Loading...
HomeMy WebLinkAboutWPO202000026 Review Comments Erosion Control Plan 2020-05-18COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VESCP Permit Plan Review Project: Yancey Farm Pad 2 — VESCP Project file#: WP02020-00026 Plan preparer: Logan O'Day — Roudabush, Gale, & Assoc., Inc. / Engineering 172 South Pantops Drive, Suite A, Charlottesville, VA 22911 [ lodU(d)roudabush.com ] Owner or rep.: Charles Ernest Yancey / 6557 Dick Woods Road, Charlottesville, VA 22903 Plan received date: 23 Apr 2020 Date of comments: 18 May 2020 Reviewer: John Anderson County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any NISN4P VESCP permit by issuing a project approval or denial. This project is denied for reasons listed below. The VESCP application content requirements can be found in County Code section 17-402. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESOP, (3) a SWMP, and (4) any TMDL measures necessary. 1. Provide SWPPP, given potential for erosion. Use Albemarle county SWPPP template. Link: http://www.albemarle.ore/uDload/imaees/forms center/departments/Community Development/fonns/Eneineerine and WPO Forms/Stormwater Pollution Prevention Plan SWPPP template.pdf B. Pollution Prevention Plan (PPP) — See above. The PPP content requirements can be found in County Code section 17-404. 1. Please ensure PPP Exhibit identifies: a. Rain gauge b. Construction entrance that drains to a trapping measure C. Stormwater Management Plan (SWMP) — NA: VESCP only VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved for reasons listed below. The stormwater management plan content requirements can be found in County Code section 17-403. D. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved for reasons listed, below. The erosion control plan content requirements can be found in County Code section 17-402. Sheet 1 2. Revise sheet index to list sheet 4 as Phase II. 3. Revise plan title to include ref. to WPO2020-00026. 4. Include title sheet Note that the fill activity is subject to 18-5.1.28. 5. Include Note that the land disturbance activity is subject to 17-300 (VESCP). 6. Include Note that Engineering has determined the activity is not subject to 17-302 (VSMP). Engineering Review Comments Page 2 of 4 7. An ESC Plan bond is required. Please submit bond estimate request form at earliest convenience. Link: http://www.albemarle.or,gwload/images/forms_center/departments/CommunityDevelopment/forms/bondsBond_Reg uest to Establish a Bond.pdf Sheet 3 8. Silt fence bars entry to fill site; provide break in SF so haul trucks may enter. 9. Similarly, provide break in silt fence at base of 18' sediment trap weir. 10. Provide site -specific sediment trap profile. This is a substantial sediment trap. VESCH typical /generic detail (sheet 6) is inadequate. 11. Where proposed grade ties to existing grade, there are new permanent channels. Evaluate channel capacity /velocity against 2-, 10-yr events, respectively. Evaluate permanent channels for erosion. Provide /specify stabilization matting /blanket, if needed, for permanent channels created by proposed final grade. (blue arrows; images below) Sheet 3: Sheet 4 Engineering Review Comments Page 3 of 4 12. Acquire temporary off -site construction easement, TMP 71-21, if needed. 