HomeMy WebLinkAboutWPO201700047 Bond Estimates 2018-07-03 Barterbrook Phase 2 7/3/2018
WPO file number: WP0201700042
Erosion and Sediment Control Bond Estimate
Item Item No. Unit Unit Cost Cost
Number (installed)
stablization(PS,TS) 0.13 acres $3.000.00 $390.00 .
silt fence(SF) 2295.0 ft $4.50 $10,327.50
safety fence(SAF) 0.0 ft $4.50 $0.00
diversion(DV,FD,RWD) 0 ft S13.00 $0.00
temporary slope drain(TSD) pipe length 0 ft pipe diameter 0 $0.00 $0.00
earthwork for trap/basin
height of dam at toe 0 ft cut at high side 0't
height of fill at face ft cut at face • 0 ft
length of dam ft length of cut 'ftft top width ft width of cut
.:re transition) 0 sf (area be: .ansition) 0 sf
total width of dam) 0 ft (total width of cut) 0 ft
(height below transition) 0 ft (depth below transition 0 ft
(area below transition) 0 sf (area above transition 0 sf
.17.'fil'vo,s-le.' 0.0 cy (total fill volume) 0.0 cy
length of spillway ft (TOAL CY estimate) 0 cy $13.00 $0.00
width of spillway _ft (spillway stone tons) 0 tons $50.00 $0.00
structures for basin _
riser height a.ft
riser diameter 0 in (riser unit price) $0.00 $0.00
barrel length 0 ft base plate orfdn $200.00 $0
barrel diameter 0 in (ba $0.00 $0.00
barrel collars $200.00 $0
baffle length 11111ft $50.00 $0
silt fence inlet protection(IP) "iml $t00.0u $200.00
stone inlet protection(IP) $200,00 $200.00
outlet protection(OP) length 0 ft width 0 ft 111111111 $0.00 $0.00
channel(SCC,matted) length 0 ft width 0 ft $0.00
check dam depth in channel 0 ft channel width 0 ft $0.00 $0.00
construction entrance(CE) $2.500,00 $0.00
wash rack 1 S2,000,00 $2,000.00
paved construction entrance $3,500.00 $3,500.00
rip-rap,placed depth 0 ft length ft
width 0.0 0 tons 560.00 $0,00
survey and layout(price per 0.1 mi.) acres 0 traps and basins $0.00
mobilization $2,500.00
stream crossing(computed independently) $0.00
1 costsum $19,117.50
contingency $1,911.75
Total $21,030
7/6/2018