HomeMy WebLinkAboutARB201800038 Correspondence 2018-07-19 (200 GARRETT ST,SUITE K CHARLOTTESVILLE VA 22902
COLLINS NGINEERING
C434.293.3719 PH 434.293.2813 FX
{ www.collins-engineering.com
TRANSMITTAL
0 FAX 0 MAIL X DELIVERY
TO: MARGARET MALISZEWSKI FROM:GRAHAM MURRAY,PE
COMPANY: DATE: 7/18/18
FAX: TOTAL NO.OF PAGES INCLUDING COVER:
PHONE NUMBER: SENDER'S PHONE NUMBER:
PROJECT/SUBJECT:
Flow Auto Final ARB Plan (ARB-2018-38)
PLEASE FIND ENCLOSED:
NO.COPIES DATE DESCRIPTION
1 7/18/18 PLANS
1 7/18/18 COMMENT RESPONSE LETTER
1 7/18/18 REVISED APPLICATION SUBMITTAL
NOTES/COMMENTS:
THE APPLICANT ATTEMPTED TO FULLY ADDRESS ALL REMAINING SITE ARB COMMENTS.THE
APPLICANT KINDLY REQUESTS HE BE CONTACTED TO TROUBLE SHOOT ANY POTENTIAL PROBLEMS
SHOULD THE SITE COMMENTS NOT BE CONSIDERED RESOLVED.
SINCERELY,
GRAHAM MURRAY
GRAHAM@COLLINS-ENGINEERI NG.COM
(434)566-3011
RECEIVED BY:
SIGNATURE DATE
COLLINS ENGINEERING 200 GARRETT ST,SUITE K CHARLOTTESVILLE VA 22902
434.293.3719 PH 434.293.2813 FX
www.collins-engineering.com
Ms. Margaret Maliszewski
Chief of Planning
Albemarle County Community Development
401 McIntire Road, North Wing
Charlottesville,VA 22902
RE: Flow Auto Final ARB Plan(ARB-2018-38)
Dear Ms. Maliszewski
Thank you for the comments dated July 9,2018 on our ARB plan submission of Flow Auto. Below is our comment
response letter for the comments.
Architecture
Comments 1-5 are being addressed separately by the Architect and Collins Engineering has coordinated their plans
with the Architect's plans.The Architect will be resubmitting their materials separately.
Site
6. Sheet 6's note has been revised to require the contractor to install bronze light poles.The note now reads,"All
proposed pole lights shall be bronze."
Architecture/Site
7.Collins Engineering has received direction from the Architect multiple times that the guardrails on top of the
retaining walls in excess of 30"will be embedded glass guardrail with a 1"aluminum cap.This will be the
guardrail installed at Flow Auto and Collins Engineering has updated their plans accordingly.The Architect will
be required,per this letter and ARB direction,to update their plans to consistently label the guardrails and to
provide a detail.The applicant hopes that Collins Engineering's plans will be deemed acceptable provided the
Architect submits updated plans reflecting this requirement. In efforts to further ensure Collins Engineering
addresses their portion of this comment their plans have been updated slightly to provide further clarification.
The note on sheet 4 for the front retaining wall adjacent to route 250 has been tweaked.This note now states
handrails are not required here since finished grade wall heights are designed to not exceed 30".Similarly,the
note for the lower seatwall along the eastern side of the building has been revised.This note also now states
handrails are not required since the wall heights are not in excess of 30".There are two walls however that
require handrails.The previously submitted plans specified embedded glass guardrail with a 1"aluminum cap
for the western retaining wall.This requirement remains.The second retaining wall with heights in excess of
30" is the eastern upper retaining wall adjacent to the pedestrian entrance into the building.This note has been
expanded to specify the same embedded glass guardrail with a 1"aluminum cap.The applicant hopes at this
time their plans are to be found satisfactory pending the updated submission of the Architect's plans.
Please let me know if you have any questions or require any additional information for final ARB approval.
Sincerely,
Graham Murray, PE
graham@collins-engineering.com
ram'
BCQSNr 0. C H I T E C i 5
memo
To Margaret Maliszewski
Chied of Planning/Resource Management
Dept. of Community Development
401 McIntire Road, North Wing
Charlottesville,VA 22902
Date 7.18.18
Project Flow Audi-15026
Subject RE:ARB-2018-39: Flow Auto Final
Dear Margaret,
We have revised our Architectural Construction Document set to reflect your comments
dated July 9, 2018. Our responses per comment:
1.We have chosen Glen-Gery"Oyster White with Speck"as it has a more 'mottled' look than
previous brick specified. We will have the selected GC make a mock wall as soon as
possible and coordinate with the ARB to advise.
