October 24, 2019
Mr. Jonathan Showalter, P.E. —Timmons Group
608 Preston Ave., Suite 200, Charlottesville,VA 22902
(434)-327-1681 /jonathan.showalter@,timmons.com
Mr. Joseph Letteri—Albemarle County School Board
401 McIntire Road, Charlottesville,VA 22902
(434)-975-9340/jletteri@,kl2albemarle.org
RE: Conditional Approval of SDP-2019-00055
(Scottsville Elementary School Addition—Initial Site Plan / Digital—9/9/2019)
Mr. Showalter and Mr. Letteri:
The Agent for the Board of Supervisors hereby administratively grants conditional approval to the above
referenced Initial Site Plan (dated 9/9/2019). A Final Site Plan for this project will not be approved until
all review comments identified in the attached updated SRC comment letter(dated 10/24/2019)have
been addressed and resolved to the satisfaction of each applicable SRC Plan Reviewer, and until each
SRC Plan Reviewer have indicated in writing their(tentative) approval.
Please note important updates or clarifications to the updated SRC comment letter(dated 10/24/2019):
• Planning comment#3 has been updated and withdrawn;
• VDOT comments were provided on 10/22/2019 and are attached therein;
• VDH comments were provided on 10/22/2019 and are attached therein; and
• CDD-Engineering comments were provided on 10/23/2019 and are attached therein.
This conditional approval shall be valid for a period of five (5) years from the date of this letter,provided
that the developer submits a Final Site Plan for all or a portion of the site within one(1)year after the
date of this letter as provided in section 32.4.3.1 of Chapter 18 of the Code of the County of Albemarle,
and thereafter diligently pursues approval of the Final Site Plan.
In accordance with Chapter 18 of the Code of the County of Albemarle, Section 32.4.2.8, Early or Mass
Grading may be permitted after the following approvals are received:
1. Engineering approval of a VSMP plan meeting the requirements of Chapter 17 of the Code of the
County of Albemarle.
2. Approval of all easements for facilities for stormwater management and drainage control.
1
3. Submittal of a tree conservation checklist with areas for tree preservation identified.
Please be advised that the Final Site Plan will not be considered to have been officially submitted until
the following items are received:
1. A Final Site Plan that satisfies all of the requirements of Section 32.6 of Chapter 18 of the Code.
2. A fee of$1,613.00 per Section 35.1.c(3) of Chapter 18 of the Code.
You may continue to utilize CDD's digital submission and digital review process for the Final Site Plan,
if you wish. However, if you choose to submit the Final Site Plan through the traditional paper/hard-copy
submittal and review process, please submit a minimum of nine (9) copies of the Final Site Plan to the
Community Development Department (CDD). The assigned Lead Reviewer will then distribute the plans
to all reviewing agencies. (Note:for ACSA,please coordinate directly with Mr. Alex Morrison or Mr.
Richard Nelson to determine how many copies ACSA requires; it may be more than the one (1) minimum
copy specified below). CDD staff will then provide you with the first comment letter containing review
comments from each SRC plan reviewer for the Final Site Plan; after receiving that letter,please work
directly with each SRC plan reviewer to address and resolve their respective requirements.
The Community Development Department shall not accept submittal of the four(4) signature copies of
the Final Site Plan (for final approval signatures) until each of the following agencies/reviewers indicate
in writing that the Final Site Plans satisfies the attached conditions* and all other applicable
requirements, and has been given (tentative) approval:
SRC Members(and minimum number of copies required by each,if traditional paper/hard-copy submittal):
• Albemarle County Planning Services (Planner)—2 copies
• Albemarle County Engineering Services (Engineer)— 1 copy
• Albemarle County Information Services (E911)— 1 copy
• Albemarle County Inspections Services (Inspections)— 1 copy
• Albemarle County Department of Fire & Rescue (Fire—Rescue)— 1 copy
• Albemarle County Service Authority (ACSA)— 1 copy (minimum); please coordinate directly with
ACSA to determine total number of copies
• Virginia Department of Transportation (VDOT)— 1 copy
• Virginia Department of Health (VDH)— 1 copy
If you have any questions about this conditional approval, or the Final Site Plan submittal requirements,
or any other aspect of your application(s), please feel free to contact me using the information provided
below. Community Development staff remain available to assist.
