HomeMy WebLinkAboutSDP201800087 Review Comments Final Site Plan and Comps. 2019-04-15 (7)GfRGSIytP
County of Albemarle
Department of Community Development
Memorandum
To: Dustin Greene
From: Tori Kanellopoulos - Planner
Division: Planning Services
Date: April 15, 2019
Subject: SDP201800087- Timberwood Square - Final Site Plan
The Planner for the Planning Services Division of the Albemarle County Department
Community Development will recommend approve the plan referred to above when the
following items have been satisfactorily addressed. (The following comments are those that have
been identified at this time. Additional comments or conditions may be added or eliminated
based on further review.) [Each comment is preceded by the applicable reference to the
Albemarle County Code.]
Required Prior to Final Site Plan Approval:
Planning Comments:
Comments from Initial Site Plan that have a note or are not fully addressed:
1. See attached direction from the Post Master regarding group mailboxes. Please
coordinate location with the Post Master.
a. REV 1: Follow-up: Location is acceptable to Planning. Please be sure to
coordinate with the Post Master as well.
b. REV 2: Addressed.
2. [18-32.5.2.b] Written schedules or data. Revise note to read "office use" instead of
"commercial use", for Parking Tabulations and Square Footage, as the office use has
specific parking requirements that are distinct from other commercial uses, on SP2.
a. REV 1: Not addressed: All proposed uses for the 65 parking spaces are office
uses. If the uses change in the future, Zoning will need to make a parking
determination. The application may be updated in the future, however it
should be listed as office uses at this moment, as that is what is being
proposed with this development.
b. REV 2: Addressed.
3. [18-32.5.2.1] Existing and proposed utilities. Label all utilities as either existing or
proposed. Include the deed book and page number of all existing easements. Proposed
easements that are not yet recorded must be recorded with an easement plat prior to final
site plan approval.
a. REV 1: Follow-up: If there are DB/PG for the existing easements on SP3
(specifically the water line and the sewer line on the west side), please include
them.
b. REV 2: Not fully addressed. On SP5 and SP6 please label all easements as
either "ACSA" or "public" OR "private". Some easements say "existing (e.g.
sanitary sewer)" but it is not clear if they are private or public. All proposed
easements should also be labeled to be clear they are public or private. All
private and public non-ACSA easements will need to be shown on an
easement plat and recorded with maintenance documents.
4. [18-32.5.2.1 and 18-4.11.4] Existing and proposed utilities. Revise the easements that are
conflicting with any structures. See Lot 10 as an example (appears easement conflicting
with deck).
a. REV 1: Not fully addressed: See Engineering comment as well. There
appears to be a conflict with utilities and landscaping (See SP9 and pin oak).
Appears there may be conflict with waterline on SP10 and pin oak.
b. REV 2: Addressed.
5. [18-4.12.51 Location ofparking areas. Parking is required to be on the same lot as the
primary use, except as authorized by 18-4.12.8. The lot lines for all of the lots overlap
with the parking spaces in such a way that the parking spaces are split by the lot lines.
Some lots contain one full parking space and one or two parts of other parking spaces,
however only some lots (1, 2, 6, 10, 11, 15, 19, 20, 28 and 32) contain at least two full
parking spaces. A shared parking agreement will be required for the lots for the
townhomes.
a. REV 1: Not addressed: Even with an access easement, a shared parking
agreement is still needed for the townhomes. This can be covered as part of
the HOA covenants and restrictions. Another option is to assign two parking
spaces to each dwelling unit, and this must be clearly shown in the
covenants/restrictions.
b. REV 2: In Progress: Will be provided with HOA documents.
6. [18-4.12.8(e)] Instrument assuring continuation of off -site parking. Stand-alone parking
for the commercial area: If stand-alone parking or off -site shared parking is to be
provided, the applicant shall submit with the application for a site plan, site plan waiver
or, if a site plan is not required, with an application for a zoning compliance clearance, an
instrument that restricts the use of that part of the land on which parking is provided to
that use, and assures that a minimum number of parking spaces as required by this section
shall be established and maintained for the life of the use. The instrument shall be in a
form that is suitable for recording. shall be subiect to review and annroval as to form and
substance by the county attorney, and shall be recorded in the office of the clerk of the
circuit court of the county before the site plan or site plan waiver is approved. As the
parking requirements for the use or structure change, subsequent instruments may be
submitted, reviewed, approved and recorded that rescind or modify the prior instrument.
a. REV 1: Not addressed: This is a requirement prior to final site plan
approval. Stand-alone parking is parking that is not on the same lot as the
use. This stand-alone parking was previously approved for the office area of
this development, however the instrument is still required, given that a new
office space is proposed. The same number (65 spaces) is still the
requirement. This is to ensure both office spaces have access to and sufficient
parking.
b. REV 2: In Progress: Will be provided with HOA documents.
