HomeMy WebLinkAboutSUB201900097 Correspondence 2019-07-18From:
John Anderson
Sent:
Monday, July 8, 2019 10:18 AM
To:
kurtgloeckner@gmail.com
Cc:
Tori Kanellopoulos
Subject:
2265 Decca Lane plat / WPO plan - once plat /WPO plan approved [
WP0201900035, SUB201900097 ]
Kurt,
Thanks for your call earlier this morning.
Note: DEQ coordination (steps listed below) is not required for 2265 Decca Lane WPO /VSMP
Application.
I will be away 18-30 Jul, 2019 —will not be able to respond to email, and regret any inconvenience.
Thanks again, take care,
J. Anderson
434.296-5832 -x3069
[ fyi, Next steps, below, an unrelated project ]
From: John Anderson
Sent: Tuesday, June 04, 2019 11:57 AM
To: Seth Roderick <sroderick@monteverdedesigns.com>; Elam Summey
<esummey@monteverdedesigns.com>; Tyler Jones <tjones@r717.net>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tom Shumate Jr <tomjr@tomshumatesurveyor.com>;
Andy Reitelbach <mreitelbach@albemarle.org>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
Seth,
Next steps:
1. LS revises plat (ref county email sent 6/4/2019 11:40 AM)
2. CDD reviews /accepts plat
3. CDD FWD .PDF of plat to CAO (ref. 6/4/2019 11:40 AM)
4. SWM Facility Maintenance Agreement executed
5. County records Maintenance Agreement
6. County formats deed (a CAO template) using parcel -ownership information from Maintenance
Agreement, and Agreement deed bk.-pg. ref.
7. Applicant submits signed -notarized deed (signatures should match Maintenance Agreement)
8. Applicant submits LS-sealed plat w/ notarized owner signature/s to CDD/Engineering, with deed
(item 7)
9. CDD/Engineering routes to CAO for county (attorney /executive) signatures
10. Signed deed /plat returned to CDD
11. CDD notifies Applicant plat /deed available for pickup /recordation
12. Applicant records deed
13. Applicant sends circuit court receipt of recordation to Engineering (deed bk.-pg.)
14. Engineering registers project with DEQ, entering data in DEQ SWCGP database
15. DEQ reviews registration
16. DEQ requests payment of state -portion of VPDES permit fee (emails jgykmofpay.com -listed on
registration statement)
17. DEQ receives payment; Agency sends email receipt to Applicant /entity submitting payment
18. Applicant FWD e-receipt of DEQ payment to Engineering
19. At this point, project eligible for pre -construction meeting / Grading permit
20. Use form to request preconstruction meeting. Final county -portion of fee required with
preconstruction meeting request form
21. Link to form:
http://www.albemarle.org/upioad/images/forms center/departments/Community Development/fo
rms/Engineering and _WPO_Forms/WPO_Pre-Construction Meeting_ and Permit_Request.pdf
I hope this helps —thanks Seth
best, I Anderson 434.296-5832 -0069
From: Seth Roderick <sroderick@monteverdedesigns.com>
Sent: Tuesday, June 04, 2019 10:18 AM
To: John Anderson <]anderson2@albemarle.org>; Elam Summey
<esummey@monteverdedesigns.com>; Tyler Jones <t5ones@r717.net>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tom Shumate Jr <tomlr@tomshumatesurveyor.com>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP.
Approved pending ]
Thank you for the update, John. Do you have an ETA for the formal approval of the various docs and
issuance of a permit? Understanding that bond will need to be placed prior to issuance; Michael has
indicated he has the bond ready, pending approval of the estimate and other docs.
Thanks,
Seth Roderick, PE
540-820-0898
From: John Anderson <janderson2@albemarle.org>
Sent: Tuesday, June 4, 2019 9:42 AM
To: Elam Summey <esummey@monteverdedesigns.com>; Tyler Jones <tlones@r717.net>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tom Shumate Jr <tomlr@tomshumatesurveyor.com>;
Seth Roderick <sroderick@monteverdedesigns.com>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
All, plans are here in my office, and have been, in plain sight. Thanks, and please accept my apology.
Ana has ESC -SWM plan bond estimate amounts, but only just received them Sunday. Thanks again
From: Elam Summey <esummey@monteverdedesigns.com>
Sent: Tuesday, June 04, 2019 8:49 AM
To: John Anderson <ianderson2@albemarle.org>; Tyler Jones <tiones@r717.net>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tom Shumate Jr <tomir@tomshumatesurveyor.com>;
Seth Roderick<sroderick@monteverdedesigns.com>
Subject: RE: Planning Application Review for WPO201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
John,
Were you able to locate the submitted plans?
Elam Summey, PE
Monteverede Engineering & Design
(540) 820-3574
www.MonteverdeDesigns.com
From: John Anderson <ianderson2@albemarle.org>
Sent: Monday, June 3, 2019 9:22 AM
To: Tyler Jones <tiones@r717.net>
Cc: Elam Summey<esummev@monteverdedesigns.com>; Michael McGinnis <mmcginnis@r717.net>;
Tom Shumate Jr <tomir@tomshumatesurveyor.com>
Subject: RE: Planning Application Review for WPO201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
Thanks, Tyler, let me search —thanks for writing
From: Tyler Jones <tiones@r717.net>
Sent: Monday, June 03, 2019 7:06 AM
To: John Anderson <janderson2@albemarle.org>
Cc: Elam Summey <esummey@monteverdedesigns.com>; Michael McGinnis <mmcginnis@r717.net>;
Tom Shumate Jr <tomir@tomshumatesurveyor.com>
Subject: RE: Planning Application Review for WPO201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
Good Morning John,
I sent you the email attached above on May 15 that I had dropped off all the hard copies of the plans at
the front desk of your office. They assured me you would receive them.
Thanks,
Tyler Jones
Accounting Coordinator
Innovative Refrigeration Systems, Inc
373 Mt. Torrey Rd., Lyndhurst, VA 22952
(540) 941-2069
tiones(@r717.net
Connect with us ID L_L.�� 0
http://www.r7l7.net "
style='position:absolute;margin-Ieft:20.1pt;margin-top:-
.55pt;width:211pt;height:64.85pt;z-
index:251659264;visibility:visible;mso-wrap-
style:square;mso-width-percent:0;mso-height-
pe rce nt:0; mso-wra p-distance-I eft:9 pt; mso-wra p-d ista nce-
top:0;mso-wrap-distance-right:9pt;mso-wrap-distance-
bottom:0;mso-position-horizontal:absolute;mso-position-
horizontal-relative:text;mso-position-
vertical:absolute;mso-position-vertical-relative:text;mso-
width-percent:0;mso-height-percent:0;mso-width-
relative: page; mso-height-relative: page'
AM
wsM �ooti.v. •s�.�
••
i�111t •Tninlr�
From: John Anderson [mailto:ianderson2@albemarle.org]
Sent: Sunday, June 2, 2019 2:23 PM
To: Elam Summey <esummey@monteverdedesigns.com>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tom Shumate Jr <tomlr@tomshumatesurveyor.com>;
Tyler Jones <tlones@r717.net>
Subject: RE: Planning Application Review for WPO201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
Elam,
We haven't corresponded for a while, so want to ask if I've overlooked item 4., below. Please let us
know if print plans have been submitted, or if you have any questions re. email, below.
