HomeMy WebLinkAboutWPO201500060 Bond Estimates WPO VSMP 2017-01-05 Town&Country Shopping Center,VSMPIWPO201500060
WPO file number- 201500060
Erosion and Sediment Control Bond Estimate
Item Item N.9 VIA Unit Cost Cost
Number fr>s_Nedl
1 stablaation(PS,1S) 124 acres 35,000 00 $6,20000
2 tree protection O U. Oft 55.00 S0 00
3 silt fence(SF) 350 ft 35.00 31.800.00
4 safety fence(SAF) 180 ft $5.00 $900.00
5 diversion(DD,FD,RWD) 535 ft $13.00 $6,955.00
6 temporary slope drain(TSD) pipe length 0 ft pipe diameter 0 in $0.00 S0.00
7 earthwork for trap WI)
8 height of dam at toe 2 ft cut at high side 3.5 ft
9 height of Si at face 3.5 6 cut at face 3.5 ft
10 length of dam 20 ft length of cut 50 ft
11 top width 2 6 width of cut 30 ft
12 31 5 of (area below transition) 129 5 sf
13 4 ft (total width of cut) 44 ft
14 -1.5 ft (depth below transitior 0 ft
15 -5.25 sf (area above transition 0 sf
16 87.5 cy (total fill volume) 383.7 cy
17 length of spillway 10 ft (TOAL CY estimate) 413 cy $13.00 $5,389.00
18 width of spibway 5 ft (spillway stone tons) 3.5 tons $50.00 S175.00
7 silt fence inlet protection(IP 5 $500.00
8 stone inlet protection(IP) 2 $400.00
9 outlet protection(OP) length 0 ft width 0 ft 0 S0 00
10 channel(SCC,matted) length 0 ft width 0 ft $0.00
11 check dam depth in channel 0 ft channel width 0 ft 0 $0.00
12 construction entrance(CE) 0 $0.00
13 wash rack 1 $2,000.00
14 paved construction entrance 1 $3,500.00
15 rip-rap,Pieced depth 0 ft length 0 ft
18 width 0 (tons) 0 tons $60 00 S0 00
-17 Etter fabric(below nprap) vital 0 length 0.0 0 sy $3 10 SO 00
18 survey and layout(price per 0.1 mi.) area 0 traps and basins 0 $0 00
19 mobilization $500.00
20 stream crossing(computed independently) $0.00
cost sum $28,299.00 ••
prof mgmt $4,244.85 ■
ESC_bond_WP0201500060_town&countryja111715 contingency 53,25439 `
Total $35,800
11/17/2015