HomeMy WebLinkAboutWPO201900050 Bond Estimates 2019-12-11 (2)Project Name: Berkmar Overlook VSMP Plan (WP0201900050) WPO file number: WP0201900050 TMP(s): 45-112F1, 45-112F2, 45-84A & 45-85 Date Estimate Completed: 12/08/2019; chkby JA /Albemarle, 12/11/19 Erosion and Sediment Control Bond Estimate Item Item No. Unit Unit Cost Cost Number installed stablization (PS, TS) acres $5,000.00 $48,500.00 silt fence (SF) 2555. ft $5.00 $12,775.00 safety fence (SAF) 1770.0 ft $5.00 $8,850.00 diversion (DID, FD, RWD) 1485 ft $13.00 $19,305.00 temporary slope drain (TSD) pipe length 0 ft pipe diameter 0 in $0.00 $0.00 earthwork for trap/basin: Sediment Basin #1 height of dam at toe 8 ft cut at high side 14 ft height of fill at face 2 ft cut at face 12 ft length of dam 195 ft length of cut 200 ft top width ft width of cut 25 ft bove transition 28 sf k transitic (total width of dam) 16 ft (total width of cut) 77 ft (height below transitio 6 ft (depth below transit 2 ft (area below transition: 12 sf (area above transiti, 73 sf (total fill volume) 288.9 cy (total fill volume) 4896.3 cy length of spillway ft (TOAL CY estimate 4993 cy $13.00 $64,909.00 width of spillway ft (spillway stone tons 25.9 tons $50.00 $1,295.00 structures for basin riser height ft riser diameter 4 in (riser unit price) $150.00 $1,350.00 barrel length 11 ft base plate or fdn $200.00 $200 barrel diameter 18 in )rice) $40.00 $4,480.00 barrel collars $200.00 $400 baffle length 1Mft $50.00 $0 earthwork for trap/basin: Sediment Trap #1 height of dam at toe 2 ft cut at high sideEft ft height of fill at face 0 ft cut at faceft length of dam 140 ft length of cutft top widthL 3 ft width of cut a ca auuve transition pl sf (died uuiuvv transitic 92 sf (total width of dam) 4 ft (total width of cut) 31 ft (height below transitio 2 ft (depth below transit 0 ft (area below transition; 0 sf (area above transitic 0 sf (total fill volume) 0.0 cy (total fill volume) 408.9 cy 12/11/2019 Project Name: Berkmar Overlook VSMP Plan (WP0201900050) WPO file number: WP0201900050 TMP(s): 45-112F1, 45-112F2, 45-84A & 45-85 Date Estimate Completed: 12/08/2019; chkby JA /Albemarle, 12/11/19 Erosion and Sediment Control Bond Estimate Item Item Number length of spillway ft width of spillway ft silt fence inlet protection (IP) stone inlet protection (IP) outlet protection (OP) #1 length 12 ft outlet protection (OP) #2 length 20 ft channel (SCC, matted) length 0 ft check dam depth in channel 1 ft construction entrance (CE) wash rack paved construction entrance rip -rap, placed depth 2 ft width 6.0 survey and layout (price per 0.1 mi.) acres 9.7 mobilization stream crossing (computed independently) WP0201900050 ESC_bond -Berkmar Overlook-CE120819 chk ja121119 JOAL CY estimate (spillway stone tons width width width channel width No. Unit Unit Cost installed 409 cy $13.00 14.4 tons $50.00 $100.00 $200.00 6 ft $324.00 6 ft $540.00 Oft �Ift length -ft 13.8 tons traps and basins cost sum contingency Total $135.00 $2,500.00 $2,000.00 $3,500.00 $60.00 Cost $5,317.00 $720.00 $1,000.00 $4,000.00 $648.00 $1,080.00 $0.00 $270.00 $0.00 $4,000.00 $7,000.00 $828.00 $5,850.00 $2,500.00 $0.00 $195,277.00 $19,527.70 $214,810 12/11/2019