I just sent Ana values she needs for bonds —it's been busy, thanks for your patience. ( Ana is quite busy,
as well.)
best, J. Anderson 434.296-5832 -0069
From: John Anderson
Sent: Monday, May 13, 2019 3:18 PM
To: Elam Summey <esummey@monteverdedesigns.com>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tom Shumate Jr <tomir@tomshumatesurveyor.com>;
Tyler Jones <tlones@r717.net>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP. [
Approved pending ]
Elam, thank you
1: Wherever project ID WPO201900005 appears on SWM plan, ESC plan, or SWPPP, please revise to
read WPO201900024.
2: Please revise consolidated project plan title to read (likely, sheet 1 of ESC Plan): Hillcrest Vineyard &
Winery LLC - VSMP /WPO201900024 —this is important
3: Consolidate final print ESC —SWM plans as one, for stamped approval. Combine ESC /SWM plans as
a single plan set.
4: We need four (4) print copies of a unified plan; 2 print copies of 11" X 17" ESC /SWM Plan SWPPP
inserts.
5: Next steps: bond estimate request form (w /$250 fee); print submittal; plat, rev. to address Planning
comments; plat recordation; VAR10; bonds posted for Grading Permit
Also, please read, below
Ref. Attached ESC /SWM bond estimate forms. Please do not change unit prices, but revise qty. values
to match this plan. Important: Applicant is not required to complete .XLS. It is not an expectation, but
may help speed the process (please see below).
Tom,
Very briefly, please send .PDF that shows ESC Plan legend that includes inlet protection, IP. Thanks —
remainder of this note touches on your submittal, as well. ( ESC Plan item 25: Revise ESC Plan legend to
include IP.)
Incidentally, how is easement plat review progressing with Andy Reitelbach?
Elam,
E-mail sent last Monday included request for a sediment trap (ST) —a substantial new comment. Having
reviewed revised plans sent as .PDF last Friday:
1. All prior Engineering review comments are addressed, including design -related email request
items sent 6-May 2019 (save one; item for T. Shumate, above).
2. Certain non -design -related items persist, required for VSMP Plan approval.
3. New Engineering review comments should typically be held to a minimum, but on 6-May,
Engineering requested ST design —yet not a word of protest.
4. A number of review errors stressed the review process. The number of (review) errors was
high. At no point did you or Tom express frustration. Again, not a word.
Tom /Elam: I am grateful for calls several weeks ago, which advanced design and review. Your
responsiveness and initiative kept this on track. Email would not have helped as much. Thank
you
Please keep an eye out for Approval -pending VSMP /WPO Memo, which outlines Process. This memo
will state non -design -related requirements which persist (required prior to VSMP Plan approval),
including: easement recordation, VAR10 permit issuance, retaining wall coordination with County
building permits (not required for VSMP Plan approval, but possibly required for building permit
approval), and print plan set submittal (4 -full size) /SWPPP (ESC /SWM Plan) inserts for approval.
Easement plat review is well underway.
ESC /SWM plan bonds need to be posted prior to receiving a grading permit.
Please send request for VSMP /WPO Plan bond estimate with check for $250 to address below, or hand -
deliver bond estimate form with check to front desk, CDD:
http://www.albemarle.oriz/upload/imaizes/forms_center/departments/Community Development/forms/bon
ds/Bond_ Request_ to Establish_a Bond.pdf
If Monteverde /Tom Shumate would like to help with qty. takeoffs, your values may improve accuracy,
limit bond amounts, and save time. Attached are partial bond estimates with approximate values for this
project. If you want to help with estimates, thank you. Engineering will double-check values. Please
note: shrubs are included with SWM plan bond (slopes >3:1). 16,800 shrubs appear to be required
(spacing 1' O.Q. Please do not revise spacing on plans, but estimate may be based on 2' O.C. Also,
typical unit price for container shrubs (1 Gal.) is $50. We reduced unit price and qty. in this instance, but
may not eliminate this stabilization measure.
Very well done, thank you both
best,
J. Anderson 434.296-5832 -x3069
John Anderson, PE, Civil Engineer II • (434) 296-5832 -x3069
Community Development Dept. I Engineering Division
County of Albemarle 1 401 McIntire Road
Charlottesville, Virginia 22902-4596
From: Elam Summey <esummey@monteverdedesigns.com>
Sent: Friday, May 10, 2019 4:07 PM
To: John Anderson <janderson2@albemarle.org>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP
Engineering review comments ]
John,
Attached are the revised PDFs. I've only included the 24x36 versions of the plans to be included in the
SWPPP so they can be reviewed at scale. On the final submission we will shrink them to 11x17 to be
included in the SWPPP binder. I think I've hit all the comments, its been a long week.
For the Pollution Prevention Plan I am referencing the temp. sediment basin on its own sheet ST-1.01.
Tom will also reference ST-1.01 on the E&S Plan. I think this provides the cleanest way for the two of us
to coordinate our design.
Have a good weekend,
Elam Summey, PE
Monteverede Engineering & Design
(540) 820-3574
www.MonteverdeDesigns.com
From: John Anderson <janderson2@albemarle.org>
Sent: Monday, May 6, 2019 2:25 PM
To: Elam Summey<esummev@monteverdedesigns.com>; Tom Shumate Jr
<tomlr@tomshumatesurveyor.com>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tyler Jones <tlones@r717.net>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP
Engineering review comments ]
Tom, in a few minutes, I will send comments. ESC Plan comments include a glaring omission, which I
should have caught please see, below.
Please work with Elam and decide where sediment trap should be mentioned in SWM Plan ESC
Sequence (sequence item 5 or 6).
As grading proceeds, channelized flow goes somewhere. We cannot approve with silt fence only; design
requires ST. I am glad to review .PDFs.
Thanks Tom —regret the inconvenience.
hYM►1
1. Provide Sediment Trap (ST) in location proposed for Extended Detention Basin.
2. Revise ESC Plan legend, notes, labels, sequence, etc. to allow for construction of sediment trap.
3. Provide ST rp ofile. Ref. VESCH, 3rd Edit., 1992, Std. & Spec. 3.13, Plate 3.13-1.
a. Provide depth of excavation elevation, floor of ST.
b. Provide wet and dry storage elevations.
c. Provide weir elevation.
