HomeMy WebLinkAboutWPO202000015 Plan - VSMP 2020-06-08LEGEND
EXISTING
1►10Mh
1
X
5or�
X
T I I= T
a�w
11
X
508W
lII B
11
x
-X
X -
-0-
-0-
0
0
- OHU
OHU
- UGU
U G U
00
00
q
q
00 00
S S
W
W
00
0
0
�
A
A
GAS GAS
DESCRIPTION
btNUNIVIAKK
SITE PROPERTY LINE
ADJACENT PROPERTY LINE
BUILDING SETBACK
PARKING SETBACK
SITE TEXT
PARKING COUNT
TOPOGRAPHY
INDEX CONTOUR
INTERVAL CONTOUR
SPOT ELEVATION
TOP OF CURB ELEVATION
TOP OF WALL ELEVATION
BOTTOM OF WALL ELEVATION
STREAM
STREAM BUFFER
100 YEAR FLOODPLAIN
BUILDING
BUILDING
RETAINING WALL
STAIRS
EDGE OF PAVEMENT
ROAD CENTERLINE
FRONT OF CURB
BACK OF CURB
CG-12 TRUNCATED DOME
SIDEWALK
BIKE PARKING
HANDICAP ACCESSIBLE AISLE
HANDICAP PARKING
I.UINUKt I It
RIPRAP
ASPHALT
EC-2 MATTING
EC-3 MATTING
WETLAND
TREELINE
FENCE
UTILITY POLE
GUY WIRE
OVERHEAD UTILITY
UNDERGROUND UTILITY
STORM MANHOLE
DROP INLET
STORM SEWER
ROOF DRAIN
SANITARY MANHOLE
SANITARY SEWER MAIN
SANITARY SEWER LATERAL
WATER LINE
WATER METER
WATER METER VAULT
FIRE HYDRANT
FIRE DEPARTMENT CONNECTION
GAS
GAS LINE
CONSTRUCTION
GRADING
ACCESS
SIGHT DISTANCE
UTILITY
STORMWATER FACILITY MAINTENANCE
STORMWATER ACCESS
DRAINAGE
SANITARY
WATERLINE
GASLINE
GENERAL CONSTRUCTION NOTES
1. Prior to any construction within any existing right-of-way, including connection to any existing road, a permit shall be obtained
from the Virginia Department of Transit (VDOT). This plan as drawn may not accurately reflect the requirements of the
permit.Where any discrepancies occur the requirements of the permit shall govern.
2. All materials and construction methods shall conform to the current specifications and standards of VDOT unless otherwise
noted.
3. Erosion and siltation control measures shall be provided in accordance with the approved erosion control plan and shall be
installed prior to any clearing, grading or other construction.
4. All slopes and disturbed areas are to be fertilized, seeded and mulched.
5. The maximum allowable slope is 2:1 (horizontle:vertical). Where reasonably obtainable, lesser slopes of 3:1 or better are to be
acheived.
6. Paved, rip -rap or stabilization amt lined ditch may be required when in the opinion of the County Engineer or designee it is
deemed necessary in order to stabilize a drainage channel.
7. All traffic control signs shall conform with the Virginia Manual for Uniform Traffic Control Devices.
8. Unless othrewise noted all concrete pipe shall be reinforced concrete pipe - Class III.
9. All excavation for underground pipe installation must comply with OSHA Standards for the Construction Industry (29 CFR Part
1926).
GENERAL CONSTRUCTION NOTES FOR
EROSION AND SEDIMENT CONTROL PLANS
1. The plan approving authority must be notified one week prior to the pre -construction conference, one week prior to the
commencement of land disturbing activity, and one week prior to the final inspection.
2. All erosion and sediment control measures will be constructed and maintained according to minimum standards and
specifications of the Virginia Erosion and Sediment Control Handbook and Virginia Regulations VR 625-02-00 Erosion and
Sediment Control Regulations.
