HomeMy WebLinkAboutWPO201900021 Bond Estimates 2019-10-23 (2)Project Name: UVA Research Park Loop Road VSMP Plan WP0201900021
WPO file number: WP0201900021
TMP(s): 03200-00-00-006R0, 03200-00-00-01800
Date Estimate Completed: 10/22/19
Erosion and Sediment Control Bond Estimate
Item Item No. Unit Unit Cost Cost
Number installed
1 stablization (PS, TS) 4.7 acres $5,000.00 $23,300.00
2 silt fence (SF) 1316.0 ft $5.00 $6,580.00
3 tree protection (TP) 458.0 ft $5.00 $2,290.00
3 safety fence (SAF) 200.0 ft $5.00 $1,000.00
4 diversion (DID, FD, RWD) 1260 ft $13.00 $16,380.00
5 temporary slope drain (TSD) pipe length 45 ft pipe diameter 15 in $35.00 $2,075.00
13 Sediment Trap #1 _
14 earthwork for trap/basin
15 height of dam at toe SO
ft cut at high sideMdft
ft
16 height of fill at faceft cut at face ft
17 length of damft length of cut ft
18 top width ft width of cut
19 (area above transition 0 sf (area below transiti( 112 sf
20 (total width of dam) 6 ft (total width of cut) 42 ft
21 (height below transitio 3 ft (depth below transit 3 ft
22 (area below transition 0 sf (area above transiti 54 sf
23 (total fill volume) 0.0 cy (total fill volume) 215.2 cy
24 length of spillway ft (TOAL CY estimate 215 cy $13.00 $2,795.00
25 width of spillway ft (spillway stone tons 17.6 tons $50.00 $880.00
26 Sediment Trap #2
27 earthwork for trap/basin
28 height of dam at toe 3 ft cut at high side 6 ft
29 height of fill at face cut at face 4 ft
30 length of damn2ft
7 ft length of cut L=40ft
31 top width 3 ft width of cut ft
32 �-- Qoove transition 1- �-- —ow transiti( 92 sf
33 (total width of dam) 6 ft (total width of cut) 35 ft
34 (height below transitio 1 ft (depth below transit 2 ft
35 (area below transition 2 sf (area above transiti 31 sf
36 (total fill volume) 51.6 cy (total fill volume) 182.2 cy
37 length of spillway ft (TOAL CY estimate 199 cy $13.00 $2,587.00
38 width of spillwayWft (spillway stone tons 12.1 tons $50.00 $605.00
39 structures for basin
40 riser height 0 ft
10/29/2019
Project Name: UVA Research Park Loop Road VSMP Plan WP0201900021
WPO file number: WP0201900021
TMP(s): 03200-00-00-006R0, 03200-00-00-01800
Date Estimate Completed: 10/22/19
Erosion and Sediment Control Bond Estimate
Item Item
No. Unit
Unit Cost
Cost
Number
installed
41 riser diameter
in
(riser unit price)
$0.00
$0.00
42 barrel lengthMin
ft
base plate or fdn
$200.00
$0
43 barrel diameter
(barrel . price)
$0.00
$0.00
44
barrel collars
$200.00
$0
45
baffle length
Mft
$50.00
$0
46
47 silt fence inlet protection (IP)
$100.00
$100.00
48 stone inlet protection (IP)
$200.00
$2,200.00
49 outlet protection (OP)-@ Str 200 length
9 ft
width
ft
$364.50
$364.50
50 outlet protection (OP)-@ Str. 300 length
9 ft
width
ft
$243.00
$0.00
51 outlet protection (OP) length
0 ft
width
0 ft
$0.00
$0.00
52 channel (SCC, matted) length
0 ft
width
0 ft
$0.00
53 check dam depth in channel
0 ft
channel width
0 ft
$0.00
$0.00
54 construction entrance (CE)
$2,500.00
$0.00
55 wash rack
$2,000.00
$2,000.00
56 paved construction entrance
$3,500.00
$3,500.00
57 rip -rap, placed depth
0 ft
length `
Aft
58 width
(tons)
0 tons
$60.00
$0.00
59
6o survey and layout (price per 0.1 mi.) acres
traps and basins
$3,330.00
61 mobilization
$2,500.00
62 Temporary Access road
$500.00
cost sum
$72,986.50
WP0201900021 UVA Research Park Loop Road_ESC_bond_est
102219Ja rev 102919
contingency
$7,298.65
Total
$80,290
10/29/2019