2. Graniti Fiandre"New Ground Anthricite, honed finish" is still being used and can be
found as F-1 on the Finish Schedule. Fibre C by Rieder is no longer being specified in this
project.
3. There is no real visible difference between Solarban 60 and Solarban 70XL. Solarban
70XL is a more efficient piece of glass. It is not tinted, has a VLT of 64 and a VLR of 12. A
sample is in route if still required.
4. A separate sign package is being worked on and will be submitted at a later date.
5. We've coordinated all of the notes to reflect a single design: "embedded glass guardrail
with 1"aluminum cap"as they are all the same design throughout the site. There should be
no guardrail fronting Route 250.
6. Civil should be changing the Pole lights to bronze.
7. Civil cleaned up the language to reflect a single design across all the guardrails and
denoted more specifically where these are located on the site. There are no'handrails'on
the site and all guardrails are 'embedded glass guardrail with 1"aluminum cap'.
Thank•you.
From Isaac Miller
Assoc Architect
imiller@brw-architects.com
112 fourth street ne I charlottesville virginia 22902 1434.971.7160 I www.brw-architects:com
COLLINS EN G I N I N G ARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
434.293.3719 PH 434.293.2813 FX
www.collins-engineering.com
Ms. Margaret Maliszewski
Chief of Planning
Albemarle County Community Development
401 McIntire Road, North Wing
Charlottesville,VA 22902
5
Ci
RE: Flow Auto Final ARB Plan(ARB-2018-pf/
Dear Ms. Maliszewski
Thank you for the comments dated May 7,2018 on our ARB plan submission of Flow Auto. Below is our comment
response letter for the comments.
Architecture
Comments 1-4 are being addressed separately by the Architect and Collins Engineering has coordinated their plans
with the Architect's plans.
Site
5. A note has been added to the'Lighting Plan'sheet that mandates all proposed pole lights be black. Please also
note,the adjacent properties are slated for renovations following this development.At that time it is intended
the existing pole lights will be upgraded to match Audi's poles.
6. The note in question on sheet 2 has been removed.
Architecture/Site
7.The Site plans have been revised to provide a label consistent with the architectural plans,which now specifies
an 'embedded glass guardrail with 1"aluminum cap' on sheet 4.Sheet 4 has also been updated to direct the
contractor to the architectural plans for the details of this guardrail.
Please let me know if you have any questions or require any additional information for final ARB approval.
Sincerely,
Graham Murray, PE
graham@collins-engineering.com
7/f/
( iARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
COLLINS EN GIN RING
(434.293.3719 PH 434.293.2813 FX
l> www.collins-engineering.com
TRANSMITTAL
❑ FAX ❑ MAIL X DELIVERY
TO: MARGARET MALISZEWSKI FROM:GRAHAM MURRAY,PE
COMPANY: DATE:6/22/18
FAX: TOTAL NO.OF PAGES INCLUDING COVER:
PHONE NUMBER: SENDER'S PHONE NUMBER:
PROJECT/SUBJECT:
Flow Auto Final ARB Plan (ARB-2018-35)
PLEASE FIND ENCLOSED:
NO.COPIES DATE DESCRIPTION
2 6/22/18 PLANS
1 6/22/18 COMMENT RESPONSE LETTER
1 6/22/18 REVISED APPLICATION SUBMITTAL
NOTES/COMMENTS:
THE APPLICANT ATTEMPTED TO FULLY ADDRESS ALL REMAINING SITE ARB COMMENTS.THE
APPLICANT KINDLY REQUESTS HE BE CONTACTED PRIOR TO ISSUANCES OF AN APPROVAL OR
COMMENTS TO TROUBLE SHOOT MINOR ITEMS SHOULD IT BE NECESSARY. k) n�.
