 7. ALL TRAFFIC CONTROL SIGNS SHALL CONFORM WITH THE VIRGINIA MANUAL FOR UNIFORM TRAFFIC CONTROL DEVICES. 4. CONTRACTOR SHALL NOTIFY LANDOWNERS, TENANTS AND THE ENGINEER A MINIMUM OF 72 HOURS PRIOR TO THE INTERRUPTION OF ANY SERVICES. 8 UNLESS OTHERWISE NOTED ALLCONCRETE PIPESHALL BE REINFORCED CONCRETE PIPE -CLASS 111, SERVICE INTERRUPTIONS SHALL BE KEPT TQ A MINIMUM. 9. ALL EXCAVATION FOR UNDERGROUND PIPE INSTALLATION MUST COMPLY WITH OSHA STANDARDS FOR THE CONSTRUCTION INDUSTRY (29 CFR PART 5. CONTRACTOR TO MAKE ANY NECESSARY ADJUSTMENTS TO ALL UTILITY JUNCTION BOXES, VALVE BOXES, MANHOLES, CLEAN -OUTS, AND OTHER GRADE 1926). RELATED ITEMS IN SIDEWALK, ROADWAY, AND/OR ADJACENT AREAS TO MATCH FINISHED GRADE. COSTS ARE TO BE INCLUDED UNDER THE VARIOUS UNIT BID ITEMS. NO SEPARATE PAYMENT WILL BE MADE. EARTH WORD AND SITE CONDITIONS: 1. EXCEPT AS OTHERWISE SHOWN ON THE PLANS, ALL CUTS AND FILLS SHALL BE NO GREATER THAN 3:1. 2. UNLESS OTHERWISE NOTED ON THE PLANS OR IN THE SPECIFICATIONS, ALL FILL MATERIALS SHALL BE COMPACTED TO 95% OF THEORETICAL MAXIMUM DENSITY AS DETERMINED BY AASHTO T-99 METHOD A, WITHIN PLUS OR MINUS 2% OF OPTIMUM MOISTURE, FOR THE FULL WIDTH AND THE DEPTH OF THE FI LL. 3. THE CONTRACTOR SHALL ADD, CHANGE, OR RELOCATE EROSION AND SEDIMENT CONTROLS AT THE DIRECTION OF THE ALBEMARLE COUNTY E&S INSPECTOR TO THEIR SATISFACTION AT NO ADDITIONAL COST TO THE OWNER. 4. ALLGRADING AND IMPROVEMENTS TO BE CONFINED TO THE PROJECT AREA UNLESS OTHERWISE INDICATED. 5. PROPOSED GRADES SHALL BE FIELD ADJUSTED TO CONFORM TO TH'E INTENT OF THE TYPICAL SECTIONS. A SMOOTH GRADE SHALL BE MAINTAINED FROM THE BASELINE TO THE PROPOSED EDGE OF PAVEMENT OR FACE OF CURB TO PRECLUDE THE FORMING OF FALSE GUTTERS AND/OR PONDING OF WATER ON ALL PAVED SURFACES. 6. CONTRACTOR SHALL MAINTAIN) A SMOOTH GRADE TO THE PROPOSED? EDGE OF PAVEMENT OR FACE OF CURB TO PROVIDE POSITIVE DRAINGE ON ALL PAVED SURFACES. ANY AREAS WHERE WATER IS IMPOUNDED SHALL BE iCORRECTED BY CONTRACTOR AT NO ADDITIONAL COST. POSITIVE DRAINAGE OF ALL ROADWAY AREAS TO THE STORM DRAIN INLETS OR OTHER ACCEPTABLE DRAINAGE CHANNELS AS NOTED ON THE PLANS IS REQUIRED. 7. CONTRACTOR SHALL MAINTAIN EXISTING STREAMS, DITCHES, DRAINAGE STRUCTURES, CULVERT AND FLOWS AT ALL TIMES DURING THE WORK. CONTRACTOR SHALL PAY FOR ALL PERSONAL INJURY AND PROPERTY DAMAGE WHICH MAY OCCUR AS A RESULT OF FAILING TO MAINTAIN ADEQUATE DRAINAGE. 8. ALL PIPES, DI'S AND OTHER STRUCTURES SHALL BE INSPECTED BY THE ENGINEER BEFORE BEING BACKFILLED OR BURIED. THE ENGINEER MAY REQUIRE CONTRACTOR, AT NO ADDITIONAL COST, TO UNCOVER AND RE -COWER SUCH STRUCTURES IF THE HAVE BEEN BACKFILLED OR BURIED WITHOUT SUCH INSPECTION. 9. ALLSTORM CHANNELS, DRAINS, AND SEWER SYSTEMS SHALL BE CLEANED UPON COMPLETION OFTHE PROPOSED WORK. SEDIMENT, CHEMICALS, AND/OR DEBRIS REMOVED FROM THESE SYSTEMS SHALL BE REMOVED AND DISPOSED OF PROPERLY. MAINTENANCE OF TRAFFIC: 1. TEMPORARY STREET CLOSURE PERMIT REQUIRED FOR CLOSURE OF SIDEWALKS, PARKING SPACES AND ROADWAYS AND IS SUBJECT TO APPROVAL BY THE ALBEMARLE COUNTY TRAFFIC ENGINEER. 2. THE VIRGINIA WORK AREA PROTECTION MANUAL AND THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD) SHALL GOVERN ALL TEMPORARY TRAFFIC CONTROL OPERATIONS THROUGHOUT CONSTRUCTION OF THIS PROJECT. ADHERENCE TO APPLICABLE PROVISIONS OF THE MANUAL IS REQUIRED OFTHE CONTRACTOR EVEN THOUGH DETAILED REFERENCETO ALLSIUCH PROVISIONS MAY NOT BE CONTAINED IN THE PLANS. GENERAL NOTES < 3. ALL EXISTING RESIDENTIAL AND COMMERCIAL ENTRANCES SHALL BE MAINTAINED AT ALL TIMES, UNLESS OTHERWISE DIRECTED BY THE ENGINEER. C 4. NO TEMPORARY PAVEMENT MARKING SHALL BE ALLOWED ON THE FI NAL ASPHALT SURFACE COURSE. � 0' 5. THE CONTRACTOR SHALL MAINTAIN ALL LANES OF TRAVEL OPEN FROM 6:30 AM TO 9:00 AM AND 3:00 PM TO 5:00 PM UNLESS DEEMED UNNECESSARY BY 00 THE ENGINEER. SHORT PERIODS OF ONE WAY FLAGGING OPERATIONS MAY BE CONDUCTED OUTSIDE THE HOURS MENTIONED ABOVE. 6. ALLTRAFFIC SIGNALS SHALL BE ADJUSTED AS DEEMED NECESSARY 'BY THE ENGINEER PRIOR TO ANYTRAFFIC CHANGES. C.3 7. WHEN WORK IN THE EXCAVATION AREA IS DISCONTINUED FOR ASHORT PERIOD OF TIME, AS AT NIGHT, THE CONTRACTOR SHALL BACKFILL THE CUT AREAS C ADJACENT TO THE BUSTING PAVEMENT WITH A TILLET OF MATERIAL'. THE FILLET SHALL BE COMPOSED OF THE SAME MATERIAL (EXCAVATION, BORROW, IN THE PRICE BID FOR OTHER BID ITEMS OF < O BASE COURSE, ETC.) ALL COSTS FOR PLACING AND REMOVING THIS FILLET OF MATERIAL SHALL BE INCLUDED n Lu WORK ON THIS PROJECT, AND NO ADDITIONAL CHARGE WILL BE ALLOWED. �.�. 8. EXISTING SURFACE, AGGREGATE BASE AND SUBBASE MATERIAL WHICH WILL BE DEMOLISHED OR OBLITERATED DURING CONSTRUCTION AND WHICH IS d SUITABLE FOR MAINTENANCE OF TRAFFIC AS DETERMINED BY THE ENGINEER, SHALL BE SALVAGED AND UTILIZED FOR MAINTENANCE OF TRAFFIC PRIOR TO E THE USE OF COMMERCIAL MATERIAL. WHEN NOT SPECIFIED AS /A SEPARATE PAY ITEM, THE REMOVAL AND SALVAGING OF EXISTING SURFACES ANDW AGGREGATE BASE AND SUBBASE MATERIAL WILL BE MEASURED AND PAID FOR AS REGULAR EXCAVATION IN ACCORDANCE WITH SECTION 303 OF THE VDOT O m ROAD AND BRIDGE SPECIFICATIONS. < 9. CONSTRUCT ALL INTERSECTIONS AND DRIVEWAYS UNDER TRAFFIC. 10. IF USED, TEMPORARY TRAFFIC BARRIER SERVICE SHALL BE INSTALLED AND REMOVED SO AS NOT TO PRESENT ANY BLUNT END OR HAZARD TO THE MOTORING PUBLIC. 11. CONTRACTOR SHALL NOTIFY TRANSIT PROVIDERS A MINIMUM OF TVWO WEEKS PRIOR TO ANY IMPACT OR DISRUPTION TO REGULAR SERVICE OR STOPS. 12. ALL EXISTING PAVEMENT MARKINGS CONFLICTING WITH PROPOSED CONSTRUCTION PAVEMENT MARKINGS (IF USED) SHALL BE ERADICATED. 13. INSTALLATION AND REMOVAL OF TEMPORARY TRAFFIC CONTROL 'DEVICES SHALL BE IN ACCORDANCE WITH THE SECTION 6G.25 OF THE WORK AREA PROTECTION MANUAL. 14. USE APPROPRIATE SIGNS TO SHIFT PEDESTRIAN TRAFFIC AS NEEDED. 15. CONTRACTOR SHALLASSURE ENDS OF TEMPORARY CONCRETE BARRIER (IF USED) DO NOT OBSTRUCT INTERSECTION SIGHT LINES. WORD AREA PROTECTION AND MAINTENANCE: 1. CLEARING AND GRUBBING SHALL BE CONFINED TO THOSE AREAS NEEDED FOR CONSTRUCTION, AND AS SHOWN IN THE DRAWINGS. 2. DISTURBED AREAS BEYOND THE ROADWAY CURB AND WHERE INDICATED ON THE PLANS SHALL RECEIVE TOPSOIL AS NECESSARY AND AS DIRECTED. SEEDING MIXTURE SHALL BE DETERMINED BYTHE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK SECTION 3.32 3. CONTRACTOR IS PERMITTED TO WORK IN THE PUBLIC RIGHT-OF-WAY AND ANY TEMPORARY OR PERMANENT EASEMENT SHOWN ON THE PLANS. HOWEVER, CONTRACTOR SHALL NOTIFY PROPERTY OWNER(S) FORTY-EIGHT (48) HOURS PRIOR TO WORKING ON ANY PRIVATE PROPERTY TO COORDINATE ACCESS AND TO DETERMINE A STORAGE AREA FOR MATERIALS IF NEEDED. COORDINATION OF ACCESS TO PUBLIC RIGHT-OF-WAY AND STORAGE OF MATERIALS THEREON SHALL BE COORDINATED WITH THE ENGINEER. CONTRACTOR'S FAILURE TO NOTIFY AND COORDINATE WITH PROPERTY OWNERS AND/OR THE ENGINEER MAY RESULT IN DELAYS. NO ADDITIONAL COMPENSATION OR TIME FOR PERFORMANCE WILL BE GIVEN FOR ANY SUCH DELAYS. 