HomeMy WebLinkAboutWPO201909999-Full Inspection Report (4)orA1.4 Inspection Result: Compliant
TH
Ljk GI'.�ti�
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
HOLLYMEAD TOWN CENTER A-2
Project/WPO Number:
WP0201909999
TMP:
ctmp»
DEQ Permit Number (if
applicable):
VA76TEST
Project Operator:
Brian Sabin
Operator Telephone #:
Project Contact:
Brian Bada Bing Sabin
Contact Telephone #:
Contact E-Mail:
bsabin@mccinnovations.com
Qualified Personnel (QP):
Inspector:
Geoff Elsie
Weather (Wet/Dry/Rain):
Disturbed Acreage:
Inspection Date & Time:
6/3/2020
Single -Family:
Stage of Construction: Clearing
Re -Inspection: Yes
COVERAGE & POSTING REQUIREMENTS
Compliant?
Reviewed during re -inspection? Yes
Comments/Description
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
No
Nobsign
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
N/A
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
N/A
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? Yes
Comments/Description
4
The SWPPP is on -site or made available during the inspection? (CGP
N/A
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
NIA
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
N/A
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
N/A
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
The SWPPP includes a legible site plan identifying all appropriate
N/A
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
Page 1 of 4
9
The SWPPP contains the name, phone number and qualifications of
N/A
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
No
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
N/A
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ II.0 ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
N/A
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
N/A
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
N/A
K? (CGP Part 11 A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
N/A
11 A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Compliant?
Reviewed during inspection? Yes
Comments/Description
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
Yes
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
54.G)
Has the SWPPP been amended if inspections or investigations by the
17
operator's qualified personnel, or by local, state or federal officials find that
Yes
existing control measures are ineffective in minimizing pollutants in
discharges? (CGP Part II B(2))(9VAC25-870-54.G)
18
Contractor(s) that will implement and maintain each control measure are
Yes
identified? (CGP Part 11 B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
Yes
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part 11 B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
Yes
(CGP Part 11 B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
N/A
stabilization? (CGP Part 11 B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
legal control of the operator and the dates on which the operator no longer
N/A
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
54.G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
N/A
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part 11 B.4(e-f)) (9VAC25-870-54.G)
24
mendments, modifications, or updates to the SWPPP are signed in
N/A
accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Compliant?
Reviewed during inspection? Yes
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
N/A
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
26
Inspection reports are completed and signed in accordance with CGP
N/A
Part 11 F (3-4)? (CGP Part 11 F (3-4))
Page 2 of 4
27
Corrective actions are taken consistent with the requirements of the
N/A
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
28
Have stream buffers and steep slopes been protected as shown on the
Yes
plan?
Sequencing of the project is implemented in accordance with the
Yes
Fde
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
been stabilized, and have stabilization requirements for impaired waters,
30
approved TMDL(s), pollutants of concern and exceptional waters, when
N/A
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
N/A
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
N/A
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
N/A
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
N/A
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.6)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
N/A
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
N/A
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
N/A
38
(9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
N/A
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
No
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
Yes
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are temporary stream crossings of non -erodible material installed where
Yes
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
43
Is necessary restabilization of in -stream construction complete? (9VAC
Yes
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
N/A
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are soil and mud kept off paved or public roads to minimize the transport
N/A
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
46
Have all temporary control structures that are no longer needed been
N/A
removed and disturbed soil resulting from their removal permanently
Page 3 of 4
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
N/A
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
N/A
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
N/A
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
N/A
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
N/A
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
N/A
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
N/A
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
N/A
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
N/A
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
N/A
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Page 4 of 4
Construction General Permit Site Inspection Report
Request for Correction Action
Check
List #
Regulatory
Citation/Legal
Requirement*
Occur.
Observation
Recommended Corrective
Action
Recommended
Corrective Action
Deadline:
Targeted Re -
Inspection Date:
Comments:
`Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1- 4.2 et seq.), Virginia Erosion and
Sediment Control Regulations (9VAC25-840), the Virginia Stommvater Management Program (VSMP) Regulations(9VAC25-870), or the General Permit for
Discharges of Stormwater from Constructi on Activities (9VAC25-880).
Construction General Permit Site Inspection Photo Log
Photos for Item 2
Photos for Item 4
Fhoto Dzscription:
Photos for Item 10
56030HA-3546-41344-1301 B-2A9AA940A88B.jpg
t
Fhoto DBscription:
Desc
885.53KB
Photos for Item 29
IMG_0051.PNG 312.43KB
How to WARMUP for Valley[ X
E C jj https://m.yoLrtube.com/watch?v=pK35g3b_SGc * �8 IT) ,
How to WARMUP for Volleyball -Volleyball Tutorial
Elevate Yourself 2e,601 views
b 552 'I ) + A A
COMMENTS • 70
How to SEE the BLOCK-
Volleyball Tutorial
vare Yourself
Passing Angles - How to
PASS a Volleyball...
-,.vare Yourself
Upper Body Volleyball
Warmup-Volleyball...
Elevate Yourself
Jump Training FULL
wCRKOUT(11/19/16)
MMYvatevourself
1
Arm Swing Mechanics:
3Mo,lons(parl l/2)-,..
gate Your
USA manes volleyball
team warm up WL2015
6ByIICM1ev
How to Jump Serves
Volleyball -Tutorial
vHlms
How to PANCAKE the
, Volleyball Tutorial
vare Yourself
BACK Set -How to SET
Volleyball Tutorial(par...
vare Yourself
Passing Jump Serves
eMy Light Jump Training�y_
_ 4 Si, Skills of Volleyball
Photo Description: Trree
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Inspection Date: 6/3/2020
County Inspector
Charlottesville, Virginia 22902
434 296-5832