3. All erosion and sediment control measures are to be placed prior to or as the first step in clearing.
4. A copy of the approved erosion and sediment control plan shall be maintained on the site at all times.
5. Prior to commencing land disturbing activities in areas other than indicated on these plans (including, but not limited to,
off -site borrow or waste areas), the contractor shall submit a supplementary erosion control plan to the owner for review and
approval by the plan approving authority.
6. The contractor is responsible for installation of any additional erosion control measures necessary to prevent erosion and
sedimentation as determined by the plan approving authority.
7. All disturbed areas are to drain to approved sediment control measures at all times during land disturbing activities and
during site development until final stabilization is achieved.
8. During dewatering operations, water will be pumped into an approved filtering device.
9. The contractor shall inspect all erosion control measures periodically and after each runoff producing rainfall event. Any
necessary repairs or cleanup to maintain the effectiveness of the erosion control devices shall be made immediately.
10. All fill material to be taken from an approved, designated borrow area.
11. All waste materials shall be taken to an approved waste area. Earth fill shall be inert materials only, free of roots, stumps,
wood, rubbish, and other debris.
12. Borrow or waste areas are to be reclaimed within 7 days of completion per Zoning Ordinance section 5.1.28.
13. All inert materials shall be transported in compliance with section 13-301 of the Code of Albemarle.
14. Borrow, fill or waste activity involving industrial -type power equipment shall be limited to the hours of 7:00am to 9:00pm.
15. Borrow, fill or waste activity shall be conducted in a safe manner that maintains lateral support, or order to minimize any
hazard to persons, physical damage to adjacent land and improvements, and damage to any public street because o slides,
sinking, or collapse.
16. The developer shall reserve the right to install, maintain, remove or convert to permanent stormwater management facilities
where applicable all erosion control measures required by this plan regardless of the sale of any lot, unit, building or other
portion of the property.
17. Temporary stabilization shall be temporary seeding and mulching. Seeding is to be at 75 Ibs/acre, and in the months of
September to February to consist a 50/50 mix of Annual Ryegrass and Cereal Winter Rye, or in March and April to consist of
Annual Rye, or May through August to consist of German Millet. Straw mulch is to be applied at 80lbs/100sf. Alternatives are
subject to approved by the County erosion control inspector.
18. Permanent stabilization shall be lime and fertilizer, permanent seeding, and mulch. Agricultural grade limestone shall be
applied at 90lbs/1000sf, incorporated into the top 4-6 inches of soil. Fertilizer shall be applied at 1000lbs/acre and consist of a
10-20-10 nutrient mix. Permanent seeding shall be applied at 180lbs/acre and consist of 95% Kentucky 31 or Tall Fescue and
0-5% Perennial Ryegrass or Kentucky Bluegrass. Straw mulch is to be applied at 80lbs/100sf. Alternatives are subject to
approved by the County erosion control inspector.
19. Maintenance: All measures are to be inspected weekly and after each rainfall. Any damage or clogging to structural
measures is to be repaired immediately. Silt traps are to be cleaned when 50% of the wet storage volume is filled with
sediment. All seeded areas are to be reseeded when necessary to achieve a good stand of grass. Silt fence and diversion
dykes which are collecting sediment to half their height must be cleaned and repaired immediately.
20. All temporary erosion and sediment control measures are to be removed within 30 days of final site stabilization, when
measures are no longer needed, subject to approval by the County erosion control inspector.
21. This plan shall be void if the owner does not obtain a permit within 1 year of the date of approval. (Water Protection
Ordinance section 17-204G.)
22. Permanent vegetation shall be installed on all denuded areas within nine (9) months after the date the land disturbing
activity commenced. (Water Protection Ordinance section 17-207B)
GENERAL NOTES
1. The information and data shown or indicated with respect to the existing underground utilities at or contiguous to the site are
based on information and data furnished to the owner and engineer by the owners of such underground facilities or others.