4. CONTRACTOR SHALL, AT HIS EXPENSE, MAINTAIN THE WORK SITE IN A CLEAN AND ORDERLY APPEARANCE AT ALL TIMES. ALL DEBRIS AND SURPLUS MATERIAL COLLECTED SHALL BE DISPOSED OF OFF THE WORK SITE IBY CONTRACTOR, AT HIS EXPENSE. 5. EXISTING LAWNS, TREES, SHRUBS, FENCES, UTILITIES, CULVERTS, WALLS, WALKS, DRIVEWAYS, POLES, SIGNS, RIGHT -QF -WAY MONUMENTS, MAILBOXES AND THE LIKE SHALL BE PROTECTED FROM DAMAGE DURING THE. WORK. ANY DAMAGE CAUSED TO SUCH ITEMS SHALL BE REPAIRED OR REPLACED BY CONTRACTOR AT NO ADDITIONAL COST. PROPERTY PINS DISTURBED BY CONTRACTOR THAT ARE NOT SHOWN ON THE PLANS TO BE DISTURBED SHALL BE RESTORED BY LICENSED SURVEYOR AT THE CONTRACTOR'S EXPENSE. 6. MEASURES TO CONTROL EROSION AND SEDIMENT SHALL BE PROWIDED PURSUANT TO AND IN COMPLIANCE WITH CURRENT FEDERAL, STATE AND LOCAL REGULATIONS. THE INFORMATION CONTAINED IN THE CONSTRUICTION PLANS AND/QR APPROVAL OF THE PLANS SHALL IN NO WAY RELIEVE THE CONTRACTOR OR HIS AGENT OF ANY LEGAL RESPONSIBILITY WHICCH MAY BE REQUIRED BY THE CODE OF VIRGINIA OR ANY ORDINANCE ENACTED BY THE CITY OF CHARLOTTESVILLE. CONTRACTOR SHALL PROVIDE THE NECESSARY DIVERSION DITCHES, DIKES, OR TEMPORARY CULVERTS REQUIRED TO PREVENT MUD AND DEBRIS FROM BEING WASHED ONTO THE STREETS OR ADJACENT PROPERTY. CONTRACTOR'S VEHICLES SHALL BE KEPT CLEAN TO PREVENT MUD OR DUST FROM BEING DEPOSITED ON STREETS. NO AREA SHALL BE LEFT DENUDED FOR MORE THAN SEVEN (7) CALENDAR DAYS. 7. CONTRACTOR SHALL CLEAN UP, RESTORE, SEED AND MAINTAIN ALL DISTURBED AREAS IMMEDIATELY UPON COMPLETION OF WORK. TOPSOIL SEED, FERTILIZER AND MULCH SHALL BE PLACED IN ACCORDANCE WITH ALBEMARLE COUNTY STANDARDS ON ALL DISTURBED AREAS. A PERMANENT STAND OF GRASS ADEQUATE TO PREVENT EROSION SHALL BE ESTABLISHED PRIOR TO FINAL ACCEPTANCE. ALL EROSION AND SEDIMENT CONTROLS SHALL BE REMOVED WITHIN 30 DAYS AFTER THE PROJECT IS STABILIZED. (MS -18) 8. FOR FURTHER REQUIREMENTS AND DETAILS OF TREE PRESERVATION, PLANTING, EROSION AND SEDIMENT CONTROL, REFER TO THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK. 9. AN EROSION AND SEDIMENT CONTROL CONTRACTOR CERTIFICATION (E.S.C.C.C) IS REQUIRED FOR ALL LAND DISTURBANCE ACTIVITIES, 10. THE CONTRACTOR SHALL PROPERLY INSTALL AND MAINTAIN EROSIION AND SEDIMENT CONTROLS FOR THE LIFE OF THE PROJECT; AND ROUTINELY CHECK CONTROL DEVICES BEFORE, DURING AND AFTER STORM EVENTS. TOPOGRAPHY SOURCE NOTES: TOPOGRAPHY SOURCE: ACTUAL TOPOGRAPHIC GROUND SURVEY PERFORMED ON OCTOBER 24, 2018 AS REQUIRED BY ALBEMARLE COUNTY. BASIS OF DATUM: HORIZONTAL: INAD-83 VIRGINIA STATE PLANE SOUTH ZONE VERTICAL: NAV(D-88 SUGGESTED CONSTRUCTION SEQUENCING: 1. PROTECT ADJACENT AREAS FROM DAMAGE DUE TO CONSTRUCTION ACTIVITIES. 2. INSTALL PERIMETER CONTROL MEASURES AS INDICATED ON PLANS INCLUDING SAFETY FENCE, SILT FENCE, AND TREE PROTECTION 3. CLEAR AND GRUB EXISTING GROUPED COVER AND DEMOLISH EXISTING ITEMS MARKED FOR DEMOLITION. 4. GRADE SITE TO FINAL GRADES PER; PLANS. 5. FORM AND INSTALL CONCRETE WORK. 6. STABILIZE ALL AREAS AND REPAIR .ANY EROSION AND REMOVE ANY SEDIMENT. 7. INSTALL REMAINING SITE FEATURES. 8, DRESS AND OVERSEER ALL DISTURBED AREAS AS NECESSARY TO AFFECT PERMANENT VEGETATIVE COVER. 9. REMOVE PERIMETER CONTROL MEASURES ONLY UPON APPROVAL OF COUNTY INSPECTOR. 126`2018 t JDA i'1 I E L,;,.`''.r� HYEIt > Lie. No E4 45596 10NA1, A P'E:? DCH SUBMITTAL NO. 3 OJ E0 -r 1800400 LINE + GRADE KIM PM] I L T ti OP DANIEL, 49 IT o Llc,N'o PE -�j45596 ,, A I V- APPR(DV7F4-*" DCH SUBMITTAL NO. 3 P RO-1 ECT 1809400 THE VV'ORK OF LIN 'E + GRADE Si I L T ti OP DANIEL, 49 IT o Llc,N'o PE -�j45596 ,, A I V- APPR(DV7F4-*" DCH SUBMITTAL NO. 3 P RO-1 ECT 1809400 THE VV'ORK OF LIN 'E + GRADE uc CL TH Lu cf) 66 Lli L ]No IPE 45596 xi APPRO-7,7" DCH SUBMITTAL NO. 3 PROJECT 1809400 PROJECT DESCRIPTION: THIS PROJECT CONSISTS OF MAINTENANCE ACTIVITIES ASSOCIATED WITH AN EXISTING CAMPGROUND. MAINTENANCE ACTIVITIES INCLUDE THE CONSTRUCTION OF DRAINAGE IMPROVEMENTS AND SITE GRADING. THE DISTURBANCE AREA ASSOCIATED WITH THIS PROJECT IS ±1.60 AC (69,786 SF). IT IS ANTICIPATED THAT THE WORK WILL START IN NOVEMBER 2018 AND LAST 4 TO 6 MONTHS. EXISTING SITE CONDITIONS: THE SITE CONSISTS MAINLY OF AN EXISTING FLAT FIELD THAT HAS BEEN COMPACTED OVER USE AND NO LONGER DRAINS EFFECTIVELY. RECREATIONAL VEHICLE PARKING SPOTS AND UTILITY CONNECTIONS SURROUND THE FIELD ON THE WEST AND SOUTH SIIDE OF THE FIELD, AND ARE ACCESSED BYAN EXISTING GRAVEL ROAD. TO THE NORTH AND EAST ARE CAMPGROUND AMENITIES AND ASSOCIATED BUILDINGS, ALONG WITH A PAVED ENTRANCE ROAD TO THE EAST. THE SLOPES WITHIN THE PROJECT AREA RANGE FROM 0% TO 2%! ADJACENT AREAS: THE PROPOSED PROJECT IS BORDERED BY EXISTING ACTIVE FARMLAND TO THE WEST AND ADDITIONAL CAMPSITE AND RV AREAS TO THE EAST. TO THE NORTH IS A FAIRLY STEEP SLOPE ABOVE WHICH RUNS ROUTE 250. DIRECTLY TO THE SOUTH OF THE GRAWEL ACCESS ROAD IS THE 100 -YEAR FLOODPLAIN ASSOCIATED WITH STOCKTON CREEK, WHICH RUNS WEST TO EAST. SOME OFTHE EXISTING RV PARKING SITES ARE WITHIN THE LIMITS OFTHE FLOODPLAIN, HOWEVER THESE WILL NOT BE MODIFIED. THE WATER PROTECTION ORDINANCE BUFFER IS CONCURRENT WITH THE LIMITS OFTHE 100 -YEAR FLOODPLAIN. OFF-SITE AREAS: IT IS NOT ANTICIPATED THAT ANY OFF-SITE AREAS WILL BE DISTURBED DURING CONSTRUCTION. THIS WOIRK WILL REQUIRE A NET FILL CONDITION, AND STOCKPILE AREAS ARE LABELED ON THE PLANS. UNSUITABLE MATERIALS RESULTING FROM THE PROPO-SED WORK SHALL BE HAULED FROM THE SITE AND DISPOSED OF AT AN APPROVED DISPOSAL SITE PERMITTED SEPARATELY FROM THIS PROJECT. SOILS: SEE THE USDA SOILS DELINEATION MAP ON THIS SHEET. CRITICAL AREAS: CRITICAL AREAS CONSIST OF THE FLOODPLAIN TO THE SOUTH AND THE HEDGE OF MATURE TREES ALONG THE WESTERN PROPERTY LINE. THE CONTRACTOR SHALL TAKE EXTRA CARE TO PREVENT SEDIMENTATION OR EROSION OFTHE FLOODPLAIN AND THE CRITICAL ROOT ZONES OF TH E TREES. EROSION & SEDIMENT CONTROL MEASURES: REFER TO THIS SHEET FOR A LIST OF ALL PROPOSED EROSION AND SEDIMENT CONTROL MEASURES TO BE USED ON SITE. PERMANENT STABILIZATION: THE SITE WILL BE STABILIZED THROUGH THE USE OF PERMANENT SEEDING, STONE AND RIPRAP, AND LANDSCAPING. SEEDING INFORMATION, DATES AND AMENDMENTS ARE INCLUDED ON THE PLANS. SOILTESTING SHALL BE COMPLETED THE CONTRACTOR TO DETERMINE THE SUITABILITY