HomeMy WebLinkAboutWPO201700070 Review Comments WPO VSMP 2019-03-05COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit plan review Project title: Albemarle County Route 250 Business (Ivy Road) Sidewalk Project file number: WP0201700070 Plan preparer: Brian McPeters [brian.mcpeters@kimley-horn.com] Owner or rep.: Jack Kelsey Ukelsey@albemarle.org] Plan received date: September 25, 2017 (Rev. 1) 28 Jan 2019 Date of comments: October 27, 2017 (Rev. 1) 5 Mar 2019 Reviewer: David James /Initial review [dames2galbemarle.org]; J. Anderson /Rev. 1 County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The application may be resubmitted for approval if all of the items below are satisfactorily addressed. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. 1. Provide a SWPPP including registration statement. (Rev. 1) Not addressed. Please provide SWPPP at earliest convenience. Use county template; link: htW://www.albemarle.orgLunload/images/forms center/departments/Community Development/forms/Engi neerina and _WPO_Forms/Stormwater _Pollution _Prevention _Plan _SWPPP _template.pdf B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. Provide a PPP. (Rev. 1) Not addressed. Please include PPP Exhibit with SWPPP. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved for reasons listed in comments, below. The stormwater management plan content requirements can be found in County Code section 17-403. 1. Cover Sheet — Change application number to WP0201700070; Update box with nutrient credit purchase information when acquired; Include source & date of topographic information, and last date of field verification of existing site conditions; missing survey date on sidebar. (Rev. 1) Partially addressed. As follow-up, please revise ref. to `purchasing 0.78 lbs. phosphorus from xxx Nutrient Bank on xx/xx/xxxx' to read from `Gold Hill Nutrient Credit Offset Bank on 02/05/2019.' (Ref. image, sheet 1, below.) Engineering Review Comments Page 2 of 3 FOR INDEX OF SHEETS SEE SHEET 1A THIS PROJECT WAS DEVELOPED UTILIZING THE VDOT'S ENGINEERING DESIGN PACKAGE (GEOPAK). GEOPAK Computer Identification No. 105806 ALBEMARLE 001 CxESA-EME BAr PRESERVATOV MOPUMCE 1111F'1XM! X ll M1rPoPUICENr &YY1f M' xx/x!/PYXPLAN ALBEMARLE COUNTY VSMP APPLICATION - WP0201700070 2. Who will be responsible for the maintenance of underground detention SWM facilities? (Rev. 1) Comment withdrawn. SWM facility eliminated per review meeting, 2/14/19 (Jack Kelsey, Frank Pohl, J. Anderson). UG detention is not required (sheets 3, 3D, 6(4), etc.) if runoff conveyed via man- made channel to 1% point of analysis. Engineering to confirm design meets 9VAC25-870-66.B.1./4. 3. Show that the channel (ditch) at Outfall A will be non -erosive when meeting 2-yr design, velocity is 15.36 (fps) and considered excessive (>: s). (Rev. 1) Not addressed; Also, item 2, above. At 2/14 meeting, Engineering and PMD discussed ditch maintenance, soil stabilization blankets /matting (VESCH 3.36), etc. Engineering to confirm revised design (final submittal) meets 9VAC25-870- 663.1./4., that final design 2-3r, 24-hour event velocities are non -erosive. Ref. table sheet I W O: WATER QUANTITY SUMMARY Stormwater Outfall Table Site Area jAcres) 1.93 Outfall A Outfall B Drainage Area From Site (Acres) 0.6950 1.2344 Overall Draina a Area (Acres) 69.D8 70.81 Drainage Area to Existing Detention Systems (Acres) 9.94 3.02 Runoff Reduction (cf) 0 0 Receiving Channel Type (Natural, Restored, or Manmade( Manmade Manmade Channel Protection Compliance Method Non -Erosive Non -Erosive Flood Protection Compliance Method l0 rCLDfl 1.; <16yrQN, g 10-yrQD—bW<10-yrCtF.1.,, 2-year 10-year 2-year 10-year VE;:dB(ft/5) 15.32 N/A 14.49 N/A VDT 41�d(ft/s) 15.42 N/A 14,49 N/A VAiI�.d (ft/s) N/A N/A N/A N/A C1F,ds,br (CFS) N/A 1 143.96 1 N/A j 81.55 QD—kMel(CFS) N/A 143.85 N/A 79.90 QA&.cd (CFS) N/A 143.96 N/A 81.55 NOTE: All calculations are computed using the rational method due to the site area discharging into existing manmade stormsewer systems. The calculations account forthe overall drainage area reachingeach outfall. Drainage areas that are assumed to drain to existing detention systems are excluded from the water quantity calculations. NOTE: Proposed detention pipes are used to reduce the 10-yr Q (cfs) in the pipes downstream of the proposed storm sewer improvements. 