HomeMy WebLinkAboutSUB200400102 Other 2019-08-26Upper Ballard Storm Drain Inspection: Wednesday, February 14, 2018
Camera inspector: Andrew Weldon (A.G. DILLARD)
Visual Inspectors: Andrew Weldon, Dale Banton (A.G. DILLARD), Dan Staples (RGA)
Pipe/Man Hole Number
Description
STM 22 TO 24
Video inspection. No cracks to structures or pipe,
no standing water or debris build up. All pipe
joints are sealed, no settling or buckling of the
pipe.
STM 22 TO 60
Video inspection. No cracks to structures or pipe,
no standing water or debris build up. All pipe
joints are sealed, no settling or buckling of the
pipe.
STM 24 TO 26
Video inspection. No cracks to structures or pipe,
no standing water or debris build up. All pipe
joints are sealed, no settling or buckling of the
pipe.
STM 60 TO 68
Video inspection. No cracks to structures or pipe,
no standing water or debris build up. All pipe
joints are sealed, no settling or buckling of the
pipe.
MH 72
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 76
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 4
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 12
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 54
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 31
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 30
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.
MH 38
Visual inspection. No damage to manhole
structure, no standing water or debris in pipe, no
cracks or crushes in pipe were observed.