OF EXISTING SOILS AND THE NEED FOR ANY SOIL AMENDMENTS TO ENSURE THAT PERMANENT SEEDING WILL GROW EFFECTIVELY. STORM WATER RUNOFF CONSIDERATIONS: THE MAJORITY OF STORMWATER RUNOFF DURING CONSTRUCTION WILL BE DIRECTED TO A SEDIMENT TRAP LOCATED AT THE SOUTHEAST CORNER OF THE SITE. CLEAN WATER FROM UP -GRADIENT OF THE SITE SHALL BE DIRECTED AROUND THE SITE TO AN EXISTING CULVERT VIA A DIVERSION DIKE. ANY AND ALL RUNOFF FROM THE SITE SHALL BE DIRECTED TO APPROPRIATE EROSION AND SEDIMENT CONTROLS TO CLEAN WATER BEFORE DISCHARGING TO AN ADEQUATE OUTFALL PROTECTED FROM EROSION AND SEDIMENT. MAINTENANCE: ALL E&S MEASURES SHALL BE INSPECTED REGULARLY AS REQUIRED BY STATE STANDARDS AND MAINTAINED IN GOOD WORKING ORDER. REQUIRED REPAIRS SHALL BE MADE IMMEDIATELY. SEE THE MAINTENANCE NARRATIVE ON THIS SHEET FOR SPECIFIIC MAINTENANCE ITEMS AND INSPECTION TIMES. SEQUENCE OF CONSTRUCTION: 1. CONTRACTOR SHALL CONDUCT A PRE -CONSTRUCTION MEETING WITH THE PLAN APPROVING AUTHORITY PRIOR TO ANY LAND DISTURBANCE OR E&S CONTROL INSTALLATIONS. 2. INSTALL CONSTRUCTION ENTRANCE, PERIMETER CONTROLS AND TREE PROTECTION PRIOR TO ANY DISTURBANCE. 3. INSTALL STORMWATER INLET PROTECTION AROUND EXISTING DRAINAGE STRUCTURES. 4. PROTECT PERMANENT VEGETATION FOR THE DURATION OF THE PROJECT. 5. CONSTRUCT NEW STORM STRUCTURES, IF APPLICABLE, STARTING ATTHE DOWNSTREAM TERMINUS OR TIE-IN. 6. BACKFILL EXCAVATION AND TRENCH AREAS. 7. FOR GRASSY AREAS: INSTALL PERMANENT SEEDING AND MULCH. STABILIZE ALL DISTURBED AREAS. 8. FOR GRAVEL AREAS: RESTORE GRAVEL AFTER TRENCHING AND EXCAVATION OPERATIONS ARE COMPLETE 9. REPAIR ANY EROSION AND REMOVE ANY SEDIMENT. 10. DRESS AND OVER -SEED ALL DISTURBED AREAS AS NECESSARY TO AFFECT PERMANENT VEGETATIVE COVER. STABILIZE ALL REMAINING DISTURBED AREAS WITH TOPSOIL, SEED, AND MULCH ONCE WORK IS COMPLETE. , 11. AFTER FINAL SITE STABILIZATION AND APPROVAL FROM THE APPROPRIATE EROSION AND SEDIMENT CONTROL AUTHORITY, THE SILT FENCE, INLET PROTECTION AND OTHER STABILIZATION MEASURES SHALL BE REMOVED. 38° Z 2r N 38° 2 13" N Hydrologic Soil Group -Albemarle County, Virginia (Misty Mountain Campground) Area of interest (AOI) M C 4D Ashe loam, 15 to 25 B Area of Interest (AOI) CID percent slopes Solis D i 14D Chester loam, 15 to 25 B Soil Rating Polygons percent slopes A El Not rated or not available 116 Chewacla silt loam B/D ND Water Features Streams and Canals 256 Dyke silt loam, 2 to 7 B B percent slopes Transportation - - _----- BID Rails 55B McQueen loam, 2 to 7 C percent slopes 0 C Interstate Highways Interest 0CID US Routes Totals for Area ---- of --- I D Major Roads Not rated or not available focal Roads 0.3 0.0 10.8 0.0 1.6 12.7 N 3B' 2' 27N 38° 2' 13 N 2.3% 0.0% 85.1% 0.0% 12.6% 100.0% EROSION AND SEDIMENT CONTROL MEASURES: UNLESS OTHERWISE INDICATED, ALL EROSION AND SEDIMENT CONTROL PRACTICES LISTED BELOW, AND ANY OTHER EROSION CONTROL PRACTICES REQUIRED SHALL BE CONSTRUCTED AND MAINTAINED IN ACCORDANCE WI1TH THE MINIMUM STANDARDS AND SPECIFICATIONS OFTHE LATEST EDITION OF THE VIRGINIA EROSION AND SEDIMENT CONTROL REGULATIONS AND VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK, OR ALBEMARLE COUNTY STANDARDS, WHICHEVER ARE MORE STRINGENT, TEMPORARY STONE CONSTRUCTION ENTRANCE - 3.02 A PAVED OR STABILIZED STONE PAD WITH A FILTER FABRIC UNDERLINER' LOCATED AT POINTS OF VEHICULAR INGRESS AND EGRESS ON A CONSTRUCTION SITE. CONSTRUCTION ROAD STABILIZATION - 3.03 TH E TEMPORARY STABILIZATION OF ACCESS ROADS, SUBDIVISION ROADS, (PARKING AREAS, AND OTHER ON-SITE VEHICLE TRANSPORTATION ROUTES WITH STONE IMMEDIATELY AFTER GRADING. SILT FENCE - 3.05 A TEMPORARY SEDIMENT BARRIER CONSISTING OF A SYNTHETIC FILTER FABRIC STRETCHED ACROSS AND ATTACHED TO SUPPORTING POSTS AND ENTRENCHED. CULVERT INLET PROTECTION - 3.08 ASEDIMENT FILTER LOCATED AT THE INLET TO STORM SEWER CULVERTS. TEMPORARY DIVERSION DIKE - 3.09 ATEM PORARY RIDGE OF COMPACTED SOIL CONSTRUCTED AT THE TOP OR IBASE OF ASLOPING DISTURBED AREA. TEMPORARY SEDIMENT TRAP - 3.13 ATEMPORARY PONDING AREA FORMED BY CONSTRUCTING AN EARTHEN EIMBANKMENT WITH ASTONE OUTLET. OUTLET PROTECTION - 3.18 A PERMANENT OUTLET PROTECTION MEASURE THAT CONSISTS OF STRUiCTURALLY LINED APRONS OR OTHER ACCEPTABLE ENERGY DISSIPATING DEVICES PLACED AT THE OUTLETS OFALL PIPES OR PAVED CHANNEL SECTIONS. TEMPORARY SEEDING - 3.31 THE ESTABLISHMENT OFA TEMPORARY VEGETATIVE COVER ON DISTURBED AREAS THAT WILL NOT BE BROUGHT TO FINAL GRADE FOR PERIODS OF 30 DAYS TO ONEYEAR BY SEEDING WITH APPROPRIATE RAPIDLY -GROWING ANNUAL_ PLANTS. THIS MEASURE WILLALSO FUNCTION AS DUST CONTROL FOR THE SITE. PERMANENT SEEDING - 3.32 THE ESTABLISHMENT OF PERENNIAL VEGETATIVE COVER BY PLANTING SEED ON ROUGH -GRADED AREAS THAT WILL NOT BE BROUGHT TO FINAL GRADE FOR A YEAR OR MORE OR WHERE PERMANENT VEGETATIVE COVER IS NEEDED ON FINE -GRADED AREAS IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL TECHNICAL BULLETIN NO. 4: NUTRIENT MANAGEMENT FOR DEVELOPMENT SITES. TREE PRESERVATION & PROTECTION - 3.38 PROTECTION OF DESIRABLE TREES FROM MECHANICALAND OTHER INJURE DURING LAND DISTURBING AND CONSTRUCTION ACTIVITY. GENERAL EROSION AND SEDIMENT CONTROL NOTES: ES -1: UNLESS OTHERWISE INDICATED, ALL VEGETATIVE AND STRUCTUIRAL EROSION AND SEDIMENT CONTROL PRACTICES WILL BE CONSTRUCTED AND MAINTAINED ACCORDING TO MINIMUM STANDARDS AND SPECIFICATIONS OF THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK AND VIRGINIA REGULATIONS VR 625-02-00 EROSION AND SEDIMENT CONTROL REGULATIONS (4VAC50-30). ES -2: THE PLAN -APPROVING AUTHORITY MUST BE NOTIFIED ONE WEEK PRIOR TO THE PRE -CONSTRUCTION CONFERENCE, ONE WEEK PRIOR TO THE COMMENCEMENT OF LAND DISTURBING ACTIVITY, AND ONE WEEK PRIOR TO THE FINAL INSPECTION. THE NAME OF THE RESPONSIBLE LAND DISTURBER MUST BE PROVIDED TO THE PLAN -APPROVING AUTHORITY PRIOR TO ACTUAL ENGAGEMENT IN THE LAND -DISTURBING ACTIVITYSHOWN ON THE APPROVED PLAN. IF THE NAME IS NOT PROVIDED PRIOR TO ENGAGING IN THE LAND -DISTURBING ACTIVITY, THE PLAN'S APPROVAL WILL BE REVOKED. ES -3: ALL EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE PLACED PRIOR TO ORAS SOON AS THE FIRST STEP IN CLEARING ES -4: A COPY OF THE APPROVED EROSION AND SEDIMENT CONTROL PLAN SHALL BE MAINTAINED ON THE SITE AT ALLTIMES. ES -5: PRIOR TO COMMENCING LAND DISTURBING ACTIVITIES IN AREAS OTHER THAN INDICATED ON THESE PLANS (INCLUDING, BUT NOT LIMITED TO OFF SITE BORROW OR WASTED AREAS), THE CONTRACTOR SHALL SUBMIT A SUPPLEMENTARY EROSION CONTROL PLAN TO THE OWNER FOR REVIEW AND APPROVAL BY THE PLAN APPROVING AUTHORITY. ES -6: THE CONTRACTOR IS RESPONSIBLE