May13, 2016
Mr. Matt Wentland
Civil Engineer
County of Albemarle
Department of Community Development
Regarding: Inglewood Terrace—WPO-2016-00007
VSMP Permit Comments
Dear Mr. Wentland,
Thank you for your review of the preliminary site plan for Inglewood Terrace. We have revised the
plans per County comments dated February 22, 2016. Please find below a detailed comment response letter
describing the changes we have made to each of your comments.
SWMP
1• Soil data has been added. The site is all 39D soil.
2. The director of community development has done his own study of the stream and confirmed that it is an
intermittent stream. No further studies will be performed.
3. The calculations and analyses for this plan have been included with this submission.
4. Pipe profiles are correct, they just look very similar. The overflow stubout has been removed from detention
pipe C.
5. The culvert will use a standard endwall, designs for this will be provided when we have a retaining wall
design contractor selected.
6. Profiles have been included.
7. The channel will have a rip-rap swale for erosion protection.
8. Maintenance agreement will be provided on subsequent submissions.
9. A retaining wall design contractor has not been selected, plans will be provided with next submission. The.
100 year storm WSE was incorrect,it will flood to a maximum elevation of 518.5', safely below the wall top
elevation of 526'. .
ESCP
1. The erosion control plan is now staged to address this issue and for minimal disturbance during
construction. .
If you have any questions please feel free to contact me via e-mail at keane@shimp-engineering.com or Justin
Shimp at Justineshimp-engineering.com or by telephone at 434-227-5140.
Sincerely,
Keane Rucker, E.I.T.
Shimp Engineering