Thank you; sincerely,Pa414tig
<14,;‘,„stif int
Tim Padalino, AICP
Senior Planner/tpadalino(aalbemarle.org/ (434)-296-5832 x 3088
*Attached conditions:
• SRC comment letter(dated 10/21/2019; updated 10/24/2019)
2
pF ALA_
PLRGi.w,
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road,North Wing
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
October 21,2019 UPDATED October 24,2019
Mr.Jonathan Showalter,P.E.-Timmons Group
608 Preston Ave., Suite 200,Charlottesville,VA 22902
(434)-327-1681 /jonathan.showalter(a�timmons.com
RE: UPDATED SRC Comment Letter for SDP-2019-00055
(Scottsville Elementary School Addition-Initial Site Plan /Digital-9/9/2019)
Mr. Showalter:
The Planner for the Planning Division of the Albemarle County Community Development Department(CDD)and
other members of the Site Review Committee(SRC)have reviewed the development proposal referenced above.
Initial review comments from the following SRC members are included in this comment letter:
Albemarle County CDD-Planning Services(Planner)
Albemarle County CDD-Engineering Services(Engineer)
Albemarle County CDD-Building Inspections(Inspections)
Albemarle County CDD-Architectural Review Board(ARB)
Albemarle County CDD-Information Services(E911)
Albemarle County Department of Fire-Rescue
Albemarle County Service Authority(ACSA)
Virginia Department of Transportation(VDOT)
Virginia Department of Health(VDH)
Each comment is preceded by the applicable reference to Chapter 18 of the Albemarle County Code(Zoning
Ordinance)unless otherwise specified. (The following comments are those that have been identified at this time;
additional comments may be added or eliminated based on further review.)
The Planner will either approve with conditions or deny the Initial Site Plan within 15 days of the Site Review
Committee Meeting.
Please contact me at your earliest convenience if you have questions about this comment letter, the applicable
regulations, or any other issue involving your application, or if you otherwise require additional information or
assistance prior to the SRC Meeting on Thursday,October 24.
Sincerely,
- ----,14;v4 int Pa.414,,A,:ws-'
Tim Pada mo,AICP
Senior Planner/Community Development Department-Planning Division
(434)-296-5832 x 3088/tpadalino@albemarle.org
Page 1 of 4
Albemarle County Planning Services(Planner):
Contact: Tim Padalino/tpadalino(2l albemarle.org
Review Status: Requested Changes(10/21/19)—UPDATED 10/24/2019(see Planner comment#3)
1. [Z.O.32.5.2(a)]: Please add"Initial Site Plan"and"SDP201900055"to Sheet C.0(Cover Sheet).
2. [Z.O.32.5.2(a),32.5.2.(b)]: Please revise the"Site Data"information on Sheet C.0(Cover Sheet)as follows:
A. For"Zoning,"please add"Rural Areas"to"RA"and please include"Critical Slopes Overlay."
B. Please provide additional information to identify or clarify the proposed use(s),as follows:
i. the proposed maximum amount of impervious cover on the site; and
ii. the proposed parking schedule(see CDD-Planning comment#3,below).
3. [Z.O.32.5.2(a),32.7.3,4.12.6,4.12.14]:
Regarding the required number of parking spaces,Z.O.4.12.6 states the following:
"Schools: The number of proposed spaces shall be shown in a parking study submitted by the school
division(public schools)or the school(private schools). The number of required spaces shall be determined
by the zoning administrator. In making the determination,the zoning administrator shall consider the
recommendations in the parking study,traffic generation figures either known to the industry or estimated
by the Institute of Transportation Engineers,peak parking demands,and other relevant information."
UPDATE 10/24/2019: Staff acknowledges that the plans show the demolition of 15 existing parking spaces
(inclusive of one existing ADA space), and also show 15 proposed new parking spaces(inclusive of one new
ADA space),thereby creating no net loss or net gain in the number of parking spaces. Staff also acknowledges
the applicant's explanation during the 10/24 SRC meeting that this proposed school addition only serves to
provide increased facility accommodations, and the proposal does not include any corresponding additions to
staff or additional students.Therefore,considering that the overall number of parking spaces remains unchanged,
and considering the applicant's explanation that the addition will not generate additional parking needs,no
further information or revision related to Planner comment#3 is required. Planner comment#3 is withdrawn.
4. [Z.O.32.5.2(p),32.7.9.2.(b),32.7.9.4.(b)]: The following issues(below)were identified during the initial staff
review of the Landscape Plan, and must be addressed and resolved on the Final Site Plan.Any additional
detailed review comments pertaining to the Landscape Plan,if any are necessary,will be provided with the SRC
Action Letter,within 15 days or less of the SRC meeting.
A. A Conservation Checklist will need to be completed, signed, and added to the Landscape Plan to
ensure that the specified trees will be protected during construction.