FOR INSTALLATION OF ANY ADDITIONAL EROSION CONTROL MEASURES NECESSARY TO PREVENT EROSION AND SEDIMENTATION AS DETERMINED BY THE PLAN APPROVING AUTHORITY. ES -7: ALL DISTURBED AREAS ARE TO DRAIN TO APPROVED SEDIMENT CONTROL MEASURES AT ALL TIMES DURING LAND DISTURBING ACTIVITIES AND DURING SITE DEVELOPMENT UNTIL FINAL STABILIZATION IS ACHIEVED, AFTER WHICH, UPON APPROVAL OF THE PLAN -APPROVING AUTHORITY, THE CONTROLS SHALL BE REMOVED. TRAPPED SEDIMENT AND THE DISTURBED SOIL AREAS RESULTING FROM THE REMOVAL OF TEMPORARY MEASURES SHALL BE PERMANENTLY STABILIZED TO PREVENT FURTHER EROSION AND SEDIMENTATION. ES -8: DURING DEWATERING OPERATIONS, WATER WILL BE PUMPED INTO AN APPROVED FILTERING DEVICE. ES -9: THE CONTRACTOR SHALL INSPECT ALL EROSION CONTROL MEASURES AT LEAST EVERY 2 WEEKS AND IMMEDIATELY AFTER EACH RUNOFF -PRODUCING RAINFALL EVENT. ANY NECESSARY REPAIRS OR CLEANUP TO MAINTAIN THE EFFECTIVENESS OF THE EROSION CONTROL DEVICES SHALL BE MADE IMMEDIATELY. ES -10: THE CONTRACTOR IS RESPONSIBLE FOR THE DAILY REMOVAL OF SEDIMENT THAT HAS BEEN TRANSPORTED ONTO A PAVED OR PUBLIC ROAD SURFACE. ES -11: SEEDING OPERATIONS SHALL BE INITIATED WITHIN 7 DAYS AFTER; REACHING FINAL GRADE OR UPON SUSPENSION OF GRADING OPERATIONS FOR AN ANTICIPATED DURATION OF GREATER THAN 30 DAYS OR UPON COMPLETION OF GRADING OPERATIONS FOR A SPECIFIC AREA. ES -12: THE CONTRACTOR SHALL BE RESPONSIBLE FOR PREVENTING SURFACE AND AIR MOVEMENT OF DUST FROM EXPOSED SOILS WHICH MAY PRESENT HEALTH HAZARDS, TRAFFIC SAFETY PROBLEMS, OR HARM ANIMAL. OR PLANT LIFE - ES -13: A VSMP IS REQUIRED FOR PROJECTS DISTURBING 2,500 SQUARE FEET OR GREATER IN A DESIGNATED CHESAPEAKE BAY PRESERVATION AREA (CBPA) OR ONE ACRE OR GREATER OUTSIDE THE CBPA. FOR MORE INFORMATION VISIT THE VIRGINIA STORMWATER MANAGEMENT PROGRAM PERMITTING WEB PAGE AT: http://www.deq.virginia.gov/Programs/Water/StorrrnwaterManagement.aspx MAINTENANCE: IN GENERAL, ALL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE CHECKED DAILY AND AFTER EACH RAINFALL EVENT GREATER THAN 0.25 INCHES. MEASURES SHOULD BE CLEANED AND REPAIRED ACCORDING TO) THE FOLLOWING SCHEDULE AND THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK. THE FOLLOWING WILL BE CHECKED IN PARTICULAR: 1. THE CONSTRUCTION ENTRANCES AND CONSTRUCTION ROAD STABILIZATION AREAS SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOW OF MUD ONTO PUBLIC RIGHTS-OF-WAY THROtUGH PERIODIC TOP DRESSING WITH ADDITIONAL STONE AND/OR WASHING AND REWORKING OF EXISTING STONE. 2. SEDIMENT DEPOSITS SHALL BE REMOVED FROM SILT FENCE AFTER EACH RAINFALL. UNDER NO CIRCUMSTANCES SHALL DEPOSITS BE ALLOWED TO ACCUMULATE ABOVE HALF TH E HEIGHT OF THE FENCE. DAMAGED OR; UNDERCUT SILT FENCE SHALL BE REPAIRED IMMEDIATELY. SHOULD SILT FENCE BECOME INEFFECTIVE OR REACH THE END OF THE EXPECTED USEABLE LIFE, FABRIC SHALL BE REPLACED IMMEDIATELY. UPON SILT FENCE REMOVAL, DRESS ANY SEDIMENT DEPOSITS TO CONFORM WITH EXISTING GRADE AND SEED. 3. INLET PROTECTION SHALL BE CHECKED REGULARLY FOR SEDIMENT. IF EXCESSIVE SEDIMENT IS PRESENT, OR IF EXCESSIVE PONDING OCCURS AFTER RAINFALL, THE STONE SHALL BE PULLED AWAY AND CLEANED OR REPLACED. 4. STONE USED IN CULVERT INLET PROTECTION SHALL BE INSPECTED REGULARLY FOR CLOGGING AND REPLACED AS NEEDED TO MAINTAIN FULL FUNCTIONALITY. UNDER NO CIRCUMSTANCES SHALL SEDIMENT BE ALLOWED TO ACCUMULATE ABOVE ONE-HALF OF THE HEIGHT OF THE INLET PROTECTION. ACCUMULATED SEDIMENT SHALL BE REMOVED AND UPSTREAM AREAS PERMANENTLY STABILIZED BEFORE THIS CONTROL IS REMOVED. 5. CHECK DAMS SHALL BE INSPECTED REGULARLY TO ENSURE THE CENTER OF THE DAM IS LOWER THAN THE EDGES, SEDIMENT SHALL BE REMOVED WHEN IT REACHES ONE HALF THE HEIGHT OFTHE DAM. 6. ANY SOIL WITHIN TREE PROTECTION AREAS THAT IS INADVERTENTLYCOMPACTED SHALL BE AERATED WITH AN IRON BAR EVERY 18 INCHES TO A DEPTH OF 12 INCHES. PHYSICAL DAMAGE TO TREES SHALL BE REPAIRED AS OUTLINED IN THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK SECTION 3.38. TREES THAT ARE STRESSED OR DAMAGED SHALL RECEIVE AN APPROPRIATE APPLICATION OF FERTILIZER TO AID RECOVERY. 7. ALL SEEDED AREAS WILL BE CHECKED REGULARLY TO SEE THAT A GOOD STAND IS MAINTAINED. AREAS SHOULD BE FERTILIZED AND RESEEDED AS NEEDED. 8. ALL TEMPORARY EROSION AND SEDIMENT MEASURES SHALL BE DISPOSED OF WITHIN THIRTY (30) DAYS AFTER FINAL SITE STABILIZATION IS ACHIEVED AND VEGETATION IS ESTABLISHED. FINAL SITE STABILIZATION SHALL BE APPROVED BY THE OWNER AFTER THE INSPECTOR HAS DETERMINED THAT THE SITE IS STABILIZED. ALBEMARLE COUNTY GENERAL E&S NOTES: 1. THE PLAN APPROVING AUTHORITY MUST BE NOTIFIED ONE WEEK PRIOR TO THE PRE -CONSTRUCTION CONFERENCE, ONE WEEK PRIOR TO THE COMMENCEMENT OF LAND DISTURBIING ACTIVITY, AND ONE WEEK PRIOR TO THE FINAL INSPECTION. 2. ALL EROSION AND SEDIMENT CONTROL MEASURES WILL BE CONSTRUCTED AND MAINTAINED ACCORDING TO MINIMUM STANDARDS AND SPECIFICATIONS OF THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK AND VIRGINIA REGULATIONS VR 625-02-00 EROSION AND SEDIMENT CONTROL REGULATIONS. 3. ALL EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE PLACED PRIOR TO OR AS THE FIRST STEP IN CLEARING. 4. A COPY OF THE APPROVED EROSION SAND SEDIMENT CONTROL PLAN SHALL BE MAINTAINED ON THE SITE AT ALL TIMES. 5. PRIOR TO COMMENCING LAND DISTURBING ACTIVITIES IN AREAS OTHER THAN INDICATED ON THESE PLANS (INCLUDING, BUT NOT LIMITED TO, OFF-SITE BORROW OR WASTE AREAS), THE CONTRACTOR SHALL SUBMIT SUPPLEMENTARY EROSION CONTROL PLAN TO THE OWNER FOR REVIEW AND APPROVAL BY THE PLAN APPROVING AUTHORITY. 6. THE CONTRACTOR IS RESPONSIBLE FOR INSTALLATION OF ANY ADDITIONAL EROSION CONTROL MEASURES NECESSARY TO PREVENT EROSION AND SEDIMENTATION AS DETERMINED BYTHE PLAN APPROVING AUTHORITY. 7. ALL DISTURBED AREAS ARE TO DRAIN TO APPROVED SEDIMENT CONTROL MEASURES AT ALL TIMES DURING LAND DISTURBING ACTIVITIES AND DURING SITE DEVELOPMENT UNTIL FINAL STNBILIZATION IS ACHIEVED. 8. DURING DEWATERING OPERATIONS, (WATER WILL BE PUMPED INTO AN APPROVED FILTERING DEVICE. 9. THE CONTRACTOR SHALL INSPECT ALL EROSION CONTROL MEASURES PERIODICALLY AND AFTER EACH RUNOFF -PRODUCING RAINFALL EVENT. ANY NECESSARY REPAIRS OR CLEANUP TO MAINTAIN THE EFFECTIVENESS OF THE EROSION CONTROL DEVICES SHALL BE MADE IMMEDIATELY. 10. ALL FILL MATERIALTO BE TAKEN FROM AN APPROVED, DESIGNATED BORROW AREA. 11. ALL WASTE MATERIALS SHALL BE TAKEN TO AN APPROVED WASTE AREA. EARTH FILL SHALL BE INERT MATERIALS ONLY, FREE OF ROOTS, STUMPS, WOOD, RUBBISH, AND OTHER DEBRIS. 12. BORROW OR WASTE AREAS ARE TO BE RECLAIMED WITHIN 7 DAYS OF COMPLETION PER ZONING ORDINANCE SECTION 5.1.28. 