Subject: Northside Material Recovery Facility — Final Site Plan (SDP201900033)
The final site plan for Northside Material Recovery Facility has been reviewed by Engineering. The
following comments will need to be addressed before approval:
1. VSMP Plan (WP0201500001) must be amended and approved before final site plan can be
approved.
2. Plans should be signed, sealed and dated by professional. [18-32.6.1]
3. Specify the type of stone for the stone access aisle cross-section. [Sheet C6]
4. Provide a cross-section of the proposed berm.