SINCERELY, RECE D
GRAHAM MURRAY �+
GRAHAM@COLLINS-ENGINEERING.CO JUN 2 5 1 18
(434)566-3011
Nny
DEVELOPMENT
REC.' VED BY:
SI i' S •E DATE
2/Gl,c
I
34. Delineate the utility easements on the landscape plan(C-600) and the site& utility plan (C-
300). Increase planting area to ensure that there are no conflicts between the proposed
plants and extant/proposed utilities/easements.
35. Extend the proposed tree plantings along the full lengths of the EC frontage.
36. Provide street trees the full length of the Proffit Road frontage,including the southwest
corner of the site, increasing planting area as necessary to eliminate utility conflicts. "
37. Provide one additional interior parking tree.
38. Provide a continuous row of shrubs along the Rt. 29 and Proffit Road frontages.
39. Provide trees and shrubs along the 5-space parking row near the northern entrance to the
site.
40. Note that signage requires a separate application. Ground cover,shrubs and/or trees will
be required to integrate the freestanding signs into the overall development.
41. Consider adding shrubbery to the exterior of the building.
42. Reduce the number of BNH and IV to below 10 and 25 respectively(or below 25%of
typology totals) by introducing more plant variety.
43. Provided the standard plant health note on the landscape plan (C-600):All site plantings of
trees and shrubs shall be allowed to reach, and be maintained at mature height;the
topping of trees is prohibited. Shrubs and trees shall be pruned minimally and only to
support the overall health of the plant.
44. Revise the fuel pump canopy design to reflect a minimalist design.
45. Reduce the height of the fuel pump canopy to comply with the Standards for Fuel Pump
Canopies as outlined in Appendix B of the EC Design Guidelines.
46. Further reduce the footprint of the canopy to more closely meet the canopy standards.
Mr. Hancock seconded the motion. \
The motion carried by a vote of 3:2. (Stoner and Van Der Werf voted no.)
OTHER BUSINESS
a. Brookhill:Visibility from the EC •
After considering the information presented on the visibility of the proposed development, it was the
consensus of the ARB that: 1) given the distance from the EC street, the review of the Brookhill Block 3
Ice Rink Initial Site Plan may be completed by staff, with ARB input at staffs discretion, and 2) the need
for ARB review of the other blocks will be determined after some of the development is constructed.
Mr. Wardell recused himself from Flow Auto and left the meeting at 2:55 p.m. Vice Chair Binsted took
over the meeting.
b. Flow Auto: Light pole color
After considering the proposal to use gray instead of bronze as the light pole color, it was the consensus
of the ARB that bronze should be used for consistency along the corridor,as per the guidelines.
a. Next ARB Meeting: May 21, 2018
ADJOURNMENT
The meeting was adjourned at 3:01 p.m.to the next ARB meeting on Monday, May 21, 2018 in Room 241,
Second Floor, County Office Building at 1:00 p.m.
Albemarle County Architectural Review Board Final Action Memo May 7,2018 6
COLLINS GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
434.293.3719 PH 434.293.2813 FX
www.collins-engineering.com
TRANSMITTAL
o FAX a MAIL X DELIVERY
1O. IAa£6 -r FROM:
Grp-KEN. muaRAY
COMPANY: DATE: Li la3 he
FAX: TOTAL NO.OF PAGES INCLUDING COVER:
PHONE NUMBER: SENDER'S PHONE NUMBER:
113c-1 566 30
PROJECT/SUBJECT: N
ANO
PLEASE FIND ENCLOSED:
NO.COPIES DATE DESCRIPTION
2 `I P3(Ig AR c S
I-) /9-2 118 co/04,51•X R i
NOTES/COMMENTS:
LCsi ' (0./31.Ni kAAte ( aVE-Sr a /1s514.0
- sr O► C i sus
(�pp G � 1134 566 3' I
l�Pa GO,V1� N3 }NKS, As-evnkA.eet; V(1. Cp/'l
RECEIVED BY:
SIGNATURE DATE
COLLINS ,ARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
434.293.3719 PH 434.293.2813 FX
www.collins-en gineering.corn
Ms. Margaret Maliszewski
Chief of Planning
Albemarle County Community Development
401 McIntire Road, North Wing
Charlottesville,VA 22902
RE: Flow Auto Final ARB Plan(ARB-2018-39)
Dear Ms. Maliszewski
Thank you for the comments dated March 30,2018 on our ARB plan submission of Flow Auto. Below is our
comment response letter for the comments.