13. Revise design (as needed) to ensure no off -site erosive impact, or construction impact to TMP 71-21, unless easement acquired to allow off -site construction. Runoff may not impact adjacent parcels. Evaluate. Furnish calculations. 14. Provide channel cross -sections for permanent channels (north / south) created by proposed final grade, sheet 4. Sheet 4 15. Phase II diversion dike (DD) is impermissible as a permanent measure (it is a temporary ESC measure). Provide, instead, a permanent grass -lined or stabilized channel capable of withstanding 2-yr event runoff, capable of containing 10-yr event volume. 16. Certain sections of SF in Phase 11 lie upslope of final graded -disturbed areas, and are not strictly needed (comment applies to sheet 3, as well). 17. Revise legend to include WR. Do not recognize this symbol in the VESCH. 18. Sheet 5: Few if any references to Stormwater Management on this sheet are necessary; majority of references may be removed. Also, item 5, above. 19. Include code text at 18-5.1.28, Borrow, fill or waste areas (below), on the plans (except 18-5.1.28.b.6., since an Erosion and Sediment Control plan is required). Ensure text is readable. Link to text: https:Hlibrary.municode.com/va/albemarle county/codes/code of ordinances?nodeld=COALCOVI CH18ZO S 5SURE S5.ISURE S5.1.28BOFIWAAR Engineering Review Comments Page 4 of 4 Sec S.l2a eOPmv.4u or T,a]1. aneai i a d 9 a. s,mwirp.r.nw..avuaraa..,.uw..gen,e,«mlw,nG [. e,en.n•Rea•e..rwtl»•,n.re,r•mwwa+a=.a va9we>om.,m..wr.�.e pxrnr errav�nl9ee+seN..p,•rvuwnlewmn.w.,..r.Mn.]anwNv�wwae.reea.m.ragwwarr�.wwm.u.w..rasel•w.�w»�nanaw.erwxr •.water e«n er.� wn ee perm n rm.ne q,ne nT•... om.amem a nranmpwmrnle e•.adne µxn.w mmeueoe. rd owr �nsms. i. rwwd,rae.>.Aa wne. �eea�adeeea,.o,em. mpp e�,amm.n.,e,W..,.>r.«n.eeae.e py �..,p�er �swar.r.«.. a.y nn=n q,rrry.,>,..r..e eremeu.ream.em.er.e.�e.rp..w<n.ro.a lo-..m:e-wn 3. raenrey*alleanaeyr e..^N evlryawwa, e�iaa ml•�nrews*ar nsva,e�erar•S xr••vpwf�nemp ran. yeayp.appy .,,. a sr• a raN reern egsarompNem w,n. evow•,Mwrrnlexb.•q.wwN Ylerwn xAMn,.e grinrprnyan weroN7•ro•.rtlemaean xlreeavr. wama wn.. nN.q �e,Nrn,l�ran. m,n.rneeyo.;mrniw yr.�aaae.*+pr¢.w dap•�erb mam Weary in.rpy.ne.u.y.,e,.nu..1u[em.rrlg rnrnu w,xn.y.n nn m.Mn.-+=napm Nr..e rheln ypn malq.re•y,.m.,.urr.y�aer.tlenexyi.re nrw.w¢.pnn.enre rre�un.. paced � Pp.w.amal,K o•nr,... a�.*o"y nxn.ee«e � �paxp awn awr., m w a,. reel a u. ea n wnrsy w x •rdn•rv.e. s. m.mr.�,ew...,e,o<,«nerer•m•w.«e,w��.m. mw. w..,e..mn rwpam �nwr:+r«m.x..nae.,,nm:vex,�....ea,el.p.rrdmn.C.m,dn,�n.,,.�•. men �.e..•,r.rc..arr.e,.,nyrww,.mnrr..reepr�nnn.. p�,l..ran�rmM, wKepexrk wtrr tan�q.�vma. m emw•e:ns •na•,Her tea x Ix•n q cnewMyu ve FM.^ snOp.ay x ine e�r�n's.•pnx vmw M r.0 arar•+mee n Ir•v^,^nr^^^^ •aa,eea m�� na+spnWq �n tM �aOr. ,M F.gOm w IM eva u arw ewrp wi av m wsor.^i rwmwear d.vrvne.emxmmer..