4. ST /Plan view:
a. Include floor dimensions.
b. Dimension weir (L X W).
5. Provide inlet protection (IP), 15" culvert pipe.
6. Revise ESC Plan legend to include IP.
7. Provide dewatering structure detail (filter bag): VESCH Std. & Spec. 3.26.
best, J. Anderson 434.296-5832 -x3069
From: John Anderson
Sent: Monday, May 06, 2019 12:01 PM
To: Elam Summey <esummev@monteverdedesigns.com>; Tom Shumate Jr
<tomir@tomshumatesurveyor.com>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tyler Jones <tlones@r717.net>
Subject: RE: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP
Engineering review comments ]
Elam,
Albemarle County will shift VAR10 and inspection logs from initial SWPPPs to revised SWPPP.
Also, please rev. SWPPP, Sec. 1, Registration Statement, item 9., at least area of disturbance value.
Thanks Elam
(Note: total Land Area of Development is rarely less than Area to be Disturbed; these values may trigger
questions by DEQ. 1.01 Ac. = ?)
Tom, overlooked:
Please extend SF to wrap 18" DIA Ex. Det. Pond pipe outfall, and revise LOD Area to include this pipe
(2.06 Ac., should increase slightly).
Thanks Tom
From: John Anderson
Sent: Monday, May 06, 2019 11:06 AM
To: Elam Summey <esummev@monteverdedesigns.com>; Tom Shumate Jr
<tomir@tomshumatesurveyor.com>
Cc: Michael McGinnis <mmcginnis@r717.net>; Tyler Jones <tlones@r717.net>
Subject: Planning Application Review for WP0201900024 Hillcrest Vineyard and Winery - VSMP. [
Engineering review comments ]
The Review for the following application has been completed:
Application Number = WP0201900024
Reviewer = John Anderson
Review Status = Pending
Completed Date =
This email was sent from County View Production.
Elam, excellent work —multiple comments are withdrawn; there were multiple review errors.
I appreciate speaking with you several weeks ago. The most substantive remaining comments:
1. Reverse benches on 2:1 cut slopes above facility, and Swale A may require revised
contours. Swale A, if 12' wide, may be in pavement.
2. Given 10-yr. depth of flow in swales, A, B, C, (0.370', 0.200', 0.123') 12' width may be reduced
to 8.67' to provide 0.66' depth. A design decision.
3. Swale typ., with 5:1 side slopes and 2' bottom appears to be 12.0' wide. Swales B, C appear to
scale 6'-0" in plan view, C-1.02. Revise plan view width to scale.
4. Banked 2:1 cut slope (contours 810', 816') and swales A, B, C, should be shown to scale in plan
view, with grading that matches typ., and benches that convey runoff to edges of cut slope.
5. A typical detail for benches is required. Recommend benches extend 10'-15' beyond edge of cut
slope at 0% grade, to serve as a natural level spreader.
6. Benches do not require easement, but should receive periodic maintenance, indefinitely. If
length of benches not extended, erosion may occur at edge of cut slope.
7. Engineering recognizes 4' horizontal: 1' vertical grade (bench contours at 8101, 8161), but a
bench detail, as well as contour labels (810', 816') at very edge of cut slope should help ensure
design is built.
8. I lost track of 4' width approaching edge of 2:1 cut slope —a trick of the eyes, perhaps, but we
need to ensure 4' bench (reverse bench that fits within 4 horizontal: 1 vert) carries at least to the
edge of the cut slope (recommend extend 10'-15' beyond edge).
9. Need SWPPP logs
10. C-2.01, Note 2: Provide a tentative schedule for exploring soils in the detention basin in at least 2
locations, since Haysville loam is prone to piping.
11. Alternative (to 10.): Provide C-2.01 Note requiring contractor to export soils evaluated by a
qualified geotechnical professional as unsuitable for basin embankments (based upon sampled
physical properties).
12. If I I., provide Note requiring suitable fill material for basin embankments.
13. If I I., provide Note specifying qualified geotechnical evaluation, with reports submitted to
owner and Albemarle County, describing suitability of on -site soils for extended detention basin
embankments.
14. Geotechnical Note should specify classes of suitable (fill) soils, and reports must indicate that
suitable soils are used to construct extended detention basin embankments.
15. Need 18" DIA Ex. Det. Pond outfall pipe length, slope, INV in/out labels on Section through
Detention Basin, C-2.01.
16. A few edit changes (C-1.02 basin discharge INV out elev. (170 LF at 0.5%) appears to be
789.65', for example).
17. Note: Work within existing 30' Easement requires coordination with VDOT / VDOT Land Use
Permit.
Given review errors /extent of review comments, this submittal is exceptional —calculations, profile,
attention to design, data /notes provided, energy balance eq. —this is a comprehensive
response. Formal comments to follow, later today.
Let's finish via .PDF preview, this week, if that fits your schedule. Once you receive review comments,
later today (very little beyond items outlined in bullets, above), feel free to call if any questions. Thanks,
Elam.
Tom,
Likewise, excellent work. I enjoy speaking with you when you call.
Prior review comments were in error, or are withdrawn or addressed with this submittal. Formal
comments to follow, later today.
Thank you for your help and patience.
best, J. Anderson 434.296-5832 -x3069
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Tuesday, July 16, 2019 10:53 AM
To: Tori Kanellopoulos; John Anderson
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; 'O'Brien, Ernie'; dcroker@ilexconstruction.com
Subject: Easement Plat - FINAL PDFs
Attachments: f; f;
SHEET 3 REV.pdf
John and Tori,
Please find attached the final PDFs for the plat per this morning's meeting with John.
Thanks!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
ER
E NGIrQEE] ]RNrti(; S sirRVEiYr1G INC.-
From: Tori Kanellopoulos [mailto:vkanellopoulos@albemarle.org]
Sent: Tuesday, July 16, 2019 8:39 AM
To: Kurt Gloeckner; John Anderson
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie;
dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Hi Kurt,
I am confirming that there are no outstanding Planning comments — thank you!!
Tori
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson <janderson2@albemarle.org>; Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
EENQINEE] REND S ti�ERVEiYINU IN -.-
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson; Tori Kanellopoulos
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; O'Brien, Ernie; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
Attachments: f; f;
SHEET 3 REV.pdf
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
ENGINI . I Ni U& tiURVFY10%(3 1NC.
From: John Anderson
Sent: Tuesday, July 16, 2019 5:50 AM
To: kurtgloeckner@gmail.com; gloecknerengineering@gmail.com
Cc: Mike Myers; craigjohnson3@icloud.com; Tori Kanellopoulos
Subject: Fw: SUB201900097
Attachments: - -
071519rev.2.pdf; Easement Plat - Updated Revision
Thanks, Kurt, see you later this morning.
