Loading...
HomeMy WebLinkAboutSUB201700107 Correspondence Final Plat 2017-12-14Cameron Langille From: Alexander Morrison <amorrison@serviceauthority.org> Sent: Tuesday, December 12, 2017 4:07 PM To: Cameron Langille Subject: RE: SUB201700107: Northfields Lot 1C Final Plat Cameron, Jeremy has held a pre -construction meeting with the applicant. I believe they still need to order materials. He said it sounded like they were in a hurry. Maybe pose the question to them if they want to hold off on the approval until they install, or go ahead and bond it to obtain approval. Alexander J. Morrison, P.E. Senior Civil Engineer Albemarle County Service Authority 168 Spotnap Road Charlottesville, Virginia 22911 (0) 434-977-4511 Ext. 116 (C) 434-981-5577 (F) 434-979-0698 From: Cameron Langille [mailto:blangille@albemarle.org] Sent: Tuesday, December 12, 2017 4:02 PM To: Alexander Morrison <amorrison@serviceauthority.org> Subject: RE: SUB201700107: Northfields Lot 1C Final Plat Hi Alex, Since County Code requires that the utilities be built or bonded prior to final plat approval, they still need to either install the sewer or have it bonded before we can sign and approve the plat. Have you had any conversations with the applicant regarding when they expect to start construction of the sewer lines? Thanks, Cameron From: Alexander Morrison [mailto:amorrison@serviceauthority.org] Sent: Thursday, December 07, 2017 10:08 AM To: Cameron Langille <blangille@albemarle.org> Subject: SUB201700107: Northfields Lot 1C Final Plat Cameron, The sewer utility plan has been approved. The plan adjusted the sewer alignment across lot 2A and 1C. The applicant shall update the plat accordingly and submit it for approval. They should ensure there are notes that the sewer easement is to be centered on the as -built location. Alexander J. Morrison, P.E. Senior Civil Engineer Albemarle County Service Authority 168 Spotnap Road Charlottesville, Virginia 22911 (0) 434-977-4511 Ext. 116 (C) 434-981-5577 (F) 434-979-0698