13. ALL INERT MATERIALS SHALL BE TRANSPORTED IN COMPLIANCE WITH SECTION 13-301 OF THE CODE OF ALBEMARLE. 14. BORROW, FILL OR WASTE ACTIVITY INVOLVING INDUSTRIAL -TYPE POWER EQUIPMENT SHALL BE LIMITED TO THE HOURS OF 7:00AM TO 9:OOPM. 15. BORROW, FILLOR WASTE ACTIVITY SHALLBE CONDUCTED IN ASAFE MANNER THAN MAINTAINS LATERAL SUPPORT, OR ORDER TO MINIMIZE ANY HAZARD TO PERSONS, PHYSICAL DAMAGE TO ADJACENT LAND AND IMPROVEMENTS, AND DAMAGE TO ANY PUBLIC STREET BECAUSE 0 SLIDES, SINKING, OR COLLAPSE. 16. THE DEVELOPER SHALL RESERVE THE RIGHT TO INSTALL, MAINTAIN, REMOVE OR CONVERT TO PERMANENT STORMWATER MANAGEMENT FACILITIES WHERE APPLICABLE ALL EROSION CONTROL MEASURES REQUIRED BY THIS PLAN REGARDLESS OF THE SALE OF ANY LOT, UNIT, BUILDING OR OTHER PORTION OF THE PROPERTY. 17. TEMPORARY STABILIZATION SHALL BE TEMPORARY SEEDING AND MULCHING. SEEDING IS TO BE AT 75 LBS/ACRE AND IN THE MONTHS OF SEPTEMBER TO FEBRUARY TO CONSIST A 50/50 M IX OF ANNUAL RYEGRASS AND CEREAL WINTER RYE, OR IN MARCH AND APRIL TO CONSIST OF ANNUAL RYE, OR MAY THROUGH AUGUST TO CONSIST OF GERMAN MILLET. STRAW MULCH IS TO BE APPLIED AT 8OLBS/1OOSF. ALTERNATIVES ARE SUBJECT TO APPROVED BY THE COUNTY EROSION CONTROL INSPECTOR - 18. PERMANENT STABILIZATION SHALL BIE LIME AND FERTILIZER, PERMANENT SEEDING, AND MULCH. AGRICULTURAL GRADE LIMESTONE SHALL BE APPLIED AT 90LBS/1OOOSF, INCORPORATED INTO THE TOP 4-6 INCHES OF SOIL. FERTILIZER SHALL BE APPLIED AT 1OOOLBS/ACRE AND CONSIST OF A 10-20-10 NUTRIENT MIX. PERMANENT SEEDINtG SHALL BE APPLIED AT 18OLBS/ACRE AND CONSIST OF 95% KENTUCKY 31 OR TALL FESCUE AND 0-5% PERENNIAL RYEGRASS OR KENTUCKY BLUEGRASS. STRAW MULCH IS TO BE APPLIED AT 80LBS/100SF. ALTERNATIVES ARE SUBJECT TO APPROVED BY THE COUNTY EROSION CONTROL INSPECTOR. 19. MAINTENANCE: ALL MEASURES ARE TO BE INSPECTED WEEKLY AND AFTER EACH RAINFALL. ANY DAMAGE OR CLOGGING TO STRUCTURAL MEASURES IS TO BE REPAIR IMMEDIATELY. SILT TRAPS ARE TO BE CLEANED WHEN 50% OF THE WET STORAGE VOLUME IS FILLED WITH SEDIMENT. ALLSEEDED AREAS ARE TO BE RESEEDED WHEN NECESSARY TO ACHIEVE A GOOD STAND OF GRASS. SILT FENCE AND DIVERSION DYKES WHICH ARE COLLECTING SEDIMENT TO HALFTHEIR HEIGHT MUST BE GLEANED AND REPAIRED IMMEDIATELY. 20. ALL TEMPORARY EROSION AND SEDIIMENT CONTROL MEASURES ARE TO BE REMOVED WITHIN 30 DAYS OF FINAL SITE STABILIZATION, WHEN MEASURES ARE NO LONGER NEEDED, SUBJECT 70 APPROVAL BY THE COUNTY EROSION CONTROL INSPECTOR. MANAGEMENT STRATEGIES: THE FOLLOWING SEQUENCE OF EVENTS AND EROSION CONTROL MEASURES SHALL BE INCORPORATED INTO THE CONSTRUCTION SCHEDULE FOR THIS PROJECT AND SHALL APPLY TO ALLCONSTRUCTION ACTIVITIES WITHIN PROJECT LIMITS. 1. CONSTRUCTION WILL BE SEQUENCED SO THAT TRENCHING AND EXCAVATION OPERATIONS CAN BEGIN AND END AS QUICKLY AS POSSIBLE. 2. SOIL STOCKPILES WILL BE PROTECTED WITH APPROPRIATE EROSION CONTROL MEASURES. STOCKPILES REMAINING FOR MORE THAN 14 DAYS SHALL BE TEMPORARILY SEEDED. 3. THE CONTRACTOR SHALL USE APPROPRIATE CONSTRUCTION METHODS TO MINIMIZE DISTURBANCE ALONG MANAGED SLOPES AND EXISTING STEEP SLOPES WHERE EROSION HAZARD IS HIGH. 4. ALL STORM SEWER INLETS THAT ARE MADE OPERABLE DURING CONSTRUCTION SHALL BE PROTECTED WITH INLET PROTECTION SO THAT SEDIMENT -LADEN WATER CANNOT ENTER THE CONVEYANCE SYSTEM. 5. PREVIOUSLY GRASSED AREAS SHALL BE SEEDED AND STRAW MULCHED IMMEDIATELY AFTER TRENCHING OPERATION. 6. ALLTHE EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSPECTED 48 HOURS AFTER EVERY RAIN EVENT GREATER THAN 0.25 INCHES AND EVERY 5 DAYS EVEN IF A RAIN EVENT DOES NOT OCCUR. REQUIRED REPAIRS SHALL BE MADE AS NEEDED TO MAINTAIN DESIGNED STANDARD. 7. PERMANENT VEGETATION SHALL NOT BE CONSIDERED ESTABLISHED UNTIL A GROUND COVERED IS ACHIEVED THAT IS UNIFORM, MATURE ENOUGH TO SURVIVE AND WILL INHIBIT EROSIOIN. 8. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL THE INSTALLATION AND MAINTENANCE OF ALL EROSION AND SEDIMENT CONTROL PRACTICES. MINIMUM STANDARD COMPLIANCE: MS -1 HAVE TEMPORARY AND PERMANENT STABILIZATION BEEN ADDRESSED IN THE NARRATIVE? HAVE THE PROPOSED PRACTICES BEEN SHOWN ON THE PLAN? YES SEED SPECIFICATION YES MULCHING YES GRAVEL YES MS -2 HAS STABILIZATION OF SOIL STOCKPILES BEEN ADDRESSED IN THE NARRATIVE? YES. IS SEDIMENT TRAPPING MEASURES PROVIDED? YES. MS -3 HAS MAINTENANCE OF PERMANENT STABILIZATION BEEN ADDRESSED? YES. MS -4 ARE SEDIMENT TRAPPING FACILITIES TO BE CONSTRUCTED AS A FIRST STEP IN LDA? YES. MS -5 HAS STABILIZATION OF EARTHEN STRUCTURES BEEN ADDRESSED? YES. MS -6 ARE SEDIMENT BASINS REQIUI RED WHERE NEEDED? MS -7 HAS STABILIZATION OF CUTAND FILL SLOPES BEEN ADEQUATELY ADDRESSED? YES. MS -8 ARE PAVED FLUMES, CHANNIELS OR SLOPED DRAINS REQUIRED WHERE NECESSARY? MS -9 HAS STABILIZATION THROUGH SURFACE ROUGHENING OR OUTLET PROTECTION BEEN ADDRESSED? YES. MS -10 IS ADEQUATE INLET PROTECTFION REQUIRED ON ALL OPERATIONAL STORM SEWER INLETS? YES - MS -11 HAS MAINTENANCE OF PERMANENT STABILIZATION BEEN ADDRESSED? YES. MS -12 ARE IN STREAM CONSTRUCTION MEASURES REQUIRED SO THAT CHANNEL DAMAGE IS MINIMIZED? MS -13 ARE TEMPORARY STREAM CROSSINGS OF NON -ERODIBLE MATERIAL REQUIRED WHERE APPLICABLE? MS -14 THIS REGULATION REQUIRES THAT ALL APPLICABLE FEDERAL, STATE AND LOCAL REGULATIONS PERTAINING TO WORKING IN OR CROSSING LIVE WATERCOURSES BE FOLLOVr'VED. MS -15 HAS RESTABILIZATION OFAR2EAS SUBJECT TO INSTREAM CONSTRUCTION BEEN ADEQUATELY ADDRESSED? MS -16 IS STABILIZATION OF UTILITY' TRENCHES ADDRESSED? YES. MS -17 IS THE TRANSPORT OF SOIL AND MUD ONTO PUBLIC ROADWAYS PROPERLY CONTROLLED? (I.E. CONSTRUCTION ENTRANCES, WASH RACKS, DAILY CLEANING OF ROADWAYS, TRANSPORT OF SEDIMENT TO ATRAPPING FACILITY) YES. MS -18 HAS THE REMOVAL OFTEMP'ORARY PRACTICES BEEN ADDRESSED? YES. HAS MAINTENANCE OF PRACTICES BEEN ADDRESSED? (I.E. REPAIR OF STRUCTURES AND REMOVAL OF ACCUMULATED SEDIMENT) YES. MS -19 ARE PROPERTIES AND WATERWAYS DOWNSTREAM FROM DEVELOPMENT ADEQUATELY PROTECTED FROM EROSION AND SEDIMENT DEPOSITION DUE TO INCREASES IN PEAK STORM WATER RUNOFF? YES. Pon O �26 0 t% U I Y E R ; t'q. No.,RE 45596 NALC� � Va, DCH U MIT T AL NO. 3 I° OJ F.CT 1809400 T 0 gg VV PKK C1.2 CONSTI RI.JCTION' -3" '&k1 -2A ASPHALT TOP DDURSE 29 2% STONE CON III' 1"R' tj f"I, I ON ACCESS '-6 WN, 21A ArYCRILGAT-E DA5E PROAL //--'A5PHALT PAVED F'VASFMACK 12% EXIS:]N,',G P1,',jFMFNT I T—POS1PV1-' DRAINA(3E *WWST" EXTEEND FULL IF W �:'T[ 1 10 SEL)IN1,ENT OF INGRESS AND, EGRESS TRAPP�N(; 5"FN[CE OPERATION PLAL4 F� 0' DN,'%INAGE TO TRAIPPNG DBVICE FII.