Mitigation plan review
Project title: Old Trail Village Stream Buffer Mitigation
Project file number: WP0201900007
Plan preparer: Roudabush, Gale & Associates [bledbetter@roudabush.com]
Owner or rep.: March Mountain Properties LLC [dave@oldtrailvillage.com]
Date Received: 08 Feb 2019
Date of comments: 12 Mar 2019
Bill,
We have reviewed the above referenced plans and have the following comments:
1. Provide professional seal that is signed and dated.
2. Provide existing and proposed topography.
3. Provide legend for all linetypes (floodplain, buffer, etc).
4. Show all existing easements.
5. Show all critical slopes.
6. Ensure that no invasive species are proposed (including grass seed mixes). Provide note on the
plan that no invasive species shall be planted.
7. Please label the Old Trail Village blocks on all sheets. It is easier to navigate the areas since
discussions always revolve around blocks.
8. Details for planning area 3 and 6 appear to be missing. Please provide.
9. Please clarify that mitigation areas are equal to 2x's the total disturbed area. Some areas are
future/pending, so there needs to be a note that says how much disturbance this mitigation is for?
For example, if 100 SF was estimated to be disturbed, but it turns into 110SF, this mitigation plan
would need to be revised. Currently, the plan doesn't show how much is disturbed, it just shows
total mitigation area. This might only need to be applied to the future/planned areas. Engineering
understands that the approved mitigation plan areas are already covering the 2x, they are just being
moved around.
10. Provide maintenance requirements on the plan.
11. Please reference the 70% credit for grass/perennials (source?). Riparian guide, page XX, for
example.
12. Plantings by others are shown on this plan, but you are not proposing any changes to them and
they are not included in your calculations, correct?
Please note the following document:
http://www.albemarle.org/upload/images/forms_center/departments/Community_Development/for
ms/applications/Engineering_Review_Mitigation_Plan_Checklist 2Dec2014.pdf
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
Engineering Review Comments
Page 2 of 2
discuss this review.
If you have any questions or concerns, please contact me either by email (ecox2@albemarle.org) or by
phone at 434-296-5832 ext. 3565.
Sincerely,
Emily Cox, P.E.
Civil Engineer II
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Mitigation plan review
Project title: Old Trail Village Stream Buffer Mitigation
Project file number: WP0201900007
Plan preparer:
Roudabush, Gale & Associates [bledbetter@roudabush.com]
Owner or rep.:
March Mountain Properties LLC [dave@oldtrailvillage.com]
Date Received:
08 Feb 2019
Rev. 1 Received:
20 Mar 2019
Date of comments:
12 Mar 2019
Rev. 1 comments:
25 April 2019
We have reviewed the above referenced plans and have the following comments:
1. Provide professional seal that is signed and dated. Rev. 1: Comment addressed.
2. Provide existing and proposed topography. Rev. 1: Comment addressed.
3. Provide legend for all linetypes (floodplain, buffer, etc). Rev. 1: Comment addressed.
4. Show all existing easements. Rev. 1: Comment addressed.
5. Show all critical slopes. Rev. 1: Comment addressed.
6. Ensure that no invasive species are proposed (including grass seed mixes). Provide note on the
plan that no invasive species shall be planted. Rev. 1: Comment addressed.
7. Please label the Old Trail Village blocks on all sheets. It is easier to navigate the areas since
discussions always revolve around blocks. Rev. 1: Comment addressed.
8. Details for planning area 3 and 6 appear to be missing. Please provide. Rev. 1: Comment
addressed.
9. Please clarify that mitigation areas are equal to 2x's the total disturbed area. Some areas are
future/pending, so there needs to be a note that says how much disturbance this mitigation is for?
For example, if 100 SF was estimated to be disturbed, but it turns into 110SF, this mitigation plan
would need to be revised. Currently, the plan doesn't show how much is disturbed, it just shows
total mitigation area. This might only need to be applied to the future/planned areas. Engineering
understands that the approved mitigation plan areas are already covering the 2x, they are just being
moved around. Rev. 1: Comment addressed.
10. Provide maintenance requirements on the plan. Rev. 1: Comment addressed.
11. Please reference the 70% credit for grass/perennials (source?). Riparian guide, page XX, for
example. Rev. 1: Comment addressed.
12. Plantings by others are shown on this plan, but you are not proposing any changes to them and
they are not included in your calculations, correct? Rev. 1: Comment addressed.
13. REV 1: Per the meeting at the county on 4/25/19, please clarify the total required areas vs the total
proposed areas.
14. REV 1: Per the meeting at the county on 4/25/19, please add a note on the cover sheet stating that
Engineering Review Comments
Page 2 of 2
any areas not in the 100 ft. buffer will be placed in an easement. This easement plat must be
recorded before any mitigation bonds will be released.
15. REV 1: Per the meeting at the county on 4/25/19,the amount needed to be bonded with this master
plan will be the difference between what is proposed and what is currently bonded. Block 32 (area
3) and Area 6 will be bonded with those plans at that time.
Please note the following document:
http://www.albemarle.org/upload/images/forms_center/departments/Community_Develop ment/for
ms/applications/Engineering_Review_Mitigation_Plan_Checklist 2Dec2014.pdf
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
If you have any questions or concerns, please contact me either by email (ecox2@albemarle.org) or by
phone at 434-296-5832 ext. 3565.
Sincerely,
Emily Cox, P.E.
Civil Engineer II