Subject: SDP201900023- UVA Encompass Rehabilitation Hospital - Initial Site Plan
The Planner for the Planning Services Division of the Albemarle County Department Community
Development will recommend approve the plan referred to above when the following items
have been satisfactorily addressed. (The following comments are those that have been
identified at this time. Additional comments or conditions may be added or eliminated based
on further review.) [Each comment is preceded by the applicable reference to the Albemarle
County Code.]
Initial Site Plan Comments:
Required Prior to Initial Site Plan Approval:
1. ZMA2005-3 Proffers: Compliance with the following proffer is needed prior to initial site
plan approval:
a. Proffer 9: Historic resources: Prior to preliminary plat, preliminary site plan, or an
early grading permit in Tract 1, the Owner shall provide a survey to provide
archival record of the existing buildings within Tract 1, and shall meet VDHR
standards.
Required Prior to Final Site Plan Approval:
Planning (Tori Kanellopoulos)
2. 18-4.6.1 Frontage: A new parcel for this proposal is needed, which will have required
frontage on Loop Road. Approval of the road plan for Loop Road is needed before the
final site plan can be approved.
3. 18-4 Zoning overlays: Include the Airport Impact Area (AIA) Overlay District on Sheet
C0.0.
4. 18-32.5.2(k): Easements: Verify that all necessary easements for proposed water, sewer,
and any drainage facilities have been shown on the plan. Show and label existing and
proposed easements on utility plan and indicate if any easements are to be dedicated to
public use.
5. 18-4.1 Watersupplies and sewer systems and Proffers per ZMA2005-3: This site is on
public water and sewer (ACSA). Several of the proffers per ZMA2005-3 dealt with the
Fire Station and connection to public sewer. The site plan appears to show existing
connections to public sewer for the Fire Station. Please confirm if this connection exists,
or label as future proposed connection.
a. Proffers per ZMA 2005-3 (also attached): 8.1(D); 8.4; 8.5
6. 18-4.12.6 Parking: Please provide a letter from the zoning administrator showing the
approved parking requirements for this site, as the hospital use required spaces are
determined by the zoning administrator. If this determination has not yet been made,
please submit a request for the number of spaces needed, under public use and
hospital.
7. 18-4.17 Lighting: Submit a lighting plan with the final site plan that meets the
requirements of 18-4.17 and ARB requirements.
8. 18-32.5.2 Contents of an initial site plan and 18-32.6.2 Contents of a final site plan:
a. Label the use on C0.0 as "Public Use: Hospital"
b. Include the following on sheet C0.0: "Proffers per ZMA2005-3".
c. Include the Magisterial District (Rio) on Sheet C0.0.
d. Also include the Zoning District of adjacent parcels (along with owner and
DB/PG).
e. Include the distance to the centerline of the nearest existing intersection for
ingress and egress.
9. 18-32.7.9.4 Contents of a landscape plan:
a. Sheet L2.1 shows 8 shrubs Sheet L2.0 shows 100 shrubs for a total of 108,
however Sheet L3.0 lists 78 shrubs. Please revise.
b. Include a Conservation Checklist.
10. 18-32.7.9.5: Street trees:
a. Please see ARB comments as well for additional requirements.
b. The Road Plan will need to include the tree information (including caliper) and
count for the required street trees.
11. Consistency with the Comprehensive Plan (CCP) for the use of the site
a. Per LOD2019-14, it was determined that this proposal is considered a "public
use". Staff also determined that a CCP application was needed. Tim Padalino
(Senior Planner) has been coordinating with Elise Cruz, Fred Missel, and Todd
Marshall at the UVA Foundation regarding this application. This application is
reviewed and either approved by the Planning Commission or sent to the Board
of Supervisors by the Planning Commission for final determination. Approval of
the CCP is required prior to final site plan approval.
12. ZMA2005-3 Proffers: Compliance with the following proffer is needed prior to initial site
plan approval:
a. Proffer 9: Historic resources: Prior to preliminary plat, preliminary site plan, or an
early grading permit in Tract 1, the Owner shall provide a survey to provide
archival record of the existing buildings within Tract 1, and shall meet VDHR
standards.
13. ZMA2005-3 Proffers: Compliance with the following proffers per ZMA2005-3 is needed
prior to final site plan approval:
a. Proffer 3.1: Square footage: Include a table, as shown on previous site plans
under this rezoning, that shows total build out.
b. Proffer 4.3: Wetlands: Label the location of the wetlands area for future open
space.
c. Proffer 5.2: Internal roads must be dedicated for public use. Label Loop Road as
public and please confirm that this is a public street.
d. Proffer 7.1: Landscaping and roads: All roads in the project must be landscaped
according to "Exhibit D: UREF's North Fork Street Tree Master Plan", filed with
Albemarle County on November 1, 1994. Ensure that the road plan for Loop
Road meets these landscaping standards.
e. Proffer 8: Fire Station
i. Proffer 8.1(D): The septic drainage field that was serving the Fire Station
must be closed and removed once the Fire Station is connected to public
sewer.
