HomeMy WebLinkAboutWPO201700038 Bond Reduction 2019-04-11Project Name: University of Virginia Foundation Squash Facility at Boar's Head Addition WPO file number: WP0201700038 TM P(s): 059D2-01-00-01500 Date Estimate Completed: 04/09/19 Stormwater Management Bond Estimate % Cost Item Item No. Unit Unit Cost Cost complete Remaining Number installed permanent diversion or ditch ft $13.00 $1,456.00 100 $0.00 standard manhole frame top (not inlet) ea lea $500.00 $1,500.00 100 $0.00 drop inlet or grate $3,500.00 $28,000.00 100 $0.00 manhole structure (per ft. rise) 0 ft $450.00 $0.00 100 $0.00 pipe, rcp, cmp (15 to 48") 15.0 in d 4 EC-1 600.5 ft $35.00 $24,517.50 100 $0.00 pipe, rcp, cmp (15 to 48") 24.0 in d ES-1,2 F 0 EC-1 15.6 ft $50.00 $1,280.00 0 $1,280.00 pipe, rcp, cmp (15 to 48") JES-1,2 48.0 in d r ES-1,2 0 EC-1 8§d§ft $150.00 $12,750.00 100 $0.00 aggregate base or drainage stone 0.0 in d ft L `0.0 ft W 0.0 ton $35.00 $0.00 bioretention #1 height of dam at toe 0 ft cut at high side ft height of fill at face 0 ft length of dam Oft cut at face length of cutoft ft ft top width ft width of cut (area above transiti( 0 sf (area below transiti, 0 sf (total width of dam) 0 ft (total width of cut) 0 ft (height below transil 0 ft (depth below transit 0 ft (area below transitic 0 sf (area above transiti 0 sf (total fill volume) 0.0 cy (total fill volume) 369.0 cy length of spillway ft JOAL CY estimate 369 cy $13.00 $4,797.00 100 $0.00 width of spillway ft W (spillway stone tons 0 tons $50.00 $0.00 bioretention #2 height of dam at toe ft cut at high sideoft ft height of fill at faceft cut at face ft length of damft Lft length of cutft top width width of cut (area above transiti( 0 sf (area below transiti, 0 sf (total width of dam) 0 ft (total width of cut) 0 ft (height below transil 0 ft (depth below transit 0 ft (area below transitic 0 sf (area above transiti 0 sf (total fill volume) 0.0 cy (total fill volume) 67.0 cy length of spillway JOAL CY estimate 67 cy $13.00 $871.00 100 $0.00 =ft width of spillway ft (spillway stone ton: 0 tons $50.00 $0.00 100 $0.00 trees F 4 ea $275.00 $1,100.00 100 $0.00 shrubs 137 ea $50.00 $6,850.00 100 $0.00 seedlings 60 ea $5.00 $300.00 100 $0.00 biofilter mix (per acre) 1 ea $70.00 $70.00 100 $0.00 underdrain (LF) 99 ft $5.00 $495.00 100 $0.00 biofilter soil mix (CY) 120 cy $45.00 $5,400.00 100 $0.00 trash rack/ anti vortex devices ft $1,500.00 $0.00 100 $0.00 maintenance access road (LF) =ft $50.00 $9,000.00 100 $0.00 rip -rap, placed depth ft length _ft 100 $0.00 width (tons) 37.5 $60.00 $2,250.00 100 $0.00 survey and layout (price per 0.1 mi.) acres basins $1,700.00 100 $0.00 mobilization $500.00 0 $8,603.00 as -built drawings (per facility) $2,000.00 $2,000.00 50 $1,000.00 materials testing (per facility) Mea ea $2,000.00 $4,000.00 100 $0.00 compaction testing (per dam) ea $3,000.00 $0.00 100 $0.00 manufactured facilities (attach manufacturer's or contractor's price as a base) $0.00 $0.00 4/11/2019 Project Name: University of Virginia Foundation Squash Facility at Boar's Head Addition WPO file number: WP0201700038 TM P(s): 059D2-01-00-01500 Date Estimate Completed: 04/09/19 Stormwater Management Bond Estimate Item Item Number JA 040919,rev 041119 checked with A. Kilmer files, 11.6.18 No. Unit Unit Cost Cost (installed) cost sum $108,836.50 contingency $10,883.65 Total $119,730 Cost complete Remaining $10,883.00 $1,088.30 $11,973 4/11 /2019