From: Alexander Morrison <amorrison@serviceauthority.org>
Sent: Tuesday, December 12, 2017 4:07 PM
To: Cameron Langille
Subject: RE: SUB201700107: Northfields Lot 1C Final Plat
Cameron,
Jeremy has held a pre -construction meeting with the applicant. I believe they still need to order materials. He said it
sounded like they were in a hurry. Maybe pose the question to them if they want to hold off on the approval until they
install, or go ahead and bond it to obtain approval.
Alexander J. Morrison, P.E.
Senior Civil Engineer
Albemarle County Service Authority
168 Spotnap Road
Charlottesville, Virginia 22911
(0) 434-977-4511 Ext. 116
(C) 434-981-5577
(F) 434-979-0698
From: Cameron Langille [mailto:blangille@albemarle.org]
Sent: Tuesday, December 12, 2017 4:02 PM
To: Alexander Morrison <amorrison@serviceauthority.org>
Subject: RE: SUB201700107: Northfields Lot 1C Final Plat
Hi Alex,
Since County Code requires that the utilities be built or bonded prior to final plat approval, they still need to either
install the sewer or have it bonded before we can sign and approve the plat. Have you had any conversations with the
applicant regarding when they expect to start construction of the sewer lines?
Thanks,
Cameron
From: Alexander Morrison [mailto:amorrison@serviceauthority.org]
Sent: Thursday, December 07, 2017 10:08 AM
To: Cameron Langille <blangille@albemarle.org>
Subject: SUB201700107: Northfields Lot 1C Final Plat
Cameron,
The sewer utility plan has been approved. The plan adjusted the sewer alignment across lot 2A and 1C. The applicant
shall update the plat accordingly and submit it for approval. They should ensure there are notes that the sewer
easement is to be centered on the as -built location.
Alexander J. Morrison, P.E.
Senior Civil Engineer
Albemarle County Service Authority
168 Spotnap Road
Charlottesville, Virginia 22911
(0) 434-977-4511 Ext. 116
(C) 434-981-5577
(F) 434-979-0698