15.42 fps is erosive per VESCH, 31 Edit., 1992, Std. & Spec. 3.36 /P. III-357: "Treatment-1 is a degradable soil stabilization blanket ...During the establishment of vegetation, Treatment-1 should Engineering Review Comments Page 3 of 3 not be subjected to shallow or deep concentrated flow moving at greater than 4 feet/second." Then: "Since Treatment-2 is non -degradable, it can be used in permanent conveyance channels, and can withstand higher velocities of flow than the vegetation and soil would normally allow. However, a 10 feet/second velocity of flow should be the maximum allowed in a conveyance system which utilizes Treatment-2." (p. III-358) 4. Contact Ana Kilmer regarding nutrient credit purchase & agreement. Plan cannot be approved without nutrient purchase agreement. (Rev. 1) Addressed. Ref, A. Kilmer email (2/27/2019 9:56 AM) "FES has paid for the credits."; and, Dahris Garcia email (February 27, 2019 9:52 AM) "This was paid on 2/21/19 via check number 200175667." 5. New: Sheet 1H(1) Water Quality and Quantity data sheet: Provide narrative discussing man-made conveyance capacity to convey the post -development peak flow rate from a two-year 24-hour storm event without causing erosion of the system. Include capacity and condition of roadside ditch (Ivy Rd.-Rt. 250) to 1% limits of analysis. Transportation Engineer may provide further coordinating details to KHA. 6. New: Revise match -line references, sheets 3D and 3E. D. Erosion and Sediment Control Plan (ESOP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESOP. This plan is approved. 1. Remove Roadway Plan including road profiles/sections from this set. (Rev. 1) Partially addressed. As follow-up: Please remove driveway and Ivy Road (Route 250) profiles from VSMP /WPO Plan set. 2. Provide a soils map &description. Show existing conditions sheet (easements deed bk/pg, critical slopes, etc.). (Rev. 1) Request for soils map withdrawn; unnecessary given project corridor. Existing conditions shown in sufficient detail across multiple plan sheets. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Please call if any questions. J. Anderson, 434.296-5832 -0069 Process; After agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; http://www.albemarle.org/deptforms.asp?department=cdengmTo COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit plan review Project title: Albemarle County Route 250 Business (Ivy Road) Sidewalk Project file number: WP0201700070 Plan preparer: Brian McPeters [brian.mcpeters@kimley-horn.com] Owner or rep.: Jack Kelsey Ukelsey@albemarle.org] Plan received date: September 25, 2017 Date of comments: October 27, 2017 Reviewer: David James [djames@albemarle.org] County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The application may be resubmitted for approval if all of the items below are satisfactorily addressed. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. 1. Provide a SWPPP including registration statement. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. Provide a PPP. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17-403. 1. Cover Sheet — Change application number to WP0201700070; Update box with nutrient credit purchase information when acquired; Include source & date of topographic information, and last date of field verification of existing site conditions; missing survey date on sidebar. 2. Who will be responsible for the maintenance of underground detention SWM facilities? 3. Show that the channel (ditch) at Outfall A will be non -erosive when meeting 2-yr design, velocity is 15.36 (fps) and considered excessive (>10fps). 4. Contact Ana Kilmer regarding nutrient credit purchase & agreement. Plan cannot be approved without nutrient purchase agreement. D. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. Engineering Review Comments Page 2 of 2 This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Remove Roadway Plan including road profiles/sections from this set. 2. Provide a soils map &description. Show existing conditions sheet (easements deed bk/pg, critical slopes, etc.). The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process; After agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; h!Ltp://www.albemarle.oriz/deptforms.asp?department=cden�wpo File: Albemarle County Route 250 Business (Ivy Road) Sidewalk - VSMP.docx