HomeMy WebLinkAboutSDP201900080 Review Comments Initial Site Plan 2020-01-30County of Albemarle
Department of Community Development
Memorandum
To: Tim Padalino
From: Emily Cox
Date: 30 January 2020
Subject: Brook Hill River Park Boat Launch — Initial Site Plan (SDP201900080)
The Brook Hill River Park Boat Launch — Initial Site Plan has been reviewed by Engineering. The
following comments will need to be addressed before approval:
1. WPO Plan satisfying VSMP requirements must be submitted and approved before final
site plan approval.
2. Floodplain Development Permit (FDP) must be submitted and approved before final site
plan approval.
3. Fill is not allowed in the floodplain, therefore the proposed earthen mounds are not
allowed.
4. Ensure all proper permits are obtained (army corps of engineers, VDOT, etc.) It appears
the army corps must be contacted because the proposed detail for the boat launch shows
work below the mean water level. It appears drainage goes off site onto VDOT property,
so a land use permit or something else may be required.
5. The nearby Brookhill development is spelled as one word. (Just wanted to make sure you
were aware)