7. [18-4.12.11(b)] ldenli, _ation of use served. For standalone parking, at least one (1) sign
shall be posted in the parking area identifying the off -site use served by the parking area.
a. REV 1: Not addressed: See previous comment.
b. REV 2: Addressed.
8. [18-32.7.9.41 Contents of a landscape plan. Revise the small notes counting the number
of trees on SP9 and SP10, as some are incorrect.
a. REV 1: Not fully addressed: On SP9 I counted 3 CJ, not 2. On SP11 I
counted 27 AF (not 30) and 101 CJ (not 100). Please correct and update all
relevant tabulations.
b. REV 2: Not fully addressed:
i. I counted 83 CJ, not 82 as shown on SP11.
ii. SP9 in the bottom right corner has a label for 4 QP's (by the biofilter)
however there are no trees there. Remove label.
iii. SP10 has a label in the top right corner for 2 QP's, however there is
only 1 QP. Revise label.
iv. On SP11 the Conservation Plan Checklist has not printed correctly
and the boxes are not checked. Please revise.
9. [18-4.16.1(3)1 1,«,..„...„, w, cat. i.tuicaw iww one rccrcauonai area is being calculated. In
the residential area, there appears to be 2,525 sq. ft. for the tot lot, 25,289 sq. ft. for one
section of open space and 4,692 sq. ft. for the other section of open space. The
recreational area is listed as 17,376 sq. ft.
a. REV 1: Not fully addressed: Appears to be corrected on SP2, however seems
incorrect on SP10.
b. REV 2: Addressed.
10. [18-32.7.2.31 Sidewalks. Request for applicant to provide sidewalks along Timberwood
Blvd. and Worth Crossing along the edge of the property. Provide ADA accessible ramps
at the corner of Timberwood Blvd and Worth Crossing, and at the trailhead where it
meets Worth Crossing. The sidewalks in the public ROW will need to be dedicated to the
County and maintained by VDOT. Additional detail pending VDOT's comments.
a. REV 1: Not fully addressed: Planning staff has determined that 6' asphalt
paths would be acceptable in place of sidewalks along Timberwood Blvd. and
Worth Crossing along the edge of the property. Asphalt paths have been the
standard for connectivity in this area. While pathways along these public
streets may have not been previously required, this type of connectivity is
now standard, including with the 2015 Comprehensive Plan update.
b. REV 2: Addressed with 6' asphalt paths.
11. [Future Application Comments]
a. [Cwnme1..,. � 1-11 .,.u.-1.0division plat will be needed to create lots for the
Townhomes.
i. REV 1: Addressed: This may occur after final site plan approval.
b. [Comment]: The proposed private streets will need to meet the private streets
standards in Chapter 14 (Subdivision Ordinance) during the subdivision phase of
this development.
i. REV 1: Addressed: This may occur after final site plan approval,
however applicant should keep these street standards in mind. The
application appears to be meeting them, as Engineering has been
reviewing Road Plans with these standards.
c. [Comment]: Note that approved Road Plans, WPO and VSMP are required prior
to final site plan approval.
i. REV 1: In progress: See Engineering comments.
ii. REV 2: Still in progress with second submittal. See Engineering
comments.
New Comments:
1. [Comment] Uses. Revise "Proposed Use" on SP2 to be "Office" instead of "Club". As
discussed in a meeting with staff, the club is on a separate parcel and no club is proposed
with this project. Only office uses and residential units are proposed.
a. REV 2: Addressed.
2. [18-4.20] Setbacks. On SP2, also include the setbacks under 18-4.20, as these would
apply to the office uses on the other portion of the development.
a. REV 2: Addressed.
3. [Comment] All required landscaping that will be maintained by the HOA/private entity
and is on individual lots must have easements. Most of the required landscaping is
already shown with easements, however the street trees are not. An access easement does
not cover landscaping easements on individual lots.
a. REV 2: Addressed. Will be part of HOA documents/maintenance and
easements are now shown on the site plan.
