HomeMy WebLinkAboutSUB200500186 Bond Reduction 2019-03-20COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832
20 March 2019
David Sharp, VP Development
Barbara Roberts, Executive Administrator
Cathcart Group
200 Reserve Boulevard, Suite 300
Charlottesville, Virginia 22901
Dear Ms. Roberts /Mr. Sharp,
Fax (434) 972-4126
We received your road bond inspection request with fees paid for the Village at Chestnut Grove project on 03/04/19. A
bond reduction is possible, but there are outstanding items required in order to process further reduction, including
installation of guardrail in locations shown on the approved Road Plan. Please ref. attached checklist. Also, given
degree of correspondence, meetings, and history, a series of email with attachments, including scans of approved plan
sheets have or will be sent as supplemental information. Please reference VDOT emails sent on February 20, 26, and
28 (X 2), several with attachments, which outline VDOT and county road acceptance procedures and expectations, as
well as road plan bond reduction or release requirements (checklist; next pg.). Furthermore, a bond release cannot be
processed without items noted in the County's Public Road Acceptance Procedure. Your request to release bond is on
hold until the listed outstandingitems are complete. Please document completion within 30-days of this notice, or a
new application and fee will be required to release or lower the bond from its new updated amount of $75,620.
Below are links to Albemarle County procedures for public road acceptance:
http://www.albemarle.org/upload/images/forms center/departments/Community Development/forms/En ink eering and
WPO_Forms/Road _ Inspections & Acceptance- Public Road Acceptance Procedure 07-26-2012.pdf
http://www.albemarle.org/upload/images/forms_center/departments/Community_ Development/forms/En ing eering and
WPO_Forms/Road _Inspections_& Acceptance- Certificate of Completion for Subdivision 03-16-09.pdf
Please contact me if you have any questions. Thank you.
Sincerely,
John E. Anderson, PE
County of Albemarle
(434) 296-5832 ext. 3069
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
Road Bond Inspection
Bond Title: The Village at Chestnut Grove
File Number: SUB200500186
Date of inspection: 2/26/19 Original Bond Amount: $315,660.00
Reviewer: John Anderson Current Bond Amount: $114,510.00
Phone: (434) 296-5832 -x3069 Updated Bond Amount: $ 75,620.00
Your bond inspection request has been processed. This list contains an update on the items received and
approved.
Received
Approved
Y
N
Y
N
N/A
VDOT
■
❑
Completed inspection request and fee
■
❑
❑
❑
■
❑
As -built plan, updated, sealed to current date, per As -built policy
❑
❑
❑
❑
■
❑
Copies of recorded plats for right-of-way, easements
■
❑
❑
❑
■
❑
VDOT approval AM-4.3, or partial completion via punchlist
❑
❑
❑
■
❑
■
Letter from P.E. certifying improvements are built to plan
❑
❑
❑
❑
❑
■
Current certification form completed by owner/developer
❑
❑
❑
❑
■
❑
CBR test reports for each road
❑
❑
❑
■
■
❑
Stone depth and material inspection reports (or core tests)
❑
❑
❑
■
■
❑
Pavement depth and material inspection reports (or core tests)
❑
❑
❑
■
❑
■
Compaction test reports for fill areas under road
❑
❑
❑
■
❑
■
Pipe trench inspection reports
❑
❑
❑
❑
❑
■
Pipe interior inspections reports and video
❑
❑
❑
❑
❑
■
Concrete test reports for structural concrete, curbing, aprons, etc.
❑
❑
■
❑
❑
■
Structural inspection reports for any bridges or box culverts
❑
❑
■
❑
■
❑
County road name signs and posts, or a sign agreement for alt. posts
❑
■
❑
Please refer to on-line content at http://www.albemarle.org/dotforms.asp?department=cdengMoo for checklists and procedures.
OUTSTANDING ITEMS /please complete to be eligible for additional reduction, or bond release:
1.Orange-shaded table values /items; ref VDOT email to Applicant, February 20, 2019 4:34.
Yellow -shaded items to be "addressed with a pavement repair procedure submitted with possible monitoring."
Note: email reads, in part: "Also, if underdrain was not installed then disregard that item."
2. Pipe: Repair 48" DIA storm line to VDOT standards. Ref. VDOT pipe inspection summary email w/ Attachments,
sent 2/28/2019 3:03 PM
3.45-day VDOT inspection punch -list (VDOT email sent 2/28/2019 4:15 PM). Complete 45-day punch -list items.
4. Pipe video inspection once repairs complete; 2 copies of CD with video, with printed summary of findings, to CDD.
(Also, item 2., above.)
5.Oran ems: recorded plats, date recorded/receipt: email, JA to VDOT 2/26/2019 12:33 PM; Deed bk.-pg. 3449-310.
6.Orange item:.PDF of originally Approved plans; sent as supplement to this letter / bond inspection checklist; series
of 7 plan sheets, SUB200500186, approved 27 June 2006. See filenames HPSCANNER129 /131 /.PDFs.
7. Guardrail:Install guardrail. See Approved ROAD PLAN, sheets 3 (plan view, location), and 5 (GR-2, GR-6 details).
8. Stop sign: Reset so sign post is vertical.
Note: As -built plan review is pending. As -built drawings received 3/12/19.
SUB200500186 Village at Chestnut Grove BIR Letter-032019.docx