From: John Anderson
Sent: Monday, July 15, 2019 5:41 PM
To: John Anderson
Subject: SUB201900097
John Anderson, PE, Civil Engineer II • (434) 296-5832 -x3069
Community Development Dept. I Engineering Division
County of Albemarle 1401 McIntire Road
Charlottesville, Virginia 22902-4596
From: John Anderson
Sent: Saturday, July 6, 2019 12:27 PM
To: kurtgloeckner@gmail.com
Cc: Tori Kanellopoulos
Subject: Planning Application Review for SUB201900097 2265 DECCA LANE -
EASEMENT PLAT. [ Engineering plat review comments ]
Attachments: ktig2ol qnnnu - - f
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 07/06/2019
This email was sent from County View Production.
Kurt,
It was a pleasure to speak with you a week or so, ago.
Attached comments also in CV.
Thanks for your patience.
Please let us know if you have any questions.
Thank you.
best,
J. Anderson 434.296-5832 -0069
Note: I will be away, 18-30 Jul, not working, not checking email; regret any inconvenience.
Thanks again
From: John Anderson
Sent: Sunday, July 14, 2019 12:27 PM
To: Kurt Gloeckner
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos; Mike Myers;
craigjohnson3@icloud.com
Subject: Planning Application Review for SUB201900097 226S DECCA LANE -
EASEMENT PLAT. [ Engineering plat review comments ]
Attachments: KtjR2nlqnnnq7 - -
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 07/14/2019
This email was sent from County View Production.
Kurt,
Excellent —truly outstanding. Attached review comments also in CV. Thank you.
Additional /important:
Final Engineering review comments; please:
1. Provide easement around the wet pond. The SWM Access easement is fine, Forest /Open Space
Easement is fine, but I do not see an easement for the wet pond —am I overlooking?
2. Revise plat title: Insert between first and second lines of title, this new line: `SWM Facility &
SWM Access Easement Plat.'
3. Revise first line of plat title to read `Forest /Open Space Easement and'.
4. Label SWM Facility Easement (wet pond) and SWM Facility Access Easement areas (x.xx Ac).
5. Planning Div. follow-up comment.
6. Text edit, sheet 1 Forest -Open Space note (see attached).
7. Provide deed-bk. pg. ref. to S.R. 678 VDOT 30' prescriptive easement.
Feel free to send .PDF to Engineering once revised. Until print copy of revised plat is submitted
(recommend Tue AM, when we meet), Planning will take no further action on this Application. Planning
Division is typically expected (by policy, in fairness to others) to review submittals in order received.
I am glad Tori is plat reviewer. Whatever I was looking at Friday when we spoke, I managed to overlook
this fact: Planning has already reviewed plat and issued comments. You must have wondered as I began
talking about needing to share this plat with Planning. We are well -positioned in that respect. I compared
revised plat (rcvd. Sat) w/ Planning comments, and offer one follow-up recommendation (see
attached). Feel free to send digital plat revised in response to comments, as .PDF. That digital version
(which will almost certainly address all Engineering and prior Planning Div. comments) will not be sent
to CAO for review, not until a SWM BMP Facilities Maintenance Agreement is recorded.
Once Planning Div. comments are addressed with final revised plat (we assume they will be), and once
SWM /BMP Facilities Maintenance Agreement is recorded:
1. Engineering will format deed and send unsigned deed + final easement plat (.PDFs) to CAO for
review /comment.
2. If no CAO comments, submit original signed /notarized deed + plat to CDD front desk to my
attention with cover reading `Not for review, for signature approval.'
3. Engineering routes to CAO for attorney and county executive signatures /execution. Engineering
notifies when executed deed /plat may be picked up.
4. Applicant records deed /plat, sends scan of circuit court receipt of recordation to Engineering
(deed bk.-pg.).
5. Deed /plat must be recorded prior to scheduling a pre -construction meeting, where grading permit
is issued.
6. SWM and ESC plan bonds must be posted prior to receiving a Grading Permit.
We discussed Friday (7/12) that Applicant needs to work with Ana Kilmer on:
• SWM /BMP Facilities Maintenance Agreement (once Agreement is finalized /signed; the county
records)
• SWM and ESC plan bonds (bonds must be posted prior to receiving a Grading Permit)
( Ana may be reached at: 434.296-5832-x3246)
I will be away 18-30 Jul, not working or checking email. Once we meet Tuesday, I anticipate plat (from
Engineering perspective), and VSMP /WPO plan will address prior review comments.
Planning Div. comments appear to be addressed. Engineering recommends follow-up to a single
Planning comment. So, Tuesday when you submit bond estimate request form w/ fee (after we meet), I
recommend submit revised final 3-sheet print version of easement plat (with Application) at CDD front
desk so it may route to Tori, and reach her queue.
Thanks again
best, J. Anderson 434.296-5832 -x3069
From: John Anderson
Sent: Friday, June 21, 2019 9:37 AM
To: kurtgloeckner@gmail.com
Cc: Tori Kanellopoulos
Subject: Planning Application Review for SUB201900097 2265 DECCA LANE -
EASEMENT PLAT. [ Planning plat review comments ]
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = Tori Kanellopoulos
Review Status = Requested Changes
Completed Date = 06/20/2019
This email was sent from County View Production.
Kurt,
Planning (plat) review comments, also in CV.
Review comments:
1. 14-302(A): Include a vicinity map at a scale of 1 " = 2,000 feet or at other appropriate scale.
2. Please add the following notes to the plat:
2a. 14-302(B)(5): Include the zoning district, which RA Rural Area.
2b. 14-302(B)(7): Add the watershed water supply note to the notes section.
2c. 14-302(B)(10): Add the following note: "The stream buffer(s) shown hereon shall be managed in
accordance with the Albemarle
County Water Protection Ordinance."
2d. 14-303(A): Add the following note, revised as needed with the correct information for this plat: "The
platting or dedication of the following described land [insert a correct description of the land subdivided]
is with the free consent and in accordance with the desire of the undersigned owners, proprietors and
trustees, if any."
3. 14-303(0)(P): Include signature panels for each owner and for the agent or his designee. The signature
panel for the owner shall be located immediately below the statement required by the statement in
comment 2c.
4. 14-303(0): Include a signature block for the agent (County).
5. Please revise the adjacent parcels information. It appears TMP 42-58A is shown twice and on 58A1.
Additionally, TMP 42-125 appears to be 42-127 in GIS.
