HomeMy WebLinkAboutARB201700033 Correspondence 2018-04-09 Heather McMahon
From: Heather McMahon
Sent: Monday, April 09, 2018 11:30 AM
To: 'David Timmerman'
Subject: RE: malloy ford metal sample
Hi David,
Thank you for the clarification, that's helpful. I have approved these revised drawings (A0.0,A3.0,A3.1, and A.3.2) dated
3/20/18.Your CoA is still valid.
Please note that, as per your CoA,the visibility of all mechanical equipment shall be eliminated from the Entrance
Corridor.Although I believe the position of the "New Mechanical Roof and Mezzanine" will not be visible from the EC, it
is still the applicant's onus to ensure that this condition is met.
Thanks,
Heather McMahon, Senior Planner
Albemarle County Department of Community Development
401 McIntire Road
Charlottesville,VA 22902
434-296-5832 x3278
hmcmahon@albemarle.org
From: David Timmerman [mailto:dtimmerman@brucewardell.com]
Sent: Friday,April 06, 2018 5:10 PM
To: Heather McMahon <hmcmahon@albemarle.org>
Subject: RE: malloy ford metal sample
Hi Heather-
I'm just now getting back to the office.
I believe only other change is that there were originally 7 garage doors on the south elevation and now there are only 5
—we had to change the layout some to make the vehicular circulation work.
Hope that helps,
David
david timmerman
brw architects
1 1 2 4th street ne
charlottesville
virginia 22902
[p] 434 . 971 . 7160
www.brw-architects.com
1
From: Heather McMahon [mailto:hmcmahon@albemarle.orq]
Sent: Friday, April 06, 2018 12:12 PM
To: David Timmerman
Subject: RE: malloy ford metal sample
Hi David,
So,these drawings you've attached here: do they differ in any way other than not illustrating the transparent panels on
the south elevation of the warehouse buildings from those drawings approved with your CoA? I will have to go pull those
to verify, but I just want to ask you first...
Thanks,
Heather McMahon, Senior Planner
Albemarle County Department of Community Development
401 McIntire Road
Charlottesville,VA 22902
434-296-5832 x3278
hmcmahon@albemarle.org
From: David Timmerman [mailto:dimmerman@brucewardell.comJ
Sent: Friday, April 06, 2018 12:04 PM
To: Heather McMahon<hmcmahon@albemarle.org>; Margaret Maliszewski<MMaliszewski@albemarle.org>
Subject: RE: malloy ford metal sample
Good afternoon, Heather.
There was some further back and forth on this clear paneling issue and the client has finally decided against using them.
I apologize for the inconvenience.
But per your second point below, I'd like to submit our updated drawings; which have the updated north elevation you
requested.
Does this still need to be submitted with application and as a Minor Amendment?
If not, let me know what I need to turn into your office and I'll drop by next week.
In the meantime, I've attached the revised set for your records.
Thank you and again my apologies for the change in plans...
Have a good weekend,
David
david timmerman
brw architects
1 1 2 4th street ne
charlottesville
virginia 22902
[p] 434 . 971 . 7160
2
www.brw-architects.com
From: Heather McMahon [mailto:hmcmahon@albemarle.orq]
Sent: Monday, March 05, 2018 10:44 AM
To: David Timmerman; Margaret Maliszewski
Subject: RE: malloy ford metal sample
Hi David,
I've heard back from two out of four board members in regard to your request, and although that doesn't quite meet a
quorum, I am going to relate to you that the consensus thus far is that the board has "no objection" to the use of the
translucent material in the isolated spots on the southern elevation of the warehouse buildings which are shown in your
submitted drawing. So please submit an ARB application for a Minor Amendment to Architectural Plans with supporting
materials (including a material sample, if possible)for staff review. (And please be sure to update the elevation drawing
to show the correct number of apertures on the north elevation of the showroom so that confusion doesn't set in...)
Thanks,
Heather McMahon, Senior Planner
Albemarle County Department of Community Development
401 McIntire Road
Charlottesville,VA 22902
434-296-5832 x3278
hmcmahon@albemarle.org
From: David Timmerman [mailto:dtimmerman@brucewardell.com]
Sent:Tuesday, February 27, 2018 4:41 PM
To: Heather McMahon<hmcmahon@albemarle.org>; Margaret Maliszewski<MMaliszewski@albemarle.org>
Subject: RE: malloy ford metal sample
Hi Heather—
I received the final word on this issue of the metal paneling: they will install the Slate Grey—the sample you have on file.
One new minor issue that the ownership was inquiring about—please see the attached warehouse building elevations.
They wanted to see if clear panels (as shown on the North elevation as the 4'x10'grey rectangles)would be allowed?
These would allow some daylight into the work space.
The installer provided photos of what these look like installed—this building is obviously a different color but should give
you the idea.
I apologize for yet another tweak in the design but the G.C. brought it up last week and as a favor I told the owner I
would send this along for your review.
Thank you,
david timmerman
3
brw architects
1 12 4th street ne
charlottesville
virginia 22902
[p] 434 . 971 . 7160
www.brw-architects.com
From: Heather McMahon [mailto:hmcmahon©albemarle.orq]
Sent: Tuesday, February 20, 2018 2:50 PM
To: David Timmerman; Margaret Maliszewski
Subject: RE: malloy ford metal sample
Hi David,
It is an easy question and a quick answer: no,the material sample which we have on file (which was previously
approved)for the cladding of the service buildings in the rear is the Ceco Signature 300 series"Slate Gray." I recognized
on the drawings you submitted for the building permit that you called out"Charcoal Gray" by Ceco, and I looked it up on
the Ceco website; while the latter color is darker than that approved by ARB staff(i.e., the "Slate Gray"), it was not a
significant enough change for me to deny your permit drawings. However, if you choose to revert to the Slate Gray
option,that has been previously approved. If you move forward with the Charcoal Gray option, please drop off a sample
to me and I will update the Approved Building Materials list for ARB2017-33: Malloy Ford.
Thanks,
Heather McMahon, Senior Planner
Albemarle County Department of Community Development
401 McIntire Road
Charlottesville,VA 22902
434-296-5832 x3278
hmcmahon@albemarle.org
From: David Timmerman [mailto:dtimmerman@brucewardell.com]
Sent:Tuesday, February 20, 2018 2:41 PM
To: Heather McMahon<hmcmahon@albemarle.org>; Margaret Maliszewski<MMaliszewski@albemarle.org>
Subject: malloy ford metal sample
Good afternoon Heather and Margaret:
This should be an easy question—I was hoping you could confirm what color sample you have on file for the metal
paneling at the Ford warehouses(behind the new showroom)...?
Our submitted drawings had a "Charcoal Grey" called out ... However, I just wanted to make sure this matches the
sample you have in possession.
Hope you are enjoying the nice weather...take care,
david timmerman
brw architects
1 1 2 4th street ne