4. [18-32.8.21 Agreement and Surety. A surety for street trees, all required landscaping and
sidewalks is required prior to final site plan approval. This can be included in the HOA
covenants and restrictions. This bonding can be done with the bonding for the Road
Plan.
a. REV 2: Waiting for HOA documents/covenants/maintenance.
5. [Comment] HOA covenants and restrictions are required for maintenance of property
and amenities, including open space, the trail, private streets, private easements (such as
landscaping, private drainage, etc.), sidewalks and street trees. These
covenants/restrictions must include the private street maintenance agreement. This is
required prior to Road Plan approval, and therefore prior to final site plan approval.
a. REV 2: Waiting for HOA documents/covenants/maintenance.
6. [14-234(C)] Private streets in the Development Areas. A private street request is required
prior to Road Plan approval. This request may be in the form of a letter (emailed to the
Planning Reviewer) that shows the streets meet the criteria of 14-234(C) items 1-5. Staff
sees no issues with the private street request; this letter of request is now a requirement
and must be included with the application folder. Staff has already reviewed the private
streets for compliance.
a. REV 2: Engineering Review: Requested changes — see Engineering
comments.
b. REV 2: Planning Review: Agrees with Engineering review and confirms that
no public street is shown in the Comprehensive Plan and that road
maintenance agreement must be approved per Section 14 Subdivision
regulations prior to plat approval.
7. [Comment] Easement plats and final plat after site plan approval applications may be
submitted after final site plan approval. As indicated in previous comments here,
covenants/restrictions that include maintenance and sureties must be complete and
approved before final site plan approval. As stated in previous comments here as well, the
roads, sidewalks and street trees must be bonded before Road Plan (and therefore final
site plan) approval.
a. Rev 2: In progress: See previous comments.
Engineering Comments:
Remaining from Initial Site Plan (SDP2018-71):
1. Text, email, Engineering to Planning (6/18/2016 2:11 PM -also RMS docs,
SDP201500023): "(SDP201500023) —Engineering has No Objection to FSP design.
Engineering comments addressed with this or prior submittal. FSP Approval requires
ROAD Plan Approval, and requires that roads (Lois Lane, Landon Lane) be built or
bonded. ROAD Plan is not approved. FSP Approval requires that WPO be approved and
bonded. Planning coordinator should confirm that SWM Maintenance Agreements have
been signed, that project has received VPDES Permit coverage letter from DEQ. Please
confirm WPO status with Max Greene, Engineering Div." (1/14/19 review) Comment
persists; see item 25., below.
a. REV 2: Comment persists.
2. Ch. 14 Division 5, Procedures for the Approval of Private Streets, Sec. 14-233, When
private streets in development areas may be authorized is relevant. It appears no element
of initial site plan approval persists, and that request for approval of private streets in the
development area is required. (1/14/19) Since private roads are being proposed, please
submit private street authorization request. Please ref. Sec. 14-233 for procedure.
Recommend contact and coordinate with FSP review coordinator.
a. REV 2: Addressed.
3. Final Site Plan Approval requires Planning Division to authorize private streets in the
development area, if private streets are proposed. (1/14/19) Applicant response: `Private
roads are being proposed. Comment noted.' As follow-up: Please coordinate private
street authorization request with FSP plan coordinator, Tori Kanellopoulos.
4. Final Site Plan Approval requires roads be built or bonded. (1/14/19) Applicant response:
`Comment noted.'
a. REV 2: Addressed.
5. Final Site Plan Approval requires WPO Approval. Last .,etior o WPO20 500032.
. If Applicant re -submits a WPO plan based
on WPO201500032, Engineering requests cloud revisions of any change to plans since
last submittal of WPO201500032. (1/14/19) VSMP/WPO Plan submitted. A new
VMSP/WPO file# to be assigned. Plan was reviewed, and comments sent to Applicant
on 12/28/18. A VSMP/WPO Application fee is required (see comment Memo email).
a. REV 2: Comment persist. WP0201900015 is under review.
6. This Initial Site Plan appears to require an Initial and/or Final Plat. (1/14/19) Applicant
response: `A final plat will be provided under separate cover.'
a. REV 2: Comment persists.