Please coordinate revision in response to Planning comments directly with Tori, should you have
questions, but do not submit a revised plat until Engineering comments, likely early to mid -week next
week. Also, please do not send .PDF to planning or engineering for courtesy preview. We are working
under heavy workflow, intense deadline, and cannot in good faith replace reviews in queue with follow-
up review of a .PDF. Engineering typically is able to review a revised plat or plan relatively quickly, as
we tend to focus on revisions in response to comments; that is, we do not start from scratch. I appreciate
Tori's speed, and regret I cannot match it. Anticipate Engineering plat review comments within 3-5
business days. Thanks for your patience.
best, J. Anderson 434.296-5832 -0069
From: Tori Kanellopoulos
Sent: Tuesday, July 16, 2019 10:56 AM
To: Kurt Gloeckner; John Anderson
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; 'O'Brien, Ernie'; dcroker@ilexconstruction.com
Subject: RE: Easement Plat - FINAL PDFs
Thanks! You're all set from the Planning perspective! And John, thank you for your Engineering review
with this — really for Planning it's just the notes!
Tori
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Tuesday, July 16, 2019 10:53 AM
To: Tori Kanellopoulos <vkanellopoulos@albemarle.org>; John Anderson <janderson2@albemarle.org>
Cc: gloecknerengineering@gmail.com; craig4ohnson3@icloud.com; mike@30scale.com; 'O'Brien, Ernie'
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - FINAL PDFs
John and Tori,
Please find attached the final PDFs for the plat per this morning's meeting with John.
Thanks!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
GLECKNER
EENGINE:7•RIN€, S S-URVEiVINU INC'_
From: Tori Kanellopoulos[mailto:vkanellopoulos@albemarle.org]
Sent: Tuesday, July 16, 2019 8:39 AM
To: Kurt Gloeckner; John Anderson
Cc: gloecknerengineering(a gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie;
dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Hi Kurt,
I am confirming that there are no outstanding Planning comments — thank you!!
Tori
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson <janderson2@albemarle.org>; Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Cc: gloecknerengineering@gmail.com; craigiohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
From: Tori Kanellopoulos
Sent: Tuesday, July 16, 2019 8:39 AM
To: Kurt Gloeckner; John Anderson
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; O'Brien, Ernie; dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Hi Kurt,
I am confirming that there are no outstanding Planning comments — thank you!!
Tori
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson <janderson2@albemarle.org>; Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
EEV(:INEE] RI (; S �(lRVEiYIWG INC-
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 11:26 PM
To: John Anderson; Tori Kanellopoulos
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; 'O'Brien, Ernie'; dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Attachments: f; f;
- SWM Facility Screen Shot.jpg
John,
Please find attached the revision removing the word "access" on pages 2 and 3.
The easement for the SWM Facility does extend beyond the limits of grading and all aspects of the
facility. Please see the attached screen shot of the CAD file with the design and easement (the easement
is the highlighted dashed line).
Thanks and see you in the morning!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
N
E - -NGIN REND S ' VRVEiYI G MCC. -
From: John Anderson [mailto:janderson2@albemarle.org]
Sent: Monday, July 15, 2019 4:56 PM
To: Kurt Gloeckner; Tori Kanellopoulos
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie;
dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Kurt,
As a favor, please confirm hatched area includes plunge pool at end of 8" storm line coming into the wet
pond, and includes plunge pool /LS at base of spillway /pond outfall.
Also, please delete the word Access from SWM facility easement label, sheets 2 and 3. It appears
planning comment is addressed. Prior Engineering comments are addressed.
I am typing `No objection' Memo; with Planning concurrence, CDD is set to approve.
In the time it takes to revise /delete Access, sheets 2, 3, Memo will be ready to send.
Very well done please send final .PDF, and we should be set for tomorrow.
It was nice speaking with your father, earlier today. Thanks Kurt
best, I Anderson 434.296-5832 -x3069
z
ass.
"4 ro7
el
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson <ianderson2@albemarle.org>; Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Cc: gloecknerengineering@gmail.com; craig4ohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
EENQINEE] REND S ti�ERVEiYINU IN -.-
From:
John Anderson
Sent:
Monday, July 15, 2019 4:56 PM
To:
Kurt Gloeckner; Tori Kanellopoulos
Cc:
gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; O'Brien, Ernie; dcroker@ilexconstruction.com
Subject:
RE: Easement Plat - Updated Revision
Kurt,
As a favor, please confirm hatched area includes plunge pool at end of 8" storm line coming into the wet
pond, and includes plunge pool /LS at base of spillway /pond outfall.
Also, please delete the word Access from SWM facility easement label, sheets 2 and 3. It appears
planning comment is addressed. Prior Engineering comments are addressed.
I am typing `No objection' Memo; with Planning concurrence, CDD is set to approve.
In the time it takes to revise /delete Access, sheets 2, 3, Memo will be ready to send.
Very well done —please send final .PDF, and we should be set for tomorrow.
It was nice speaking with your father, earlier today. Thanks Kurt
best, J. Anderson 434.296-5832 -x3069
ac:
J
J
`
11
1
I .JJ
r00...
'°Ro
r '•
_ 411.7
844'07
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson <janderson2@albemarle.org>; Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
GL
N
FNGIfQ[=]•RINQ S LKrRVI-.Y1NU INC.-
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Tuesday, July 16, 2019 10:48 AM
To: John Anderson; Tori Kanellopoulos
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com;
mike@30scale.com; 'O'Brien, Ernie'; dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Attachments: f; f;
- SWM Facility Screen Shot.jpg
John,
Please find attached the revision removing the word "access" on pages 2 and 3.
The easement for the SWM Facility does extend beyond the limits of grading and all aspects of the
facility. Please see the attached screen shot of the CAD file with the design and easement (the easement
is the highlighted dashed line).
Thanks and see you in the morning!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
N
E - -NGIN REND S ' VRVEiYI G MCC. -
From: John Anderson [mailto:janderson2@albemarle.org]
Sent: Monday, July 15, 2019 4:56 PM
To: Kurt Gloeckner; Tori Kanellopoulos
Cc: gloecknerengineering@gmail.com; craigjohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie;
dcroker@ilexconstruction.com
Subject: RE: Easement Plat - Updated Revision
Kurt,
As a favor, please confirm hatched area includes plunge pool at end of 8" storm line coming into the wet
pond, and includes plunge pool /LS at base of spillway /pond outfall.
Also, please delete the word Access from SWM facility easement label, sheets 2 and 3. It appears
planning comment is addressed. Prior Engineering comments are addressed.
I am typing `No objection' Memo; with Planning concurrence, CDD is set to approve.
In the time it takes to revise /delete Access, sheets 2, 3, Memo will be ready to send.
Very well done please send final .PDF, and we should be set for tomorrow.
It was nice speaking with your father, earlier today. Thanks Kurt
best, I Anderson 434.296-5832 -x3069
z
ass.