- TER CLQTH--� SECTION A—A A n1irilluni water tap of I lilich 11111st be installed Nvith a iiiiihimin I inch ballcock slititoff vahre "11pPb'*g a Wash hose NAth a fliallietel of 1.5 inclies for adequate coll;,tailt pressure. Wa, -iied away froill the entrance to an sh water rritist be cal apl)ro,ved settli- area to renio-.Fe sedhiient. All sedhiietit,Ball bepre6retite(Ifi-oiii entering storm drains, ditches or PAVED WASH RACK NO SCALE (:D CONSTRUCTION ENTRANCE WITH WASH RACK CONSTRUCTION OF A SILT FENCE (WITHOUT WIRE SUPPORT.) 1. SET THE STAKES. 2. EXCAVATE A 4�'X 4" TRENCH UPSLOPE ALONG THE LINE OF STAKES. 6' MAX. — --- ------- --- FLOW 3. STAPLE FILTER MATERIAL TO STAKES AND EXTEND IT INTO THE TRENCH. FLOW 4" 4. BACKFILL AND COMPACT THE EXCAVAwED SOIL, SHEET FLOW INSTALLATION (PERSPECTIVE VIEW) POINTS A SHOULD BE HIGHER THAN POINT B. DRAINAGEWAY INSTALLATION (FRONT ELEVATION) Source: Adapted from Installation of Straw and Fabric Filter Barriers for Sediment Control Sherwood and Wyant SILT FENCE TEMPORARY DIVERSION DIKE Compacted Soil 18" min. E Hary 4.5' min. Source: Va. DSWC DIVERSION DIKE Plate 3.05-2 Source: Va, DSWC Plate 338-2 TREE PROTECTION FENCING TEMPORARY SEDIMENT TRAP i 1' VARIABLE* I ORIGINAL GROUND ELEV. *SEE PLATE 3.13-1 67 CU. YD./ACRE 1.01 VARIABLE � , I 67 CU, YD./ACRE (EXCAVATED) 41 MAX. FILTER CLOTHORIGINAL GROUND \ ELEV. COARSE AGGREGATE CLASS I RIPRAP CROSS SECTION OF. OUTLET CLASS I RIPRAP LENGTH (IN FEET) = 6 X DRAINAGE AREA (IN AC.) DIVERSION DIKE COARSE AGGREGATE SHALL BE VDOT #3, #357 OR #5 OUTLET (PERSPECTIVE VIEW) Plate 3.09-1 Source: Va. DSWC Plate 3.13-2 SEDIMENT TRAP DETAILS AND CALCULATIONS SILT FENCE CULVERT INLET PROTECTION ENDWALL ------------------------------------- T -J TOE OF FILL L. CULVERT ----------- --1 ------- I --------- TOE OF FILL SILT FENCE * DISTANCE IS 6' MINIMUM IF FLOW LIS TOWARD EMBANKMENT FLOW OPTIONAL STONE COMBINATION FLOW Ffi VDOT #3, #357 OR #5 COARSE AGGREGATE TO REPLACE SILT FENCE IN - HORSESHOE - WHEN HIGH VELOCITY OF FLOW IS EXPECTED Source: Adapted from VDOT Standard Sheets and Va. DSWC CULVERT INLET PROTECTION EM BAN KM ENT ELEV. = 623.76 DRY STORAGE ELEV. 622.76 0?' 0, U ' 403 WET STORAGE ELEV, 621A2 Qe F BOTTOM E LEV. = 6 19.7 2 STONE OUTLET AS SHOWN ON SEDIMENT TRAP DETAIL STONE OUTLET TO FUNCTION AS I RIPRAP Plate 3.08-1 PHASE I PROP. GRADE EX. GRADE I NV- 621.34 -V— PROPOSED PIPES INSTALLED IN ULTIMATE CONDITION (INSTALL WITH PHASE I ESC) 2111 1) J I a El NN P CULVERT INLET PROTECTION. IEL INSTALL IN HORSESHOE SHAPE AS N I-) SHOWN ON PLANS. C. U H Y I-: R.. 11 Ic* Na. 5596 ST -1 Drainage Area (Ac) Required Storage Elevations] A - I AI CONTOUR Iner. Incr. Cum. 2.42 324 C A P P R 57�- 0W, DCH L W Area Vol. Vol. Vol. 162 Wet Storage 621.42 SUBMITTAL NO. 3 Elevation (Ft) (Ft) (SF) (CF) (CY) (C 162 Dry Storage 622.76 619.72 84 26 2147 0 0 0 Min. Top of 623.76 PROJECT 1809400 620.00 85 27 2272 619 23 23 embankment T Fi E 'Oil 0 R K 0 F 621.00 89 31 2734 2503 93 116 WET L i N E 622,00 93 35 3222 2978 110 226 DRY Embankment 50% 623.00 1 97 1 38 3734 34781 129 1 355 Slope (%) 624.00 11011 42 F427214003 148 503 Cls3 • ■ NN P CULVERT INLET PROTECTION. IEL INSTALL IN HORSESHOE SHAPE AS N I-) SHOWN ON PLANS. C. U H Y I-: R.. 11 Ic* Na. 5596 ST -1 Drainage Area (Ac) Required Storage Elevations] A - I AI CONTOUR Iner. Incr. Cum. 2.42 324 C A P P R 57�- 0W, DCH L W Area Vol. Vol. Vol. 162 Wet Storage 621.42 SUBMITTAL NO. 3 Elevation (Ft) (Ft) (SF) (CF) (CY) (C 162 Dry Storage 622.76 619.72 84 26 2147 0 0 0 Min. Top of 623.76 PROJECT 1809400 620.00 85 27 2272 619 23 23 embankment T Fi E 'Oil 0 R K 0 F 621.00 89 31 2734 2503 93 116 WET L i N E 622,00 93 35 3222 2978 110 226 DRY Embankment 50% 623.00 1 97 1 38 3734 34781 129 1 355 Slope (%) 624.00 11011 42 F427214003 148 503 Cls3 213 IS - L fl' I E+G 0 of kk 11 IN A Lie. O. 5596 m APPRO'q ' DCH SU BM ITT AL- NO, 3 P ROYEZCT 1809400 T H E W 0 R K 0 F LINE + GRADE it 0 of kk 11 IN A Lie. O. 5596 m APPRO'q ' DCH SU BM ITT AL- NO, 3 P ROYEZCT 1809400 T H E W 0 R K 0 F LINE + GRADE 11 A 100 -YEAR FLOODPLAIN WATER PROTECTION ORDINANCE BUFFER EX. GRAVEL ROAD REGRADED FIELD X. GRADE PROP. GRADE I 7`� LOPE __- ----- 1.5%S 77 ......... tDITCH CENTERLINE SITE SECTION III = 51 5 10 100 -YEAR FLOODPLAIN WATER PROTECTION ORDINANCE BUFFER EX. GRAVEL ROAD G 5 2, _000- RRv SITE SECTION J-11 = 51 5 10 COMPACTED BERM - r, n u r. k_1 L_ EX. GRADE REGRADED FIELD DITCH CENTERLINE 01 FINISHED GRADE 6" VDOT 21A NON -WOVEN GEOTEXTILE FILTER FABRIC r- COMPACTED SUBGRADE GRAVEL ROAD SECTION SHAPE TO BE BEVELED WITH MORTAR DO NOT BEVEL INVERT NOTES: 1. I'H" MAY BE REDUCED UNTIL "X" REACHES A MINIMUM OF 4" WHERE ENDWALL WOULD PROTRUDE ABOVE SHOULDER LINE. N NO CASE SHALL TOP OF ENDWALL PROJECT ABOVE FILL SLOPE, DITCH SLOPE, OR SHOULDER. 2. THIS ITEM MAY BE PRECAST OR CAST IN PLACE. 3. ALL CAST IN PLACE CONCRETE TO BE CLASS A3. FOR PRECAST SEE SHEET 101,02. 4. THIS STANDARD TO BE USED WITH STRAIGHT CROSSINGS AND ALL SKEWS(O* TO 45'). SITE SECTION III = 51 5 10 EW -MA C S. BEVEL EDGE IS REQUIRED ON THE HEADWALL AT THE INLET END OF THE CULVERT (WHERE THE FLOW ENTERS THE CULVERT). 7. HEADWALL AT THE OUTLET END OF THE CULVERT MAY BE EITHER SQUARE EDGE OR BEVEL EDGE, S. ON SHALLOW FILLS, WHERE ENDWALLS ARE 1 1 OR LESS BELOW SHOULDER LINE, THE TOP OF THE ENDWALL SHALL BE CONSTRUCTED PARALLEL TO THE GRADE OF THE ROAD. Gii. Y4" CHAMFER MAY BE PROVIDED ON ALL EDGES AT MANUFACTURER'S OPTION. 5. HEADEZ daEI C WITH FN ­V I[RbKwBiTk4NW A ONLY I ASSOCIATION TOP OF FILL DIAMETER OF PIPE CULVERT ENDWALL FOR ELLIPTICAL 12" 15" 18" 21" OR 24"27" OR 2 A 0'-6" 0`8" 0`91" REGRADED FIELD a 23"x14," 30"A9" REGRADED RV PADS T-3" REGRADED GRAVEL ROAD 45"x29" C T-4" 1l-7" 1'-911 2--2" 0.-9.1 D 0,671 1'-3" 1r-6" 2'-0" 2'-6" F 3:11.00% 01-81, 01-8, 0I_911 01-91l H 2--3" 2`11" 3--2" 31-91, 4'-3- L 4--0" 5`10" 6'-0" 81-O'll TIE-IN a 01-11/4'. -1.00% 0'-2" -1.00% 0'-31/4° b 01-1-1 0-11/4-1 O --1V2" gg O' -2Y2 01-91, 1.43% CUBIC YARDS OF CONCRETE CONC. PIPE 1 2ne 0.492 1 0.697 1 1,319 2.067 _j 0.257 0.521 1 0.739 1 1.398 1 2.198 3'-9" 4'-0" 4'-2" 4--5" 4'-7" 12--0" L 5'-5"' 7$-2" 81-61, 9'-2" 10'-2" L,:, J! 12 -1" 121-111, O' -3,Y4" S 11-111. 2'-6" 2.-10.1 _j 3l-6" 31-91. 4--1" 41-5$' .... . .... . a W -21/2t' 0'-31/4" 0-4/2" 0'-4" 0'-4Y2" E -:4N" 0'-5" 00-51/zl' Jv 0'-2,"I `q, 0'-2Y4" 0'-3" 0'-3Y2" 01-3Y4" 0'-4" 0'_41/2" .. ...... .... CUBIC YARDS OF CONCRETE 2,947 3.145 CONC.PIPE 0,502 0.855 1.236 1 1.500 T 1.811 2.101 2.512 2.801 CONTRACTOR TO RAISE RV UTILITY CONNECTIONS TO PROPOSED GRADE EX. GRADE PROP. GRADE SHAPE TO BE BEVELED WITH MORTAR DO NOT BEVEL INVERT NOTES: 1. I'H" MAY BE REDUCED UNTIL "X" REACHES A MINIMUM OF 4" WHERE ENDWALL WOULD PROTRUDE ABOVE SHOULDER LINE. N NO CASE SHALL TOP OF ENDWALL PROJECT ABOVE FILL SLOPE, DITCH SLOPE, OR SHOULDER. 