Loading...
HomeMy WebLinkAboutWPO201900029 Review Comments Erosion Control Plan 2019-06-11COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VESCP Permit Plan Review Project title: Miller School Baseball Field Improvements Project file number: WP02019-00029 Plan preparer: Draper Aden Associates [cbolton@daa.com] Owner or rep.: The Miller School of Albemarle Plan received date: 13 May 2019 Date of comments: 11 June 2019 Reviewer: WW Associates, Inc. Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Please show the location of the construction entrance on the plans. 2. Please show the location of the contractor parking and staging areas on the plans. Note: Total Area of Disturbance z 38,375ft2. The plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re - submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. After bonding is complete, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; hqp://www.albemarle.org/deptforms.ap?del2artment--edengno WP02019-0029 Miller School Baseball Field 06-11-19 WWAssoc