Loading...
HomeMy WebLinkAboutSUB201600196 Review Comments Road Plan and Comps. 2019-07-05County of Albemarle Department of Community Development 401 McIntire Road, Charlottesville, VA, 22902 434-296-5832 Memorandum To: Matthew Wentland From: Christopher Perez, Senior Planner Division: Planning Date: July 5, 2019 Subject: SUB2016-196 North Pointe Route 29 Improvement Plan — Road Plan The County of Albemarle Planning Division will recommend approval of the plan referenced above once the following comments have been satisfactorily addressed: [ZMA2013-14] Proffer 2.1 requires a 40-foot buffer along the Route 29 Entrance Corridor. Provide a landscaping plan sheet and show buffer location and plantings in accordance with this proffer. It appears there may be a conflict with the retaining wall that would not allow adequate width for the buffer in certain locations as well as potential utility conflicts. Some redesign may be needed to accommodate the requirements of this proffer. Rev 4. Comment addressed. 2. [ZMA2013-14, ZMA2000-91 Proffer 5.3.3. Prior to road plan approval provide documentation from VDOT that confirms this proffer is addressed. 5.3.3 Prior to the approval of plans for improvements at any U.S. Route 29 intersection, Owner shall provide VDOT traffic signal network timing plans that VDOT finds acceptably address the impacts of the proposed traffic signals for peak traffic periods. 3. [ZMA2013-14 Proffer 5.3.1(c), SP2006-34 Conditions] The road plan shall not be approved until SP conditions #4 and #2 have been satisfied. Condition #4: County approval of a grading and erosion and sediment control plan prior to issuance of a grading permit for modification of the existing stream crossing. Condition #2. County and VDOT approval offinal design plans and hydrologic/hydraulic computations for the stream crossing. Proffer 5.3.1(c) stipulates that prior to the approval of a subdivision plat or a site plan that the Owner must obtain all associated permits and post all associated bonds required to construct the phase III road improvements. The grading and erosion and sediment control plan cannot be approved by the County until the final design plans and hydrologic/hydraulic computations for the stream crossing are approved by VDOT and the County. Please submit the final design plans and hydrologic/hydraulic computations for the stream crossing to VDOT and the County for review. Please contact Christopher Perez in the Planning Division by using cperezkalbemarle.org or 434-296- 5832 ext. 3443 for further information.