2. THIS ITEM MAY BE PRECAST OR CAST IN PLACE. 3. ALL CAST IN PLACE CONCRETE TO BE CLASS A3. FOR PRECAST SEE SHEET 101,02. 4. THIS STANDARD TO BE USED WITH STRAIGHT CROSSINGS AND ALL SKEWS(O* TO 45'). SITE SECTION III = 51 5 10 EW -MA C S. BEVEL EDGE IS REQUIRED ON THE HEADWALL AT THE INLET END OF THE CULVERT (WHERE THE FLOW ENTERS THE CULVERT). 7. HEADWALL AT THE OUTLET END OF THE CULVERT MAY BE EITHER SQUARE EDGE OR BEVEL EDGE, S. ON SHALLOW FILLS, WHERE ENDWALLS ARE 1 1 OR LESS BELOW SHOULDER LINE, THE TOP OF THE ENDWALL SHALL BE CONSTRUCTED PARALLEL TO THE GRADE OF THE ROAD. Gii. Y4" CHAMFER MAY BE PROVIDED ON ALL EDGES AT MANUFACTURER'S OPTION. 5. HEADEZ daEI C WITH FN ­V I[RbKwBiTk4NW A ONLY I ASSOCIATION EW -1A TOP OF FILL DIAMETER OF PIPE CULVERT ENDWALL FOR ELLIPTICAL 12" 15" 18" 21" OR 24"27" OR 2 A 0'-6" 0`8" 0`91" O, -ill' a 23"x14," 30"A9" 34"42" T-3" T-6" 45"x29" C T-4" 1l-7" 1'-911 2--2" 0.-9.1 D 0,671 1'-3" 1r-6" 2'-0" 2'-6" F 8 01-81, 01-8, 0I_911 01-91l H 2--3" 2`11" 3--2" 31-91, 4'-3- L 4--0" 5`10" 6'-0" 81-O'll 101-oll a 01-11/4'. OI -1y4" 0'-2" 0"-21/2" 0'-31/4° b 01-1-1 0-11/4-1 O --1V2" O'-2" O' -2Y2 01-91, F CUBIC YARDS OF CONCRETE CONC. PIPE 1 0.241 0.492 1 0.697 1 1,319 2.067 C.M. PIPE 1 0.257 0.521 1 0.739 1 1.398 1 2.198 EW -1A r �� I Iv^1 I'll REFERENCE STANDARD ENDWALL FOR PIPIE CULVERTS 105 12" - 36" CIRCULAR AND 23" x 14" - 53" x 34" ELLIPTICAL PIPES 302 VIRGINIA DEPARTMENT OF TRANSPORTATION XVDC3T ROAD AND RIDGE REVISION DATE SHEET 1 OF 1 103.01 S NOTES: 1. IN NO CASE SHALL TOP OF ENDWALL PROJECT ABOVE FILL SLOPE, DITCH SLOPE, DITCH SLOPE, OR SHOULDER. 2. THIS ITEM MAY BE PRECAST OR CAST IN PLACE. 3. ALL CAST IN PLACE CONCRETE TO BE CLASS A3. FOR PRECAST SEE SHEET 101.12. 4. THIS STANDARD TO BE USED WITH STRAIGHT CROSSINGS AND SKEW ANGLES TO 15'. 5, HEADWALL TO BE BEVELED IN ALL AREAS EXCEPT WHERE A CONFLICT WITH INVERT OR WINGWALLS OCCUR, TOP OF FILL FOR ENDWALL FOR ELLIPTICAL PIPE PIPE D S SIZE OF ELLIPTICAL PIPE CULVERT (SPAN x RISE) L CUBIC YARDS CONCRETE ONE DOUBLE ENDWALL OR 36" a 23"x14," 30"A9" 34"42" 38l"x24" 42"x27" 45"x29" 49"x32" 53"04" I. -DI. A O. -Bl. 0.-9.1 7t-3" 0,671 0.179 1.-0. W-114" 181, 2'-0" 8 T-2" T -5l, 0.244 O'-2-1 0I -1V2-- 11-101l 1 4'-0" 2'-9'l C 11-81, 1l-11.1 0'-2" 2--4" 2'-5l' 20-7" 2'-8" 21-9" 3'-0" D 1'-2" T-7-- T-10.. 2'-0" 2'-3" 2'-5" 2'-81. 21-101, 01-91, F 0-8- 0'-81, 0-9" 0-9., 27" OR 30" 0.-9.0 O*_91. 01-91, 4--9" H 21-10.11 31-31, 3'-7" 3'-9" 4'-0" 4'-2" 4--5" 4'-7" 12--0" L 5'-5"' 7$-2" 81-61, 9'-2" 10'-2" 101-111, 12 -1" 121-111, O' -3,Y4" S 11-111. 2'-6" 2.-10.1 31-2" 3l-6" 31-91. 4--1" 41-5$' 0'-3" a W -21/2t' 0'-31/4" 0-4/2" 0'-4" 0'-4Y2" E -:4N" 0'-5" 00-51/zl' b 0'-2,"I 0'-21/," 0'-2Y4" 0'-3" 0'-3Y2" 01-3Y4" 0'-4" 0'_41/2" CUBIC YARDS OF CONCRETE 2,947 3.145 CONC.PIPE 0,502 0.855 1.236 1 1.500 T 1.811 2.101 2.512 2.801 r �� I Iv^1 I'll REFERENCE STANDARD ENDWALL FOR PIPIE CULVERTS 105 12" - 36" CIRCULAR AND 23" x 14" - 53" x 34" ELLIPTICAL PIPES 302 VIRGINIA DEPARTMENT OF TRANSPORTATION XVDC3T ROAD AND RIDGE REVISION DATE SHEET 1 OF 1 103.01 S NOTES: 1. IN NO CASE SHALL TOP OF ENDWALL PROJECT ABOVE FILL SLOPE, DITCH SLOPE, DITCH SLOPE, OR SHOULDER. 2. THIS ITEM MAY BE PRECAST OR CAST IN PLACE. 3. ALL CAST IN PLACE CONCRETE TO BE CLASS A3. FOR PRECAST SEE SHEET 101.12. 4. THIS STANDARD TO BE USED WITH STRAIGHT CROSSINGS AND SKEW ANGLES TO 15'. 5, HEADWALL TO BE BEVELED IN ALL AREAS EXCEPT WHERE A CONFLICT WITH INVERT OR WINGWALLS OCCUR, SHAPE TO BE BEVELED WITH MORTAR DO NOT BEVEL INVERT EW -6 RIM 6, BEVEL EDGE IS REQUIRED ON THE HEADWALL AT THE INLET END OF THE CULVERT (WHERE THE FLOW ENTERS THE CULVERT). 7. HEADWALL AT THE OUTLET END OF THE CULVERT MAY BE EITHER SQUARE EDGE OR BEVEL EDGE. 8. ON SHALLOW FILLS, WHERE ENDWALLS ARE 1' OR LESS BELOW SHOULDER LINE, THE TOP OF THE ENDWALL SHALL BE CONSTRUCTED PARALLEL TO THE GRADE OF THE ROAD. 9. 3'4" CHAMFER MAY BE PROVIDED ON ALL EDGES AT MANUFACTURER'S OPTION. 10. QUANTITIES GIVEN ARE FOR ONE ENDWALL. PLEASE REFER TO STANDARD EW -1, SHEET lOtOl FOR ALL DIMENSIONS NOT GIVEN IN TABLES. TOP OF FILL FOR FOR CONCRETE PIPE D S G L CUBIC YARDS CONCRETE ONE DOUBLE ENDWALL INCREASE FORt EACH ADDITION,1A_ PIPE a b 12" 1f-1011 21-0" 51-10" 0.329 0.088 b PIPE PROJECTION ABOVE GROUND LINE 15" 2--3" 2t -6l 7t-3" 0,671 0.179 TOP OF FILL W-114" 181, 1 2'-8" 1 3--0" W-8-11 0.941 0.244 O'-2-1 0I -1V2-- 21 1- OR 24-1 _r3'-6" 1 4'-0" 11'-6-1 1.763 0.444 0'-2 0'-2" 27" OR 30" 4�-4�- T -75--o- 1 4r7 2.730 0.663 0'-3 331, OR 36" 5'-2" 0.980 171-21 3.854 0.907 I 3 0'-3 ()1 3" 1 SHAPE TO BE BEVELED WITH MORTAR DO NOT BEVEL INVERT EW -6 RIM 6, BEVEL EDGE IS REQUIRED ON THE HEADWALL AT THE INLET END OF THE CULVERT (WHERE THE FLOW ENTERS THE CULVERT). 7. HEADWALL AT THE OUTLET END OF THE CULVERT MAY BE EITHER SQUARE EDGE OR BEVEL EDGE. 8. ON SHALLOW FILLS, WHERE ENDWALLS ARE 1' OR LESS BELOW SHOULDER LINE, THE TOP OF THE ENDWALL SHALL BE CONSTRUCTED PARALLEL TO THE GRADE OF THE ROAD. 9. 3'4" CHAMFER MAY BE PROVIDED ON ALL EDGES AT MANUFACTURER'S OPTION. 10. QUANTITIES GIVEN ARE FOR ONE ENDWALL. PLEASE REFER TO STANDARD EW -1, SHEET lOtOl FOR ALL DIMENSIONS NOT GIVEN IN TABLES. STANDARD ENDWALL FOR MULTIPLE PIPE CULVERTS ROAD AND BRIDGE STANDARDS 105 12" - 36" CIRCULAR PIPES REVISION DATE SHEET 1 OF I 302 VIRGINIA D!)EPARTMENT OF TRANSPORTATION 101.11 PB -1 .. .. j NO PROJECTION OF PIPE ABOVE GROUND LINE TOP OF FILL FOR CORRUGATED METAL PIPE _ GROUND LINE _ GROUND LINE CUBIC YARDS INCREASE FOR L[ _:f ml:_11 --I, EARTH LIl k=14//r/ MIN_ 1/10 D1 X D x BEDDING MATERIAL M D S G L CONCRETE EACH ADDITIONAL a b PIPE PROJECTION ABOVE GROUND LINE MIN. 1.5 x 0 MIN. 1.5 x D MIN, 1.5 x 0 MIN. 1.5 x D MIN. 1-5 x D MIN. 1.5 x D ONE DOUBLE PIPE TOP OF FILL TOP OF FILL GROUND LINE + It -GROUND LINE + X•GROUND % LINE ENDWALL LLI_ ROCK 0 R ......... 12" 1'-7" 2'-0" 5'-7` 0.344 0,087 01-11 -0-7-T 0,_v 15" 1` llY2" 2'-6" 0.696 0.175 1 4r7 07--174'--- 181, 2--4 t' 3--0" ! 