HomeMy WebLinkAboutWPO201900039 Bond Estimates 2020-01-21Project Name: Hillcrest Vineyard Tasting & Venue VSMP WP02019-00039 WPO file number: WP0201900039 TMP(s): 06900-00-00-02000 Date Estimate Completed: 12-30-19 ; rev. 1/21/20 (JA) Erosion and Sediment Control Bond Estimate Item Item Number 1 2 3 4 5 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 stablization (PS, TS) silt fence (SF) safety fence (SAF) diversion (DID, FD, RWD) temporary slope drain (TSD) pipe length Sediment Basin #1 earthwork for trap/basin _ 0 ft pipe diameter length of dam 140 ft ft height of dam at toe 2 ft height of fill at face 0 ft Note: initial earthwork Vol.=4066.7 Sediment Trap #1 earthwork for trap/basin cut at high side cut at face length of cut width of cut (area below transitic (total width of cut) (depth below transit (area above transiti, (total fill volume) (TOAL CY estimate (spillway stone tons �in ft ft ft ft 539 sf 75 ft 2 ft 71 sf 4066.7 cy 4067 cy 34.5 tons (riser unit price) $150.00 base plate orfdn (barrel unit price) $40.00 barrel collars baffle lengthWft I height of dam at toe ft cut at high side 8 ft height of fill at face 3. (area above transition 38.48 sf (total width of dam) 23.4 (height below transitic 8 ft (area below transition; 29.6 sf (total fill volume) 151.3 cy ft (depth below transit 4 ft length of spillway -ft Rev. unit price, earthwork, $6 /cy, Approved by County Engineer Initial ST, Earthwork=$5,447 ft length of dam 6 ft top width ft ft cut at face cut at face 4 ft length of cut 60 ft width of cut 17 ft (area below transitic 100 sf (total width of cut) 41 No. Unit Unit Cost Cost installed 137 acres $5,000.00 $66,200.00 7740.0 ft $5.00 $38,700.00 0.0 ft $5.00 $0.00 1250 ft $13.00 $16,250.00 $0.00 $0.00 CDIRECT 2865 ENTR $6.00 $17,190.00 $50.00 $1,725.00 $1,062.00 $200.00 $200 $2,400.00 $200.00 $200 $50.00 $0 $6.00 $2,514.00 1 /21 /2020 Project Name: Hillcrest Vineyard Tasting & Venue VSMP WP02019-00035 WPO file number: WP0201900039 TMP(s): 06900-00-00-02000 Date Estimate Completed: 12-30-19 ; rev. 1/21/20 (JA) Erosion and Sediment Control Bond Estimate Item Item Number 42 width of spillway ■ _ft 43 silt fence inlet protection (IP) 44 stone inlet protection (IP) 45 outlet protection (OP)-Basin#1 length ft 46 outlet protection (OP) length ft47 channel (SCC, matted) - EC-2 on 3:1 length ft lift 48 check dam depth in channel 49 construction entrance (CE) 50 wash rack 51 paved construction entrance 52 rip -rap, placed, dam /rprapspillway depth W45.0ft53 width 54 55 survey and layout (price per 0.1 mi.) acres JW1 3.24 56 mobilization 57 Temporary Access road (spillway stone tons 10.5 tons width width width channel width ft ft ft ft length -ft (tons 543.375 tons traps and basins WP0201900039 Hillcrest Vineyard Tasting & Venue VSMP ESC_bond_est 123019, rev orarao Initial ESC Plan bond Amt. /Est. = 325 690 No. Unit Unit Cost installed $50.00 1 $100.00 1 $200.00 1 $486.00 g $0.00 $135.00 $2,500.00 $2,000.00 $3,500.00 $60.00 Cost $525.00 $200.00 $200.00 $486.00 $0.00 $60,580.00 $810.00 $0.00 $2,000.00 $3,500.00 $32,602.50 $215,272.50 $7,620.00 $2,500.00 cost sum $257,464.50 contingency $25,746.45 Total $283,220 1 /21 /2020