The owner or engineer shall not be responsible for the accuracy or completeness of such information or data. The contractor
shall have full responsibility for confirming the accuracy of the data, for locating all underground utilities, for coordination of the
work with owners of such underground utilities during construction, for the safety and protection thereof and repairing any
damage thereto resulting from the work. All of these conditions shall be met at no additional cost to the owner. The contractor
shall contact "Miss Utilities" of Virginia at 1-800-552-7001 prior to the start of work.
2. When working adjacent to existing structures, poles, etc., the contractor shall use whatever methods that are necessary to
protect structures from damage. Replacement of damaged structures shall be at the contractor's expense.
3. The contractor shall be responsible for protecting all existing site structures from damage and coordinating work so that the
owner can make necessary arrangements to modify/protect existing structures from damages.
4. The contractor shall be responsible for notifying all utility owners, adjacent land owners whose property may be impacted and
the Virginia Department of Transportation prior to completing any off -site work.
5. Contractor shall notify and coordinate all work involving existing utilities with utility owners, at least 72 hours prior to the start
of construction.
6. Contractor shall immediately report any discrepancies between existing conditions and contract documents to the owner and
engineer.
7. Contractor shall submit for the approval of the owner submittals of all specified materials listed in the plans, to include shop
drawings, manufacturer's specifications and laboratory reports. the owner's approval of submittals will be general and will not
relieve the the contractor from the responsibility of adherence to the contract and for any error that may exist.
8. All bare areas shall be scarified, limed, fertilized, seeded and mulched.
9. All trees, saplings, brush, etc. shall be removed from within the right of way and the drainage easements.
10. Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated.
11. Retaining walls require separate building permits.
12. All water service lines, sanitary laterals, and sprinkler lines must be visually inspected by the Albemarle County Building
Department from the main to the structure.
PERRY RESI
OWNER/DEVELOPER
OWNER (TMP 51 - 24C):
ROBERT PERRY
(732)591-5116
7850 GORDONSVILLE ROAD
CHARLOTTESVILLE, VA, 22942
LAT: 38.117669
LONG:-78.228026
BUILDER:
CAILEN VON BRIESEN & CAL BARCLAY
(434)296-8722
ZONING
(RA): RURAL AREA
MAGISTERIAL DISTRICT
RIVANNA DISTRICT
SOURCE OF TITLE
PARCEL 51 -24C (52.24 ACRES TOTAL)
DB 5084 P 249
SOURCE OF DATUM
NAVD 1988
SOURCE OF BOUNDARY AND TOPOGRAPHY
BOUNDARY SURVEY INFORMATION PROVIDED BY:
RESIDENTIAL SURVEYING SERVICES
1710 ALLIED STEET, SUITE 20A
CHARLOTTESVILLE, VA, 22903
TOPOGRAPHIC SURVEY PROVIDED BY:
RESIDENTIAL SURVEING SERVICES ON JANUARY 29, 2019
1710 ALLIED STEET, SUIT 20A
CHARLOTTESVILLE, VA, 22903
EXISTING USE:
VACANT RESIDENTIAL LAND
PROPOSED USE:
SINGLE FAMILY HOME
BENCHMARK
EAST SIDE OF PROPERTY
ELEV 486.88
RESERVOIR WATERSHED
THIS SITE IS WITHIN THE SOUTH ANNA RIVER - DOVE FORK WATERSHED.
FLOODZONE
FEMA FLOOD INSURANCE RATE MAP (COMMUNITY PANEL 51003C0350D), EFFECTIVE DATE FEBRUARY 04, 2005
SHOWS THIS PROPERTY WITHIN ZONE "X" AND NO PORTION OF THE PROPERTY WITHIN THE 100-YEAR FLOOD
PLAIN.