"4 ro7
el
From: Kurt Gloeckner <kurtgloeckner@gmail.com>
Sent: Monday, July 15, 2019 4:37 PM
To: John Anderson <ianderson2@albemarle.org>; Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Cc: gloecknerengineering@gmail.com; craig4ohnson3@icloud.com; mike@30scale.com; O'Brien, Ernie
<eobrien@ilexconstruction.com>; dcroker@ilexconstruction.com
Subject: Easement Plat - Updated Revision
John and Tori,
Please find attached the revised easement plat. I believe I have addressed all comments but will defer to
you for review.
John,
We should be set for tomorrow's meeting at 9:00 and will be bringing 11x17s of the Plat and VSMP for
review. We will be bringing our laptops so we can make any necessary changes on the spot or shortly
thereafter.
Thanks and we look forward to seeing you tomorrow!
Kurt J. Gloeckner
Vice President
C: 434-284-0400
Gloeckner Engineering & Surveying Inc.
EENQINEE] REND S ti�ERVEiYINU IN -.-
From: Tori Kanellopoulos
Sent: Monday, July 15, 2019 8:50 AM
To: John Anderson; Kurt Gloeckner
Cc: gloecknerengineering@gmail.com; Mike Myers;
craigjohnson3@icloud.com
Subject: RE: Planning Application Review for SUB201900097 2265 DECCA LANE -
EASEMENT PLAT. [ Engineering plat review comments ]
Thank you for all of the comments and helpful next steps, John! From a Planning perspective, I can
review either a paper copy or an electronic copy — whichever the applicant prefers. Also, Planning tends
to have a relatively quick review of these types of plats, since they are Engineering -led, and therefore a
much easier review for Planning!
Tori
From: John Anderson
Sent: Sunday, July 14, 2019 12:54 PM
To: Kurt Gloeckner <kurtgloeckner@gmail.com>
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos <vkanellopoulos@albemarle.org>; Mike
Myers <mike@30scale.com>; craigjohnson3@icloud.com
Subject: RE: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT.
Engineering plat review comments ]
Kurt,
While reviewing VSMP /WPO plan (now), I realize that when you asked whether the plat should include
the wet pond footprint and I said no (thinking, incorrectly, you meant an outline of the facility), that what
you meant was should the plat include easement for the wet pond. My fault. The plat needs to provide an
easement that more than encompasses the wet pond, an area beyond pond embankments to allow
maintenance in the future —we recommend 10'-15' beyond limits of grading required to construct the wet
pond. I should have been more attuned and thoughtful, and apologize.
Thank you
best, I Anderson 434.296-5832 -0069
From: John Anderson
Sent: Sunday, July 14, 2019 12:27 PM
To: Kurt Gloeckner <kurtgloeckner@gmail.com>
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos <vkanellopoulos@albemarle.org>; Mike
Myers <mike@30scale.com>; craigjohnson3@icloud.com
Subject: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT. [
Engineering plat review comments ]
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 07/14/2019
This email was sent from County View Production.
Kurt,
Excellent —truly outstanding. Attached review comments also in CV. Thank you.
Additional /important:
Final Engineering review comments; please:
1. Provide easement around the wet pond. The SWM Access easement is fine, Forest /Open Space
Easement is fine, but I do not see an easement for the wet pond —am I overlooking?
2. Revise plat title: Insert between first and second lines of title, this new line: `SWM Facility &
SWM Access Easement Plat.'
3. Revise first line of plat title to read `Forest /Open Space Easement and'.
4. Label SWM Facility Easement (wet pond) and SWM Facility Access Easement areas (x.xx Ac).
5. Planning Div. follow-up comment.
6. Text edit, sheet 1 Forest -Open Space note (see attached).
7. Provide deed-bk. pg. ref. to S.R. 678 VDOT 30' prescriptive easement.
Feel free to send .PDF to Engineering once revised. Until print copy of revised plat is submitted
(recommend Tue AM, when we meet), Planning will take no further action on this Application. Planning
Division is typically expected (by policy, in fairness to others) to review submittals in order received.
I am glad Tori is plat reviewer. Whatever I was looking at Friday when we spoke, I managed to overlook
this fact: Planning has already reviewed plat and issued comments. You must have wondered as I began
talking about needing to share this plat with Planning. We are well -positioned in that respect. I compared
revised plat (rcvd. Sat) w/ Planning comments, and offer one follow-up recommendation (see
attached). Feel free to send digital plat revised in response to comments, as .PDF. That digital version
(which will almost certainly address all Engineering and prior Planning Div. comments) will not be sent
to CAO for review, not until a SWM BMP Facilities Maintenance Agreement is recorded.
Once Planning Div. comments are addressed with final revised plat (we assume they will be), and once
SWM BMP Facilities Maintenance Agreement is recorded:
1. Engineering will format deed and send unsigned deed + final easement plat (.PDFs) to CAO for
review /comment.
2. If no CAO comments, submit original signed /notarized deed + plat to CDD front desk to my
attention with cover reading `Not for review, for signature approval.'
3. Engineering routes to CAO for attorney and county executive signatures /execution. Engineering
notifies when executed deed /plat may be picked up.
4. Applicant records deed /plat, sends scan of circuit court receipt of recordation to Engineering
(deed bk.-pg.).
5. Deed /plat must be recorded prior to scheduling a pre -construction meeting, where grading permit
is issued.
6. SWM and ESC plan bonds must be posted prior to receiving a Grading Permit.
We discussed Friday (7/12) that Applicant needs to work with Ana Kilmer on:
• SWM /BMP Facilities Maintenance Agreement (once Agreement is finalized /signed; the county
records)
• SWM and ESC plan bonds (bonds must be posted prior to receiving a Grading Permit)
( Ana may be reached at: 434.296-5832-x3246)
I will be away 18-30 Jul, not working or checking email. Once we meet Tuesday, I anticipate plat (from
Engineering perspective), and VSMP /WPO plan will address prior review comments.
Planning Div. comments appear to be addressed. Engineering recommends follow-up to a single
Planning comment. So, Tuesday when you submit bond estimate request form w/ fee (after we meet), I
recommend submit revised final 3-sheet print version of easement plat (with Application) at CDD front
desk so it may route to Tori, and reach her queue.
Thanks again
best, J. Anderson 434.296-5832 -x3069
From: John Anderson
Sent: Sunday, July 14, 2019 12:54 PM
To: Kurt Gloeckner
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos; Mike Myers;
craigjohnson3@icloud.com
Subject: RE: Planning Application Review for SUB201900097 2265 DECCA LANE -
EASEMENT PLAT. [ Engineering plat review comments ]
Kurt,
While reviewing VSMP /WPO plan (now), I realize that when you asked whether the plat should include
the wet pond footprint and I said no (thinking, incorrectly, you meant an outline of the facility), that what
you meant was should the plat include easement for the wet pond. My fault. The plat needs to provide an
easement that more than encompasses the wet pond, an area beyond pond embankments to allow
maintenance in the future —we recommend 10'-15' beyond limits of grading required to construct the wet
pond. I should have been more attuned and thoughtful, and apologize.