• Note: Staff acknowledges the Conservation Checklist on Sheet L2.0(Landscape Notes And
Details);however,this checklist needs to be completed and signed.
B. The corresponding tree protection(TP)equipment and practices shown on Sheet L1.0(Landscape
Plan)that are intended to protect existing trees (including but not limited to the trees to be preserved,
the limits of clearing,the location and type of protective fencing,grade changes requiring tree wells or
walls,and trenching or tunneling proposed beyond the limits of clearing)must be shown on Sheets
C2.1 (Demolition Plan),C3.2 and C3.3 (E&S Control Plans),and C5.0(Grading&Drainage Plan).
• Note: Staff acknowledges that some tree protection measures are shown on the sheets listed
above;however,additional tree protection measures shown on Sheet L1.0(Landscape Plan)
appear to be missing on the sheets identified above. Specifically,three deciduous trees along
the internal travelway are identified for"TP"on Sheet L1.0,but these are not all shown with
"TP"on all sheets identified above.
C. Please add a note to Sheet L1.0 or Sheet L2.0 to verify that"The landscape plan satisfies the minimum
landscaping and screening requirements of Zoning Ordinance Section 32."
■ (Advisory/For Future Reference): Please note that the Final Site Plan cannot be approved unless and until all
the outdoor lighting information required by Z.O. 32.6.2(k)is provided to demonstrate compliance with all
applicable outdoor lighting requirements as specified in Z.O.4.17,per Z.O. 32.7.8.b. However,this information
is not required prior to County approval of this Initial Site Plan(as may be applicable).
Page 2 of 4
• (Advisory/For Future Reference): Please note that the Final Site Plan cannot be approved unless and until a
Certificate of Appropriateness(CofA)required by Z.O. Sections 32.4.2.2.b, 32.4.3.3,and 32.4.3.6 is issued on
behalf of the Albemarle County Architectural Review Board. Staff acknowledges the ongoing review of CofA
applications ARB201900100 and ARB201900106; and staff further acknowledges ARB staff's review status of
"No Objection"for this Initial Site Plan application SDP201900055.
• (Advisory/For Future Reference): Please note that a Final Site Plan for this proposed project cannot be
approved unless and until a Water Protection Ordinance Plan/VSMP Plan is submitted,reviewed, and
approved by the Engineering Services Division of the Community Development Department as required per
Z.O. 32.7.4.1 and County Code Chapter 17. Staff acknowledges the ongoing review of WPO201900051.
Albemarle County Engineering Services(Engineer):
Contact: David James/djames2@u,albemarle.org
Review Status: Requested Changes(10/23/19);please see attached CDD-Engineering comment letter.
Albemarle County Building Inspections(Inspections):
Contact: Michael Dellinger/mdellinger(uialbemarle.org
Review Status: Requested Changes(9/17/19)
1. Accessible parking spaces and access isles shall not have a surface slope greater than 1:48.Access isles shall
be at the same level as the parking space they serve.
2. Add the following note to the general notes page: ALL water lines,sewer lines,and fire lines from the main
to the structure MUST have a visual inspection performed by the building department.
3. Add the following to the general notes page: All roof drains shall discharge in a manner not to cause a public
nuisance and not over sidewalks.
4. Add the following note to the general notes page: Building or structures built before January 1, 1985 must
have an asbestos survey performed in order to apply for a permit. Asbestos removal permits are required if
positive for such. Contact VDOLI for additional requirements and permits for demolition projects.
5. Add the following note to the general notes page: Building inspections must verify proper abandonment of
site utilities before concealment.
Albemarle County Architectural Review Board(ARB):
Contact: Margaret Maliszewski/mmaliszewski@albemarle.org
Review Status:No Objection(10/9/19)
Albemarle County Information Services(E911):
Contact: Andy Slack/aslack@albemarle.org
Review Status: No Objection(9/19/19)
Albemarle County Department of Fire&Rescue(Fire-Rescue):
Contact: Shawn Maddox/smaddox(cr�,albemarle.org
Review Status: Requested Changes (10/18/19)
1. Emergency apparatus access must be provided to within 150'of each corner of the building. When the travel
way exceeds 150'an apparatus turn around must be provided.
2. If the height of the building will exceed 30'then the travel way must be 26'of unobstructed travel width.
3. An on-site fire protection water supply should be considered.Provide the ISO needed fire flow calculations
for the structure to include the existing and new portion.
Albemarle County Service Authority(ACSA):
Contact: Richard Nelson/rnelsonaserviceauthority.org
Review Status:No Objection(10/9/19)
• SDP201900055 is outside the ACSA jurisdictional area. There are no comments.