1. The submitted plat (under review by Tim Padalino) cannot be
approved until the connection to public sewer is made. The plat
shows the drainfield off -site, and drainfields must be on the same
parcel as the use they serve.
ii. Proffer 8.4: Prior to final plat or plan approval in this section of the
rezoning per ZMA2005-3 (Tracts 1 and 2 on Exhibit J): "the Applicant shall
design and construct at its sole expense, or provide sufficient bond or
other form of surety to the County in an amount sufficient to assure
construction and acceptance by the appropriate authority, a public sewer
to serve the Fire Station Parcel and, in conjunction with such construction
and upon request by the developer of the Fire Station Parcel, shall install
a lateral from the public sewer that connects the Fire Station to the
public sewer. If such a request is made, the developer of the Fire Station
Parcel shall reimburse the Applicant for its costs to design and install the
lateral, and shall pay all fees required for connecting the Fire Station to
the public sewer system."
1. Label the SAN Lateral connection to the Fire Station as "Future
Proposed SAN Lateral". This connection has not yet been made.
iii. Proffer 8.5: Once the Fire Station is connected to public sewer, the
applicant shall dedicate the Fire Station Parcel to the County within 90
days. This area is approximately 2.55 acres and is shown on Exhibit B with
the proffers approved with ZMA2005-2.
iv. Proffer 8.6: Road connection: Coordinate with Plan reviewers on the
Road Plan to ensure this connection is satisfactorily made.
14. ZMA2005-3 Proffers: Compliance with the following proffers is needed in future stages
of development. This is for informational purposes:
Proffers 5.3 and 5.4: All road improvements required on the application plan
(Exhibit M) for Phase I must be completed or bonded before the maximum build -
out of Phase 1, based on square footage of uses. Or, VDOT must determine that
the intersections will still function at an acceptable level, as described in these
proffers. This includes the intersection of SR 649 (Airport Road) and Road A
(Lewis and Clark Drive).
i. These improvements are described in detail in Proffer 5.4(B).
ii. These improvements must meet the landscaping and buffer standards in
Proffer 7.2
b. Proffer 6.1: Recreation space: Must be completed prior to maximum build -out of
Phase I.
15. Additional applications: The following applications and approvals are required prior to
final site plan approval:
a. 18-32.7.4.2 and 18-32.7.5.3: Easement Plats: It appears no private easements or
public non-ACSA easements are proposed. Any non-ACSA or private easements
must be included on an easement plat.
b. 18-32 and 14: Subdivision plat: A subdivision plat is needed prior to final site plan
approval. This plat has been submitted and is under review. Compliance with all
applicable ZMA2005-3 proffers is also needed prior to final plat approval.
c. 18-32.7.2 and 14: Approval of road plans is required prior to final site plan
approval. Proffer 5.2 refers to internal roads being public roads.
d. 18-32.7.4.1: Approval of VSMP Plans is required prior to final site plan approval.
Engineering (Matt Wentland)
1. The UVa Research Park Loop Road VSMP and Road Plans will need to be approved
before the Final Site Plan can be approved and both will need to be bonded prior to
issuance of a grading permit for this plan.
2. The VSMP plans will need to be approved before Final Site Plan approval.
VDOT (Adam Moore)
1. See attached review comments.
Fire/Rescue (Shawn Maddox)
1. Due to the height of the building exceeding 30' the travel way must be 26' clear travel
width.
2. A knox box will be required. Please add a note indicating this requirement and that
location can be coordinated with the fire marshal's office.
3. The canopy shown at the main entrance should have a minimum clear height of 13' 6".
4. A fire flow test of the new hydrants will be required prior to final acceptance of the site.
ACSA (Richard Nelson)
1. Submit 3 copies to ACSA for review.
2. Final approval will not be given until final approval of the UVA Loop Road.
3. Final approval will not be given for Lewis and Clark designs until ACSA receives an
updated master plan.
4. Confirm if the second water meter is a redundant feed to the hospital. If so it will need
to be relocated to the other side of the site.
5. RWSA Sewer capacity certification will be required.
6. Confirm uses and licensing agency to ACSA to determine capacity fees.
7. North Fork South Zone Special Rate Fees apply.
RWSA (Dyon Vega)
1. See attached review comments.
Health Department (Alan Mazurowski)
1. No objection — see attached.
Inspections (Michael Dellinger)
1. No Objection.
Architectural Review Board (Margaret Maliszewski)
1. Administrative ARB approval. See attached review comments.
E911 (Andy Slack)
1. No Objection.