HomeMy WebLinkAboutSDP201800084 Review Comments 2019-08-21 1010
DELTA AIRPORT
CONSULTANTS, INC.
August 21, 2019
. -nror Planner
Planning Department
County of Albemarle
401 McIntire Road
Charlottesville,VA 22902
Subject: SDP201800084 Parking Lot and Apron Expansion—Minor Amendment
Charlottesville-Albemarle Airport
Dear Mr. Perez:
Please find enclosed the revised plans for the above referenced project at the Charlottesville-Albemarle
Airport.
In Response to the August 16, 2019 comments, Delta offers the following:
Comment: [32.52(C), 36.6.2 (a)] Phasing:
The landscaping island fronting the pavilion can remain; however, if it is not proposed to be installed
either remove the proposed plantings or provide a phase line around these plantings to indicate
phase 2 and provide an estimated date of beginning and completion for this phase. Additionally,
sheet L101-4 depicts proposed replacement plantings throughout the existing parking lot; however,
in follow-up emails it has been stated that these improvements will be pushed to a future date.
Either remove the proposed plantings or provide a phase line around these plantings to indicate
phase 2 and provide an estimated date of beginning and completion for this phase. Rev 2. Comment
not addressed. I offer the following clarification:
If the landscaping is to be removed now but not replaced till Spring of 2020, revise all reference to
"Phase 3" for this landscaping and replace with reference to "Phase 1". Additionally, be aware that
this landscaping will be required to be bonded with the County for a 1-year period to allow the
replacement of the landscaping to be postponed.This shall take place with the final inspection of
the phase 1 parking lot expansion.
If the landscaping is to be removed in the Spring of 2020 and replaced in the Spring of 2020,then
the "Phase 3"label is appropriate, provide the following note next to the phasing: "Phase 3
landscaping is to be removed in the Spring of 2020 and replaced in the Spring of 2020".
Response: The landscaping sheets L101-4 through L103-4 have been revised. "Landscape Phase
Note: Phase 3 Landscaping is to be removed in the Spring of 2020 and replaced in the
Spring of 2020" has been added to the bottom of each sheet.
2700 POLO PARKWAY, MIDLOTHIAN VA 23113
P. (804) 275-8301 F. (804) 275-8371 WWW.DELTAAIRPORT.COM
t41.
I.
Building Inspection Comments:
Add the following notes to the general notes page:
1. Retaining walls greater than 3 feet in height require a separate building permit. Walls exceeding
4 feet in height require a stamped engineered design also. Walls require inspections as outlined
in the USBC.
2. Accessible parking spaces and access isles shall not have a surface slope greater than 1:48.
Access isles shall be at the same level as the parking space they serve.
3. ALL water lines, sewer lines, and fire lines from the main to the structure MUST have a visual
inspection performed by the building department.
4. All roof drains shall discharge in a manner not to cause a public nuisance and not over sidewalks.
Response: The requested notes has been added to the General Layout, Critical Slopes, and Project
Notes Sheet C101-1.
Thank you for your review. Should you have any questions, please call our office.
Sincerely,
rVjaketifivu
William M. Eschenfelder, P. .
Enclosures:
Cc: Jason Devillier,CHO w/o encl
Delta Project No. 17018/17019