•w�p lnkxvne [wruy,'mP, xdare a «e nemn m.wrwxerosn d «r i m,rmnw card w-pnnw •ala•wmvmn ewra. we wte•rgNd�n�e:^n:m�anatwee+.�erlrp Wnw•a••n••e npaan b.vrneeea-1elx�etwnon w.n.w•en ie ee�ex.ngpK twmyp. rre vp�..wa�arweyamm ve,wreMxw•nrseea re.ee <mrmnirtvo{�amrnr�wry•�y [plea Ae remnabama ofMeohd �Nwn,M1eO.nrer,soa. eamm Nxrrc [mr ennJa er wxeeMetl d.�aW� rm�n or JewHy.W 50 payr ahertlN ra[Yr•appn •rkhnvrpneo aM imprxetl xd uq•a�rtlyrM1e [worry nirV«er.iG bortl «oe,ar W � A, Ir�ae.nn]ae•0 tl,/eNya1N part] Ihndr.,nfO O! •HWMd 161Ae 6�M. d Ir1M Vyap,h nworahortwr.nilwwarpnbxy x,Nhe� 1M1n IGOdO muwereeL tlw. aspxlolwy pn+•A .edw.,wnl to xdml]SOIWtlnCad.tllWe+�W.tl'prup.m.MrrR.sM Mtyyo.ea pLn«anrrhra ror,rY. wYMT/14,selslks LY nsu•smnt. Ns.Oures] Iq nd w raiw:nd i, .e�m•I mXMW,9u�Cl araMpal[NmtMy..lAflmlAffSm,A3on NIMLaOtNaRImW Mae A:�aM1epCrl•y,rttp Nl•es:MpWtN MGrmNSMn Alr•16prdr.MDr+M.YNMKKY.id.RraM OrfhwJSHIM1�M/Wf /rJMtlh Wf,.]!d {ti vMKMsaSMDed ran naeromll sG m a PAkweat S. inf Odrpv.,ncp waOldrH Me v..aaynryapy lneriWaan[tlrN4atl N'We,.Merd YFM/a asNMddxNWidp•. j«.py+en6 d!ra aA�(r+apo4ifl�.5d4�.YM,r.p.PM1mM1l OriWu�i641tlerrtelase hr.WNM nfxb:gann mf llulNp•orin. eexxpmrl Or a4OIn.i PepeAei Vse POOnn auNaAemeyruim fAM9tle rn,hlaMlA[[e[[a^9•Nwmenls as eeemee reprodixe.uxT n]><nlxtnrxeedlrRrngOrNranh NSMia'x 30..F. YJiaM 1019o[M[Nppr 3. 9onow, cal d pa[ttwwHy xn]fA:rg nB.YnRnpe prvwe+ap.ipmw'[ fNC m LT.Me en mh MW. N TEO aan. w V00 p In. [.[.p n uuc M� piG[ e!ner[ercr�l.ree W'[uaneia u[oon LLON orN[ COG N NGr[•eee. •laatm.inw.wrn><e..�ryvun{ytenm�[wOaa ufenunnH2Onwwrn W.rye.Spp].nppmm�erenr..nrwneiepKwl, pryy{.v ean�ei>aggenru•q ae myperrymlaN Pm,.{.[OnypFl. Knnoets.yef.wp{.ywrQpt0e.0V. ]. Tn Wtvnn[OrMw nn:rvw xromgelw wr.•«nKa•d Wtwn�•rw-mn.2e•teprMn.unxeenan•arrra �•y Dore. enml�nnwc.eleewlnlh'...iuxnlalw�dlne.m.T*ep�am wenam mnext•alr�e wpdtv�pr[.n upon m.,nlar n9uede�[ne uCles'[ G•wn]lvafr�j inn Hann OeTa�re w [a[erN Drone apOium We•+ea[a w aaa[Sna] annN w wy+m perm. iM pieermmrewiry mq aen nsixd r.tt+mn ror a p1.de uu-..rt]� n m w. eaa.wi x exerenw w[m+u m+umprra in. xnrl , inwMa q..aw.wn.r'n YWe•n+nwmn�xtwlatwn.krwl Min•r+nrA.prwnle.wp.a Mern,w,edn.,.lpape,mwn,.wn•xw Mapxx•wep•ar.�tle.k.e uwwPWam asnrw��ryw�e�m,yxe�rr o•. et'rt•h+u,err,weall nan p•••wm e Menl,nerzl�•rrrnanls stl xneao Mtfu9Otrios E L1 �p,9851 wn ol.,ajL ,6]d5,ae m.laj� T-]GSI The VESCP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Process: After approval, plan will have to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will have to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will have to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. If any easements are required, then after easement plat is recorded, the County can hold a pre -construction conference. Applicants must complete the request for a pre -construction conference form, and pay the remainder of the application fee (if any). The form identifies the contractor and responsible land disturber, and fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; hLtp://www.albemarle.org/deptforms.asp?department--cdengmTo WP0202000026_Yancey Farm Pad 2051820