November 25, 1985
W. S. Figgatt
Rt. 1, Box 125
Crozet, VA 22932
RE: vZMA-85-28 W. S. Figgatt
\/SP-85-78 W. S. Figgatt
Dear Mr. Figgatt:
The Albemarle County Board of Supervisors, at its meeting on November
25, 1985, by a vote of 6/0, approved the above noted petitions. This
approval is subject to the following conditions:
1. The sand removal activity shall be conducted in such a manner so
as not to impede canoe and boat passage;
2. No tree removal shall be permitted except as is necessary to
provide access to sand deposits. The sand removal activity shall
be conducted in such a manner so as not to expose the root system
of shoreline trees by river bank excavation nor shall equipment
travel over, be parked on, or otherwise encroach on tree root
systems;
3. On -site processing shall be limited to screening of excavated
material. No washing of excavated material shall be permitted;
4. Use and maintenance of sediment curtains shall be required during
dredging operations; if recommended as being effective and
purposeful by the Virginia Marine Resources Commission;
-5. County Engineer approval of entrance road specifications in
accordance with 30.4.11.2 of the Zoning Ordinance;
(6.' Compliance with the soil erosion and sedimentation control
ordinance. In review of plans, the Soil Erosion Committee should
be mindful of the conditions of this special use permit;
"T. The County Engineer shall make semi-annual inspection of the
sites to insure compliance with conditions 1 through 6 of this
special use permit. The County Engineer may require such
corrective measures as deemed necessary to insure compliance with
these conditions;
8. Virginia Department of Highways & Transportation approval of
commercial entrance;
9. No operation shall occur between March 1 and June 30;
10. Compliance with Section 5.1.28 of the Zoning ordinance as outlined
in County Engineer's memo of November 7, 1985;
11. The extraction operation is limited to crane and drag -line bucket
operation. Not more than one crane and drag -line bucket assembly
shall be located on the property at any given time;
12. Special use permit shall expire at the end of five years.
If you should have any questions regarding the above -noted action,
please do not hesitate to contact me.
Sincerely, /
Jphn T. P. Horne