Architecture
Comments 1-4 are being addressed separately by the Architect and do not impact the attached plans from Collins
Engineering.
Site
5. The notes have been revised to state the retaining wall brick will match the building's brick.
6. Sheet 2's note has been updated accordingly.
7. Additional shrubs have been added around the northwest corner of the display area,as shown on sheet 6.
8. The lighting plan has been corrected and now shows photometrics and cut sheets on sheet 7.
9. A note has been added to sheet 6 mandating these plantings be 24" in height at the time of their plantings.
Architecture/Site
10.Vehicular and pedestrian handrails are not required along the retaining wall paralleling route 250, per Virginia
Building Code requirements and a conversation with Mr. Frank Pohl dated February 27`F'.The wall heights
paralleling route 250 do not exceed 30"and this parking is predominantly for display parking only where
professional drivers will be enlisted to move vehicles.Also,these vehicles will not be moved often,and the one
parking space that is not for display will be at-grade without a retaining wall in front of it. In light of these
updates,a guardrail is not shown in this location and Collins Engineering's plans reflect this.To ensure this
comment is fully addressed though,the limits of the handrails is shown and labeled in the back-rear corner
adjacent to the building on sheet 4.
11.The note on sheet 3 has been revised to now simply label these two areas as landscaped areas.These locations
are simply planting locations and the applicant apologize for any earlier confusion.
12.The plans and labels have been revised.The upper parking lot now proposes to have the same top finish as the
adjacent sidewalk and interior showroom floor.This will provide an at-grade seamless transition.Additionally,
the notes on sheets 3 and 4 have been updated to reference the material's finish(TeknoStone in soft black).
13.This note has been updated to address this comment. Please see the response above to comment#12.
14.This note has been updated to address this comment. Please see the response above to comment#12.
15.The item depicted in the comment letter is a trench drain and is now labeled on sheet 3.This item is not above
the ground and will not be visible from route 250.The trench drain is needed to capture runoff along the
sidewalk.
Please let me know if you have any questions or require any additional information for ARB approval.
Sincerely,
Graham Murray, PE
graham@ collins-engineering.com
RECEIVED
AP* 2 ¢ v
c I COLLINS E N G I Ir a 4 P I N G t, zi,GARRETT ST,SUITE K CHARLOTTESVILLE VA 22902
r 434.293.3719 PH 434.293.2813 FX
www.collins-engineering.com
March 5,2018
Margaret Maliszewski
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
RE: ARB-2016-126 Flow Auto Audi Showroom
Thank you for your comments dated February 6, 2017 on the Flow Auto Audi Showroom ARB
application. Revised plans are hereby submitted incorporating the following changes in response
to the items in your letter.
1. Architectural elevations are provided. The building and retaining walls will be norman
brick with mottled color.
2. The building and retaining walls will be norman brick with mottled color:
3. The existing guard rail will be removed.
4. The project limits has been revised.
5. The IG shrubs have been increased to 24"high minimum at planting.
6. The shrubs extend around the corner of the display area.
7. Top of wall and bottom of wall elevations for the site walls are shown on the grading
plan.
8. Plants are shown along the 10' wall on the east side of the property.
Please contact me if you have any questions or require any further information.
Sincerely,
Scott Collins, PE
COLLINS ENGINEERING 200 GARRETT ST,SUITE K CHARLOTTESVILLE VA 22902
434.293.3719 PH 434.293.2813 FX
www.collins-engineering.com
TRANSMITTAL
❑ FAX ❑ MAIL U DELIVERY
TO: FROM:
MARGARET MALISZEWSKI SCOTT COLLINS
COMPANY: DATE:
ALBEMARLE COUNTY 3/5/2018
FAX: TOTAL NO.OF PAGES INCLUDING COVER:
PHONE NUMBER: SENDER'S PHONE NUMBER:
434.293.3719
PROJECT/SUBJECT:
FLOW AUTO ARB PLAN
ARB2016-126
PLEASE FIND ENCLOSED:
NO.COPIES DATE DESCRIPTION
8 SITE PLAN
8 ARCHITECTURAL ELEVATIONS
1 LETTER
NOTES/COMMENTS:
BUILDING AND ALL RETAINING WALLS WILL BE NORMAN BRICK WITH A MOTTLED COLOR.
RECEIVED BY:
SIGNATURE DATE