Loading...
HomeMy WebLinkAboutARB201900021 Correspondence 2019-03-12 Margaret Maliszewski From: Justin Havenner <justin@christophercompanies.com> Sent: Tuesday, March 12, 2019 1:16 PM To: Margaret Maliszewski Subject: FW: Stonefield Proposed Strip Drawings Attachments: original lots 7-11.pdf; originial lots 68-74.pdf Margaret please see attached and below. This is what I'm hoping you need to satisfy"#2" in your list of items requested from me. There are the original approved strip drawings for the noted strips. Justin From: Ibingaman@devereauxarch.com <Ibingaman@devereauxarch.com> Sent:Tuesday, March 12, 2019 12:44 PM To:Justin Havenner<justin@christophercompanies.com> Cc:Jim Buehler<Jim@christophercompanies.com> Subject: RE:Stonefield Proposed Strip Drawings Justin—the attached are 2 of 3 strip elevations that were approved in the early process (the 3rd strip you are not requesting).So I marked up what lots they are and what elevations/models they were. I think this is what she is asking for?Also,we never did ARB elevations for end unit lots 75 or 12. So are you good on the materials/colors?She will just reference that? I will adjust to be 1/8" scale. Laura Bingaman Associate �J g,e/i-eiaux CLT daroGhAr; /e 1477 Chain Bridge Rd.Suite 200 Mclean,VA 22101 Phone:(703)893-0102 Fax:(703)893-0106 1 • Margaret Maliszewski From: Justin Havenner <justin@christophercompanies.com> Sent: Tuesday, March 12, 2019 1:13 PM To: Margaret Maliszewski Subject: FW: Stonefield Proposed Strip Drawings Attachments: Stonefield Color Board 5-21-15.pdf Margaret—here is the color scheme,we are not changing the colors. Justin From: Margaret Maliszewski<MMaliszewski@albemarle.org> Sent:Thursday, March 7, 2019 5:50 PM To:Justin Havenner<justin@christophercompanies.com> Subject: RE: Stonefield Proposed Strip Drawings Justin, I've received your application and I've looked through the submittal.The submittal checklist includes the following requirement: "Dimensioned architectural elevations of the existing condition and the proposed changes. Elevations must be drawn to the scale of 1/8" = 1'. Include a building materials schedule and key on the elevation drawings." I want to be sure I fully understand the changes that you are asking to make, but I'm having a little trouble, in part because this checklist requirement was not met. 1. The corresponding approved elevations were not provided for comparison. I'll need you to provide those for each of the models illustrated, or indicate which elevations in the original approved set I should be looking at. (For example, indicate that the original 20'townhome Elevation Al corresponds to Poe.) 2. Provide the elevations at 1/8" scale. 3. Identify the building materials and colors on the proposed elevations sheets. Please submit this information within 15 days so we can proceed with review of this application. Thanks. Margaret From: Margaret Maliszewski Sent: Monday, February 25, 2019 1:02 PM To: 'Justin Havenner'<iustin@christophercompanies.com> Subject: RE:Stonefield Proposed Strip Drawings Please mail 2 copies with the application and checklist. From:Justin Havenner<justin@christophercompanies.com> Sent: Monday, February 25, 2019 12:17 PM To: Margaret Maliszewski<MMaliszewski@albemarle.org> Subject: RE:Stonefield Proposed Strip Drawings I have almost finished filling out the application and checklist. On the checklist is says I need to send in 8 folded copies of plans/docs. Do I need to send in the 8 copies with these filled out application/checklist and mail it to you? 1