Page 3 of 4
Virginia Department of Transportation(VDOT):
Contact: Adam Moore/Adam.Moorenaivdot.virginia.gov
Review Status:No Objection(10/22/19);please see attached VDOT letter.
Vir2inia Department of Health(VDH):
Contact: Alan Mazurowski/alan.mazurowskina,vdh.virginia.gov
Review Status: Requested Changes(10/22/19);please see attached VDH comment letter.
Page 4 of 4
PROJECT: SDP201900055
SCOTTSVILLE ELEMENTARY SCHOOL ADDITION - INITIAL— DIGITAL
Engineering comments (David James):
1. Show location of all existing and proposed utilities and easements with deed book references.
2. Show the existing contours for the site where not shown and next to property line where not
shown.
3. Sheet 2: Show existing onsite well location. Show existing w/I connections.
4. Will proposed additions require additional w/I connection(s)? Sewer connections? Please show
proposed sewer&water connections.
5. Correct the amount of slope in parking area to be 5%or under.
44 ,
/ \
IP
QUU
' ..:*141, /
4
�'• �� .601
_,
At,. -,
.\A.
ImiNs,b
lb,
,,
t.
,,,,,,,
\ - . .,
,,,,,,\/‘ .....N
,- \,\,‘ : N.
t //
6. Show bumper blocks for the parking spaces. Show bumper block detail. Bumper blocks are
required where sidewalks are less than 6' wide in front of the parking spaces. {18-4.12.16 e}
7. Guardrail needed here along turn radius.
1 \
1
i
i
.0 f
i . ,/
\\ RII
\ FF
39
2 z
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper.Virginia 22701
Stephen C. Brich, P.E.
Commissioner
October 22, 2019
Tim Padalino
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
14 SDP-2019-00055- Scottsville Elementary School Addition— Initial Site Plan
Dear Mr. Padalino:
The Department of Transpprtation, Charlottesville Residency Transportation and Land Use
Section, has reviewed the Above referenced plan as submitted by Timmons Group,dated
September 09, 2019 and find it to be generally acceptable.
Please note that the final site plan must show conformance with the VDOT Road Design Manual
Appendices B (1) and F, as well as any other applicable standards, regulations, or other
requirements.
Please provide a copy of the revised plan along with a comment response letter. If further
information is desired, please contact Willis C. Bedsaul at 434-422-9866.
A VDOT Land Use Permit will be required prior to any work within the right of way. The
owner/developer must contact the Charlottesville Residency land Use Section at (434)422-9399
for information pertaining to this process.
Sincerely, it
CAttiv,'
ltkorb-k,
Adam J. Mo re, P.E.
Area Land Use Engineer
Charlottesville Residency
WE KEEP VIRGINIA MOVING
Tim Padalino
From: Tim Padalino
Sent: Thursday, October 24, 2019 1:08 PM
To: Jonathan Showalter
Cc: Joe Letteri
Subject: RE: SRC comment letter: Scottsville ES Addition -- Initial Site Plan
Attachments: SDP201900055_Scottsville ES Add_Initial_Letter of Conditional Approval_2019-10-24.pdf
Hello again Jonathan,
Thanks for attending the SRC meeting this morning and discussing the Scottsville Elementary School project.
I've updated the SRC comment letter, and have attached that to a letter of conditional approval for this Initial Site
Plan. Both of those are attached to this message. I will also update County application tracking software to reflect
this conditional approval.
Please let me know if there are any questions you would like to go over as you prepare the Final Site Plan, or at
any point in time.
Thanks very much - - -
Tim Padalino I (434)-296-5832 x 3088
From:Tim Padalino
Sent:Tuesday, October 22, 2019 11:57 AM
To:Jonathan Showalter<Jonathan.Showalter@timmons.com>
Cc:Joe Letteri<jletteri@k12albemarle.org>
Subject: SRC comment letter: Scottsville ES Addition-- Initial Site Plan
Hello Jonathan,
Please find attached the SRC review comment letter for the Initial Site Plan referenced above (SDP201900055).
Unfortunately, we are still waiting on review comments from the Health Department, VDOT, and CDD-Engineering.
I will forward to you any/all review comments I receive prior to the SRC meeting on Thursday morning (unless
those reviewers copy you directly).
Please let me know if you have any questions prior to the meeting; otherwise, I will plan to see you there.
Thanks very much - - -
Tim Padalino,AICP
(434)-296-5832 x 3088
Senior Planner I Community Development Department— Planning Division
https://www.albemarle.org/department.asp?department=cdd