8- 4" 0.980 0.241 - OI_1TP_ 24" 31" 4'-0" ll`f_ 1.840 0.442 0'-21 01-21, 27" OR 30" 3'-10" 15'-0'l 13`10" 2.868 0.670 0'-3 W-21/2" 4.076 STANDARD ENDWALL FOR MULTIPLE PIPE CULVERTS ROAD AND BRIDGE STANDARDS 105 12" - 36" CIRCULAR PIPES REVISION DATE SHEET 1 OF I 302 VIRGINIA D!)EPARTMENT OF TRANSPORTATION 101.11 PB -1 .. .. j NO PROJECTION OF PIPE ABOVE GROUND LINE TOP OF FILL TOP OF FILL TOP OF FILL _ GROUND LINE _ GROUND LINE L[ _:f ml:_11 --I, EARTH LIl k=14//r/ MIN_ 1/10 D1 X D x BEDDING MATERIAL M &4N", RUCK OR UNYIELDING SOIL MIN. 1/10 D� X -BED DING ._I x [ - MATERIAL EARTH F, BEDDING MATERIAL MIN. 1/10 J x] D X %2" PER 1' OF H NORMAL EARTH FOUNDATION MIN. 8", MAX. 24" ROCK FOUNDATION FOUNDATION SOFT, YIELDING, OR OTHERWISE UNSUITABLE MATERIAL PIPE PROJECTION ABOVE GROUND LINE MIN. 1.5 x 0 MIN. 1.5 x D MIN, 1.5 x 0 MIN. 1.5 x D MIN. 1-5 x D MIN. 1.5 x D TOP OF FILL TOP OF FILL TOP OF FILL GROUND LINE + It -GROUND LINE + X•GROUND % LINE III "I 11-1I I�l1I ILIIEARTH 4 LLI_ ROCK 0 R ......... MIN 1/10 D� - __ I , - , UNYIELDING MIN. 1/10 D A BEDDING L MATERIAL NORMAL EARTH FOUNDATION _= _11- SOIL V2" PER T' OF H x D X MIN. 8", BEDDING MAX. 21, MATERIAL ROCK FOUNDATION LI=t i I IF, 11 1 11 1=11 I IF, 1_111 1 ­111=;�, MIN. 1/10 BEDDING EARTH MATERIAL FOUNDATION SOFT, YIELDING, OR OTHERWISE UNSUITABLE MATERIAL BEDDING MATERIAL IN ACCORDANCE WITH EMBANKMENT SECT ON 302 OF THE ROAD AND BRIDGE NOTES: SPECIFICATIONS. FOR GENERAL NOTES ON PIPE BEDDING, CLASS I BACKFILL MAHERIIAL IN ACCORDANCE SEE INSTALLATION'OF PIPE CULVERTS WITH SECTION 302 OF THIE ROAD AND BRIDGE AND STORM SEWERS GENERAL NOTES SPECIFICATIONS. ON SHEET 107.00. REGULAR BACKFILL MATERIAL IN ACCORDANCE FOR PLASTIC PIPE CLASS I BACKFILL MATERIAL WITH SECTION 302 OF THE ROAD AND BRIDGE CRUSHED GLASS CONFORMING TO THE rrrrr IN ACCORDANCE WITH SECTION 302 OF THE ROAD SPECIFICATIONS. SIZE REQUIREMENTS FOR CRUSHER RUN AND BRIDGE SPECIFICATIONS. AGGREGATE SIZE 25 AND 26 MAY BE USED IN PLACE OF CLASS I BACKFILL, rrrrr FOR ALL OTHER PIPE REGULAR BACKFILL MATERIAL IN ACCORDANCE WITH SECTION 302 OF THE ROAD AND BRIDGE SPECIFICATIONS, XVDOT INSTALL, OF PIPE CULVERTS AND STORM SEWERS SPECIFICATION REFERENCE ROAD AND BRIDGE STANDARDS CIRC. PIPE BEDDING AND BACKFILL - METHOD "All VIRGINIA DEPARTMENT OF TRANSPORTATION 302 303 SHEET 1 OF 4 REVISION DATE 07/12 107.01 O VDOT EW -1 & 1A O VDOT EW -6 0 f�, 2018 UINF-GRADE LLC w U F1 Y E -y > No., 3E 45596 APPRM_)JvP" "t"' DCV1 PROJECT 1809400 THE WORK 01F L I N E + G R A D E C201 Channel Report Hydraflow Express Extension for Autodesk® AutOCADO Civil 300 by Autodesk, Inc ROADSIDE DITCH - 10 YEAR Triangular Side Slopes (z:1) = 3.00, 66.66 Total Depth (ft) = 2.58 Invert Elev (ft) = 621.34 Slope (%) = 1.25 N -Value = 0.035 Calculations Compute by: Known Q Known Q (cfs) = 7.43 Elev (ft) Section 6124.00 6;23.50 623.00 6122.50 6122.00 621.50 IE t 620.50 01 Highlighted Depth (ft) Q (Cfs) Area (sgft) Velocity (ft/s) Wetted Perim (ft) Crit Depth, Yc (ft) Top Width (ft) EGL (ft) Wednesday, Nov 7 2018 = 0.38 = 7.430 = 5.03 = 1.48 = 26.54 = 0.31 = 26.47 = 0.41 Depth (ft) 2.66 3 20 40 60 80 100 120 140 160 180 200 220 Reach (ft) ROADSIDE DITCH CROSS SECTION - 10 YEAR ME 1.66 1.16 0.16 -0.34 -0.84 x'111 VFRT DATA TARI F ' CULVERT NAME CULVERT DESCRIPTION HYDROLOGY TOTAL FLOW Qio (cfs) FLOW PER BARREL Q/N (cfs) HEADWATER CALCULATIONS ELEVATION HEADWATER CONTROL VELOCITY OUT (fps) LOW POINT ELEVATION FREEBOARD (ft) Material -Shape -Size SLOPE LENGTH �Q7o) (ft) 1.50% INfLET CONTROL OUTLET CONTROL HWI / D HWi FALL ELHI HWo De He kr H ELHO NJ INVo INVin MATERIAL DIA (in) Triple Culverts 3-15" RCP 1 3 1 620.97 621.37 1 RCP 15 0.60% 66.48 16.81 5.60 1.57 1.96 2.36 623.33 1.99 0.96 1-99 0.50 0-40 623.36 1 623.36 4.57 1 623.92 0.56 Twin Culverts 2-24" RCP 2 1 620.32 620.53 1 RCP 24 0-81% 33.46 1 25.70 12.85 1 0.94 1.89 2.16 622.48 1.44 1.29 1 1.44 0.50 0,271 622.03 1 622.48 1 6.54 1 624.67 1 2.19 0 625 620 CULVERT COMPUTATIONS VDOT CL. I RIPRAP SEE THIS SHEET FOR DIMENSIONS INV.IN=620.59' ' INV. OUT=620.32 0+50 1+00 TRIPLE CULVERT PROFILE SCALE: 1"=20' H; 1"=2'V PROPOSED TRIPLE CULVERT PROFILE 1" = 20' 20 40 1992 3.18 PIP.. ' O UTLE' T CONDITIONS A A4 'IPE OUTLET TO FLAT iREA WITH NO DEFINED .HANNEL L a 0 % - * SECTION A -A FILTER CLOTH KEY IN C-9% RECOMMENDED FOR ENTIRE PERIMETER 3dc (MIN.) 'IPE OUTLET TO WELL )EFINED CHANNEL I P I u/ d, SECTION A -A FILTER CLOTH KEY IN B" -S"; RECOMMENDED FOR ENTIRE PERIMETER NOTES; 1. APRON LINING MAY BE RIPRAP, GROUTED RIPRAP, GABION BASKET, OR CONCRETE. 2. La IS THE LENGTH OF THE RIPRAP APRON AS CALCULATED USING PLATES 3.18-3 AND 3.18-4. 3. d = 1.5 TIMES THE MAXIMUM STONE DIAMETER, BUT NOT LESS THAN 6 INCHES. Source: Va. DSW Plate 3.18-1 NOTE: COMPUTATIONS PER VESCH STANDARD 3.18 5 OUTLET PROTECTION DETAIL AND MINIMUM DIMENSIONS 625 CURVE NUMBER TABULATIONS DRAINAGE AREA: DA. A AREAS (Ac) SOIL Total Area Impervious (CN 98) Woods (CN 77) Open Space (CN 80) D 0.82 0.20 0.26 0.37 DRAINAGE AREA: DA. B 15.59% 0.050 AREAS (Ac) SHALLOW SOIL 1.50% 0.050 Total Area Impervious (CN 98) Woods (CN 77) Open Space (CN 80) D 1.67 0.17 0.06 1.45 DRAINAGE AREA: DA. C (%) 620 AREAS (Ac) 15.0 SOIL (MIN) SHEET 100 Total Area Impervious (CN 98) Woods (CN 77) Open Space (CN 80) D 2.23 0.54 0.07 1.62 DRAINAGE AREA: DA. D AREAS (Ac) SOIL Total Area Impervious (CN 98) Woods (CN 77) Open Space (CN 80) 1+50 1+75 D 1.77 0.78 0.12 0.87 3 CURVE NUMBER TABULATIONS TIME OF CONCENTRATION TABULATIONS DRAINAGE AREA: DA. A FLOW TYPE LENGTH SLOPE MANNING'S n FLOW AREA WETTED VELOCITY TIME (FT) (%) (S F) PERIMETER (FT) (FPS) (MIN) SHEET 100 3.82% 0.170 7.8 SHALLOW 217 13.65% 0.050 0.6 SHAILLOW 150 2.30% 0.050 1.0 TOTAL Tc = 9.5 DRAINAGE AREA: DA. B FLOW TYPE LENGTH SLOPE MANNING'S n FLOW AREA WETTED VELOCITY TIME (FT) (%) IS F) PERIMETER (FT) (FPS) (MIN) SHEET 75 5.58% 0.400 10.6 SHALLOW 182 15.59% 0.050 0.5 SHALLOW 190 1.50% 0.050 1.6 CHANNEL 190 1.10% 0.035 2.99 17.95 1.34 2.4 D50 (FT) (%) CONIDITION TOTAL Tc = 15.0 DRAINAGE AREA: DA. C PIPE APRON APRON WIDTH LENGTH SLOPE FLOW AREA WETTED VELOCITY TIME FLOW TYPE VELOCITY MANNING'S n UPSTREAM DOWNSTREAM VDOT D50 (FT) (%) CONIDITION IS F) PERIMETER (FT) (FPS) (MIN) SHEET 100 4.27% 0.400 THICKNESS FEET 14.8 SHALLOW 510 6.52% 0.050 2.1 SHALLOW 160 1.78% 0.050 INCHES CFS FPS 1.2 FEET FEET FEET TOTAL Tc = 18.1 3 x;15 DRAINAGE AREA: DA. D 10 13-25 17-25 I 1.1 LENGTH SLOPE 1 FLOW AREA WETTED VELOCITY TIME FLOW TYPE 1 23 MIANNING'S n 1 1-1 2.5 (FT) (%) (SF) PERIMETER (FT) (FPS) (MIN) SHEET 100 1.91°!0 0.150 9.3 SHALLOW 400 0.95% 0.050 4.2 TOTAL Tc = 13.6 TIME OF CONCENTRATION TABULATIONS ,OUTLET PROTECTION - MINIMUM DIMENSIONS '_, PIPE APRON APRON WIDTH APRON WIDTH STR_ # TAILWVATER SPAN DISCHARGE VELOCITY LENGTH UPSTREAM DOWNSTREAM VDOT D50 RIP RAP CONIDITION (Do) (Q o) (V�°) (La) (3 Do) (W) GLASS THICKNESS FEET INCHES CFS FPS FEET FEET FEET FEET Triple Culverts 2 3 x;15 ( 16.81 1 4.57 10 13-25 17-25 I 1.1 2.5 Twin Culverts 1 2 xi24 I 25.70 1 6.54 1 10 1 13 1 23 I 1 1-1 2.5 '_,