Thank you
best, I Anderson 434.296-5832 -x3069
From: John Anderson
Sent: Sunday, July 14, 2019 12:27 PM
To: Kurt Gloeckner <kurtgloeckner@gmail.com>
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos <vkanellopoulos@albemarle.org>; Mike
Myers <mike@30scale.com>; craigjohnson3@icloud.com
Subject: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT. [
Engineering plat review comments ]
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 07/14/2019
This email was sent from County View Production.
Kurt,
Excellent —truly outstanding. Attached review comments also in CV. Thank you.
Additional /important:
Final Engineering review comments; please:
1. Provide easement around the wet pond. The SWM Access easement is fine, Forest /Open Space
Easement is fine, but I do not see an easement for the wet pond —am I overlooking?
2. Revise plat title: Insert between first and second lines of title, this new line: `SWM Facility &
SWM Access Easement Plat.'
3. Revise first line of plat title to read `Forest /Open Space Easement and'.
4. Label SWM Facility Easement (wet pond) and SWM Facility Access Easement areas (x.xx Ac).
5. Planning Div. follow-up comment.
6. Text edit, sheet 1 Forest -Open Space note (see attached).
7. Provide deed-bk. pg. ref. to S.R. 678 VDOT 30' prescriptive easement.
Feel free to send .PDF to Engineering once revised. Until print copy of revised plat is submitted
(recommend Tue AM, when we meet), Planning will take no further action on this Application. Planning
Division is typically expected (by policy, in fairness to others) to review submittals in order received.
I am glad Tori is plat reviewer. Whatever I was looking at Friday when we spoke, I managed to overlook
this fact: Planning has already reviewed plat and issued comments. You must have wondered as I began
talking about needing to share this plat with Planning. We are well -positioned in that respect. I compared
revised plat (rcvd. Sat) w/ Planning comments, and offer one follow-up recommendation (see
attached). Feel free to send digital plat revised in response to comments, as .PDF. That digital version
(which will almost certainly address all Engineering and prior Planning Div. comments) will not be sent
to CAO for review, not until a SWM BMP Facilities Maintenance Agreement is recorded.
Once Planning Div. comments are addressed with final revised plat (we assume they will be), and once
SWM BMP Facilities Maintenance Agreement is recorded:
1. Engineering will format deed and send unsigned deed + final easement plat (.PDFs) to CAO for
review /comment.
2. If no CAO comments, submit original signed /notarized deed + plat to CDD front desk to my
attention with cover reading `Not for review, for signature approval.'
3. Engineering routes to CAO for attorney and county executive signatures /execution. Engineering
notifies when executed deed /plat may be picked up.
4. Applicant records deed /plat, sends scan of circuit court receipt of recordation to Engineering
(deed bk.-pg.).
5. Deed /plat must be recorded prior to scheduling a pre -construction meeting, where grading permit
is issued.
6. SWM and ESC plan bonds must be posted prior to receiving a Grading Permit.
We discussed Friday (7/12) that Applicant needs to work with Ana Kilmer on:
• SWM BMP Facilities Maintenance Agreement (once Agreement is finalized /signed; the county
records)
• SWM and ESC plan bonds (bonds must be posted prior to receiving a Grading Permit)
( Ana may be reached at: 434.296-5832-x3246)
I will be away 18-30 Jul, not working or checking email. Once we meet Tuesday, I anticipate plat (from
Engineering perspective), and VSMP /WPO plan will address prior review comments.
Planning Div. comments appear to be addressed. Engineering recommends follow-up to a single
Planning comment. So, Tuesday when you submit bond estimate request form w/ fee (after we meet), I
recommend submit revised final 3-sheet print version of easement plat (with Application) at CDD front
desk so it may route to Tori, and reach her queue.
Thanks again
best, J. Anderson 434.296-5832 -0069
From: John Anderson
Sent: Monday, July 15, 2019 9:23 AM
To: Tori Kanellopoulos; Kurt Gloeckner
Cc: gloecknerengineering@gmail.com; Mike Myers;
craigjohnson3@icloud.com
Subject: RE: Planning Application Review for SUB201900097 2265 DECCA LANE -
EASEMENT PLAT. [ Engineering plat review comments ]
Tori,
You are very helpful and supportive —thanks for your willingness to help the applicant this way, and for
your kind note.
best, JA -0069
From: Tori Kanellopoulos
Sent: Monday, July 15, 2019 8:50 AM
To: John Anderson <janderson2@albemarle.org>; Kurt Gloeckner <kurtgloeckner@gmail.com>
Cc: gloecknerengineering@gmail.com; Mike Myers <mike@30scale.com>; craigjohnson3@icloud.com
Subject: RE: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT. [
Engineering plat review comments ]
Thank you for all of the comments and helpful next steps, John! From a Planning perspective, I can
review either a paper copy or an electronic copy — whichever the applicant prefers. Also, Planning tends
to have a relatively quick review of these types of plats, since they are Engineering -led, and therefore a
much easier review for Planning!
Tori
From: John Anderson
Sent: Sunday, July 14, 2019 12:54 PM
To: Kurt Gloeckner <kurtgloeckner@gmail.com>
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos <vkanellopoulos@albemarle.org>; Mike
Myers <mike@30scale.com>; craigiohnson3@icloud.com
Subject: RE: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT.
Engineering plat review comments ]
Kurt,
While reviewing VSMP /WPO plan (now), I realize that when you asked whether the plat should include
the wet pond footprint and I said no (thinking, incorrectly, you meant an outline of the facility), that what
you meant was should the plat include easement for the wet pond. My fault. The plat needs to provide an
easement that more than encompasses the wet pond, an area beyond pond embankments to allow
maintenance in the future —we recommend 10'-15' beyond limits of grading required to construct the wet
pond. I should have been more attuned and thoughtful, and apologize.
Thank you
best, J. Anderson 434.296-5832 -0069
From: John Anderson
Sent: Sunday, July 14, 2019 12:27 PM
To: Kurt Gloeckner <kurtgloeckner@gmail.com>
Cc: gloecknerengineering@gmail.com; Tori Kanellopoulos <vkanellopoulos@albemarle.org>; Mike
Myers <mike@30scale.com>; craiglohnson3@icloud.com
Subject: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT. [
Engineering plat review comments ]
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 07/14/2019
This email was sent from County View Production.
Kurt,
Excellent —truly outstanding. Attached review comments also in CV. Thank you.
Additional /important:
Final Engineering review comments; please:
1. Provide easement around the wet pond. The SWM Access easement is fine, Forest /Open Space
Easement is fine, but I do not see an easement for the wet pond —am I overlooking?