New Comments:
7. Storm Sewer Profile Str. 5A-5 (sheet 15): Pipe length label is 7.10', inconsistent with
plan view scale (�40'; sheet 5); revise for consistency. Also, structure labels should
match; i.e., Ex. 5A, Ex. 5.
a. REV 2: Not addressed.
8. Lois Lane parking and street typical section note: `There is a transition period from
12+20 to 12+75 where the road width goes from 20' to 24." Please confirm transition is
limited to 55' section. Plan view (sheet 5) transition appears more gradual and appears to
extend to cover additional roadway stations.
a. REV 2: Addressed.
9. Lois Lane profile (sheet 16): Revise Str. E7 so that top of Str. matches proposed grade.
a. REV 2: Addressed.
10. Provide detail for tot lot permanent fencing shown on sheet 5. Ensure fence design
/material /height do not obscure sight distance on Lois Lane.
a. REV 2: Addressed.
11. Revise plan title to include SDP201800087.
a. REV 2: Addressed.
12. Provide dumpster pad section detail.
a. REV 2: Not addressed. Cannot locate on sheet 18, please advise.
13. Relocate pin oak (sheet 9) between drainage structure 11 and E7, to eliminate conflict.
a. REV 2: Addressed.
14. Engineering deters to VDUT on Left Turn Restriping Plan and MOT Plan (sheet 20).
a. REV 2: Addressed.
15. Sheets 5 and 7: Show and label Arbor Lake waters' edge.
a. REV 2: Addressed.
16. As discussed 1/10/19, please provide copy of letter of agreement between Timberwood
Square and Forest Lakes HOA stipulating /permitting Timberwood Square's use of Arbor
Lake for SWM purposes.
a. REV 2: Comment persists.
Engineering Private Street Comments
1. Revise sheet 5 of Road Plan, SUB 201800220, to show roadway stationing, Lois
Lane.
2. Revise sheet 14, Road Plan, to show base and surface asphalt, and base stone
depths for Lois Lane, Sta. 13+64 - 14+64, consistent with structural stone and
asphalt depths shown on all other travelway /roadway /parking sections, this
sheet; i.e.: 6" VDOT 21A, 2.5" 25.OA, 1.5" SM-9.5A.
3. Revise sheet 14, Road Plan, to show Lois Lane section with structural depths, Sta.
10+00 - 13+64.
4. Ref 1.18.19 Planning Comments, item #10/SP6: Provide CG-12 detectable
surface (but not ramp) where asphalt path intersects EP, Wirth Crossing. Show
existing asphalt path, N side, Worth Crossing.
Inspections Comments:
1. No Objection (both first and second submittal of final site plan)
Fire/Rescue Comments:
1. No Objection (both first and second submittal of final site plan)
ACSA Comments:
1. No objection on second submittal of final site plan.
Sheet 1:
1. Provide final water and sewer data sheets.
Sheet 4:
1. Eliminate this sheet from the ACSA submittal.
Sheet 5:
1. Sewer between MH's B and C shall be ductile iron. To avoid possible conflicts, I would
suggest removing pipe material labels on plan view.
2. 4-inch diameter water mains shall be Class 53.
3. Sewer between MH's A and EX1 shall be ductile iron.
4. Sewer main between MH F and EX shall be ductile iron.
Sheet 6:
1. Be sure water meter for Lot 19 falls outside of the sidewalk.
Sheets 7 and 8:
1. Show water and sewer utilities on grading plan sheets.
Sheet 14:
1. Explore any opportunity to increase the slope on sewer downstream of MH D. Several
runs of near minimum slope could be difficult for the contractor to install.
2. Sewer main between MH F and EX shall be ductile iron.
3. Show proposed grade over sanitary sewer main downstream of MH E.
Sheet 15:
1. Add note: Contractor shall deflect water main where possible to avoid vertical bends.
2. Accurately call out 8"X8" TS&V for connection along Worth Crossing.
Sheet 17:
1. Eliminate this sheet from the ACSA submittal.
Sheet 19:
1. Provide updated details for Typical Water Service and Blow -Off Assembly.
Sheet 20:
1. Eliminate this sheet from the ACSA submittal.
VDOT Comments:
1. No Objection on second submittal: See attached letter.
2. Include the applicable figures and tables for the type of operation from the Virginia Work
Area Protection Manual (latest revision) on the MOT plan sheet. Signs and spacings on
the MOT plan must match these figures.
3. Please see and address the attached MOT plan markup.