HomeMy WebLinkAboutWPO201800068 Review Comments 2019-01-28 Dewberry Dewberry Engineers Inc. 804.290.7957 4805 Lake Brook Drive, Suite 200 804.290.7928 fax Glen Allen,VA 23060 www.dewberry.com January 28, 2019 County of Albemarle, Department of Community Development Attn: David James, VSMP Reviewer 401 McIntire Road, Room 227 Charlottesville, VA 22902-4596 RE: ACSA Operations Center Expansion Parking Lot Expansion 2"d Re-submission Project File Number: WPO201800068 Dear Mr. David James, On behalf of the Albemarle County Service Authority, Dewberry Engineers Inc. is pleased to submit for your review and approval the final plans for the ACSA Operations Center Expansion Parking Lot Expansion revised per three(3) sets of county comments. Two(2)copies of the Final Design(100%) plans signed November 12, 2018 are being submitted for your review. Below are the comments along with responses (shown in bold) that were received from your review dated December 21, 2018. C. Pollution Prevention Plan(PPP) The PPP content requirements can be found in County Code section 17-404. 1. Show any proposed clearing/grading activities, paving operations, landscaping operations, E&S controls, staging, stockpile,borrow, fueling, waste disposal, vehicle/equipment washing, concrete washout locations on the PPP. (Rev.1)Partially addressed. Show all E&SC and clearing/grading operations.Turn off existing contours & use thicker linetype for LOD (for clarity). (Rev. 1) Response: All ESC measures and demolition and grading activities are included on the PPP. Existing contours have been turned off and the LOD has been more clearly defined. D. Stormwater Management Plan(SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.This plan is disapproved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17-403. 4. Submit the VRRM spreadsheet, pdf is fine. a. (Rev.1)You're showing use of a MTD-Filtering that treats 0.22 Ac.The only proposed SWM facility shown in the plans is the underground detention system and is not a filtering device.Please revise VRRM. (Rev. 1)Response: The Manufactured Treatment Device that was shown in the VRRM has been removed. The total phosphorous removal required remains the same as before-0.35 Page 1 of 3 Mr.James ACSA Operations Center Expansion Parking Lot Expansion W P0201800068 15t Submission Comment Responses • lb/year, the MTD was not providing any treatment. There is no treatment provided onsite for this project. All treatment is provided by the purchase of nutrient credits. b. (Rev.1) In the `Runoff Volume and CN Calculations' summary table incorrect precipitation values are given for the location per NOAA Atlas 14. Please revise VRRM.I 11 12-hr II (224 2.90) I (2.69-3.50) I (3.34-4.35) ,I (3.95 5 15) 24tu 3.03 3.66 4 S8 5.54 (2.72 3.40) (3.29.4.12) (4.19-5.26) (4.94 6.20) (E(E 6.48 2-may (3 20 3.99) (3.89-4.84) (4:3-6 15) (5.$n) I t� (Rev. 1)Response:The rainfall data has been updated. 5. Sheet C6.0—Provide analysis/computations to verify the discharge values shown at the outfall points. (Rev.1)Partially addressed. Should the D.A.Onsite be 0.23ac,not 0.32ac(Please verify)? (Rev. 1)Response: DA Onsite has been updated to 0.23 ac. 8. Sheet C6.3—Energy Balance worksheet shown is confusing! (Rev.1)Sheet C6.2: `Energy Balance - Outfall 1' -Provide analysis/verification of each outfall, where do you get your Runoff Volume (RV)values of 0.020 ac-ft (pre-dev) & 0.058 ac-ft(post-dev).Doesn't appear to correlate with VRRM(0.11ws-in)or Routing (0.0524. `Energy Balance- Outfall 2'—Should the value be 0.08cfs (Pre-development discharge),not 0.18cfs (Please verify)? Same thing as above,where did you get your RV values? (Rev. 1)Response: For both outfalls, the Runoff Volume(RV) is calculated using TR-55 to obtain"Q (in)."The Q is multiplied by the DA(ac) and converted to get the volume in ac-ft. The RV does not match the VRRM numbers because there are two outfalls on this project and therefore each outfall has a different RV because of the different drainage areas. The pre development RV for Outfall 1 (0.020 ac-ft)matches the existing site area runoff volume calculated in Hydrocad as shown on sheet C6.3 "Existing Conditions—Ex Onsite." The volume for the"Ex AO 1" is different because there is offsite area calculated for the outfall because of the existing parking lot that is detained in the detention pipes. Outfall 2-The existing flow has been updated to 0.08 cfs.The outfall meets channel protection. 10. [New] (Rev.1)SWM easement plat & deed of dedication must be reviewed/approved/recorded prior to VSMP plan approval. (Rev. 1)Response: Acknowledged. 11. [New] (Rev.1)Include this checklist in the plan set. http://www.albemarle.ore/unload/images/forms center/departments/Community Develo pment/forms/Ent ineerine and WPO Forms/WPO VSMP Construction Record Drawi Dewberry. Page 2 of 3 Mr.James ACSA Operations Center Expansion Parking Lot Expansion W P0201800068 1"Submission Comment Responses nes Policy 23Mav2014.pdf (Rev. 1)Response: The checklist is included on Sheet C6.2. E. Erosion and Sediment Control Plan(ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved,.and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 5. Show any offsite improvements including grading operations in a permanent easement. Provide evidence that neighboring property owner is in agreement with this offsite work in the easement. This can be a letter of agreement signed by neighboring property owner. (DSM, Sect. 8C,3F) (Rev.1)Partially addressed. Rename/show label as mentioned above on sheet C3.1. (Rev. 1)Response: Previous discussions between ACSA and the Site Plan Reviewer resulted in the easement being labeled"Permanent Grading Easement."This has been depicted on Sheet C3.1. This letter is provided as part of the resubmittal process and addresses all of the comments above. If you have any questions or require clarification please let us know. Sincerely, Z7;0. iivtivIdOL Kevin A. Pennock ti! Dewberry Page 3 of 3