2. Revise plat title: Insert between first and second lines of title, this new line: `SWM Facility&
SWM Access Easement Plat.'
3. Revise first line of plat title to read `Forest /Open Space Easement and'.
4. Label SWM Facility Easement (wet pond) and SWM Facility Access Easement areas (x.xx Ac).
5. Planning Div. follow-up comment.
6. Text edit, sheet 1 Forest -Open Space note (see attached).
7. Provide deed-bk. pg. ref. to S.R. 678 VDOT 30' prescriptive easement.
Feel free to send .PDF to Engineering once revised. Until print copy of revised plat is submitted
(recommend Tue AM, when we meet), Planning will take no further action on this Application. Planning
Division is typically expected (by policy, in fairness to others) to review submittals in order received.
I am glad Tori is plat reviewer. Whatever I was looking at Friday when we spoke, I managed to overlook
this fact: Planning has already reviewed plat and issued comments. You must have wondered as I began
talking about needing to share this plat with Planning. We are well -positioned in that respect. I compared
revised plat (rcvd. Sat) w/ Planning comments, and offer one follow-up recommendation (see
attached). Feel free to send digital plat revised in response to comments, as .PDF. That digital version
(which will almost certainly address all Engineering and prior Planning Div. comments) will not be sent
to CAO for review, not until a SWM /BMP Facilities Maintenance Agreement is recorded.
Once Planning Div. comments are addressed with final revised plat (we assume they will be), and once
SWM BMP Facilities Maintenance Agreement is recorded:
1. Engineering will format deed and send unsigned deed + final easement plat (.PDFs) to CAO for
review /comment.
2. If no CAO comments, submit original signed /notarized deed + plat to CDD front desk to my
attention with cover reading `Not for review, for signature approval.'
3. Engineering routes to CAO for attorney and county executive signatures /execution. Engineering
notifies when executed deed /plat may be picked up.
4. Applicant records deed /plat, sends scan of circuit court receipt of recordation to Engineering
(deed bk.-pg.).
5. Deed /plat must be recorded prior to scheduling a pre -construction meeting, where grading permit
is issued.
6. SWM and ESC plan bonds must be posted prior to receiving a Grading Permit.
We discussed Friday (7/12) that Applicant needs to work with Ana Kilmer on:
• SWM BMP Facilities Maintenance Agreement (once Agreement is finalized /signed; the county
records)
• SWM and ESC plan bonds (bonds must be posted prior to receiving a Grading Permit)
( Ana may be reached at: 434.296-5832-x3246)
I will be away 18-30 Jul, not working or checking email. Once we meet Tuesday, I anticipate plat (from
Engineering perspective), and VSMP /WPO plan will address prior review comments.
Planning Div. comments appear to be addressed. Engineering recommends follow-up to a single
Planning comment. So, Tuesday when you submit bond estimate request form w/ fee (after we meet), I
recommend submit revised final 3-sheet print version of easement plat (with Application) at CDD front
desk so it may route to Tori, and reach her queue.
Thanks again
best, J. Anderson 434.296-5832 -x3069
From:
John Anderson
Sent:
Friday, June 21, 2019 9:27 AM
To:
Tori Kanellopoulos
Subject:
RE: Planning Application Review for SUB201900097 2265 DECCA LANE -
EASEMENT PLAT.
Thanks Tori
From: Tori Kanellopoulos
Sent: Thursday, June 20, 2019 4:07 PM
To: John Anderson <janderson2@albemarle.org>
Subject: Planning Application Review for SUB201900097 2265 DECCA LANE - EASEMENT PLAT.
The Review for the following application has been completed:
Application Number = SUB201900097
Reviewer = Tori Kanellopoulos
Review Status = Requested Changes
Completed Date = 06/20/19
This email was sent from County View Production.
From:
John Anderson
Sent:
Tuesday, June 18, 2019 3:21 PM
To:
Tori Kanellopoulos
Subject:
RE: SUB2019-97 Easement Plat
Tori,
I left copy on your drafting table, without transmittal —is that okay? Also, I hope to comment by Friday —
if I do, and I plan to be thorough, it may spare you having to make quite a few relatively routine
comments. Either way is fine —you are lightening fast.
Thanks Ton
From: John Anderson
Sent: Tuesday, June 18, 2019 2:48 PM
To: Tori Kanellopoulos <vkanellopoulos@albemarle.org>
Subject: RE: SUB2019-97 Easement Plat
You bet, headed you way, CV comment response: 7/3/19 :)
From: Tori Kanellopoulos
Sent: Tuesday, June 18, 2019 2:18 PM
To: John Anderson <janderson2@albemarle.org>
Subject: SUB2019-97 Easement Plat
Hi John,
I was wondering if I could get a copy of SUB2019-97 to review the Planning notes? I forgot to put my
name in CV, but I am the Planning reviewer. I think it came in when I was out.
Thanks!
Tori
Tori Kanellopoulos, AICP Candidate
Planner
Community Development Department
Phone: 434-296-5832 ext. 3270
From: John Anderson
Sent: Tuesday, July 16, 2019 5:57 AM
To: kurtgloeckner@gmail.com; gloecknerengineering@gmail.com
Cc: Mike Myers; craigjohnson3@icloud.com; Tori Kanellopoulos
Subject: Re: SUB201900097
Kurt, an oversight --please revise plat revised date to Jules. I will format deed to match.
Please drop off original signed notarized plat whenever convenient, but please send .PDF of 7/15 plat so I
may send .PDF to county attorney's office (with formatted deed) for CAO review. You may want to hold
off on signatures until CAO review, as the attorney may request slight revision to plat, as happens
on occasion.
Thanks -see you soon.
From: John Anderson
Sent: Tuesday, July 16, 2019 5:49:50 AM
To: kurtgloeckner@gmail.com; gloecknerengineering@gmail.com
Cc: Mike Myers; craigjohnson3@icloud.com; Tori Kanellopoulos
Subject: Fw: SUB201900097
Thanks, Kurt, see you later this morning.
From: John Anderson
Sent: Monday, July 15, 2019 5:41 PM
To: John Anderson
Subject: SUB201900097
John Anderson, PE, Civil Engineer II • (434) 296-5832 -0069
Community Development Dept. I Engineering Division
County of Albemarle 1401 McIntire Road
Charlottesville, Virginia 22902-4596
From: Tori Kanellopoulos
Sent: Tuesday, June 18, 2019 2:18 PM
To: John Anderson
Subject: SUB2019-97 Easement Plat
Hi John,
I was wondering if I could get a copy of SUB2019-97 to review the Planning notes? I forgot to put my
name in CV, but I am the Planning reviewer. I think it came in when I was out.
Thanks!
Tori