LAND USE SCHEDULE
EXISTING AREA AC %
BUILDING 0 SF 0.0 0.0 %
PAVEMENT 0 SF 0.0 0.0 %
SIDEWALKS/ CONCRETE 0 SF 0.0 0.0 %
IMPERVIOUS AREA 0 SF 0.0 0.0 %
TURF 156000 SF 3.58 100.0 %
WOODS 0 SF 0.0 0.0 %
TOTAL=
156000 SF
3.58
100 %
PROPOSED
AREA
AC
%
PAVEMENT
7069 SF
0.16
4.5 %
BUILDING
6539 SF
0.15
4.2 %
SIDEWALKS/ CONCRETE
10638 SF
0.24
6.8 %
IMPERVIOUS AREA
24246 SF
0.56
15.5 %
TURF
131754 SF
3.02
84.5%
WOODS
0 SF
0.00
0.0 %
TOTAL= 156000 SF 3.58 100.0 %
TOTAL DISTURBANCE = 3.58 ACRES
STEEP SLOPES
NEITHER PRESERVED SLOPES NOR MANAGED SLOPES ARE PRESENT
ON THIS PROPERTY.
VSMP PLAN FOR
DENCE
TAX MAP 51, PARCEL 24C
ALBEMARLE COUNTY, VIRGINIA
VICINITY MAP SCALE: 1°=1000'
Eat)
�.4,
941
PERRY
RESIDENCE. '
Gem
i
SITE Lovisa
. Z31
Map provided by Google.com
SHEET INDEX
C1 COVER SHEET
C2 EXISTING CONDITIONS
C3 GRADING & UTILITY PLAN
C4 SWM DETAILS
C5 VRRM MAP
C6 EROSION CONTROL NARRATIVE
C7 EROSION CONTROL PLAN
C8 SITE DETAILS
SHIMP
ENGINEERING2
LAND PLANNING - PROJECT MANAGEMENT
912 E. HIGH ST. 434.227.5140
CHARLOTTESVILLE VA, 22902 JUSTIN@SHIMP-ENGINEERING.COM
LIfs
D7�1\I U i 1/
Lic. l� 183
6w
�
'SIONAL
VSMP PLAN
PERRY
RESIDENCE
ALBEMARLE COUNTY, VIRGINIA
SUBMISSION:
2020.02.28
REVISION:
1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
FILE NO.
COVER
19.024
SHEET C1 of C8
C1
I
I
I
I
-N7-48' 14„W
2934. 73,
W
z
Y00
Q��
Qco
� d-
2
Z
W W
s
zQ
1= w
_cam
X �
W Cf)
--------------------
x
o00
w w o
/- - - - - - - -
LLJ
'/'' W 460
-470- X
--------''-
-------------------' \
,'
/'
---
_ Q \ \ \ \ r
-
/
O
SHIMP
ENGINEERING
LAND PLANNING - PROJECT MANAGEMENT
912 E. HIGH ST.
CHARLOTTESVILLE VA, 22902
---- I
\
---------------
/ \\\\\\\ \\\\\\\ \\\ \\ \ \ \\ \\\ \\\ \ \\\ \`---_-----'--_'
\II
_ ----
/
-------------
----------------
I \
/
/ \\\ \- - - - - - - - - - - - - - - - - - - - - - - -
\
- - - - - - - - - - - - - - - - - - - - - - -
I
--
LLJ
WLLJ
O
W Q::� l'
/
N33056'00"W 2562.00'
434.227.5140
JUSTIN@SHIMP-ENGINEERING.COM
�q
S IMP
Lic. 183
4�
��SSJONAL ��G
VSMP PLAN
PERRY
RESIDENCE
ALBEMARLE COUNTY, VIRGINIA
SUBMISSION:
2020.02.28
REVISION:
1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
FILE NO.
19.024
EXISTING CONDITIONS
50 ! 0 50 100 150
Scale: 1 "=50'
SHEET C2 of C8
C2
. -N7'48' 14„W
2934- 731
0"5;
zQ
W
_C/)�
X �
W
w
\ \ Z LLJ
LLJ
W
z
— ---- \ - .
"-----------
LLJ /— — — — — — — — — —
LLJ
I , I
/
_
Li
-------------
---__
\
1
O
.
I o
\ \ \ \ \ \
\\\ \
\ \ \ \
\\ \\ \\ \ / w
Z w
ME
\ \
\ /Lj
CD
\
boar
I /
T
co
/ V v v v A �- A
y
I
\ O `v ao v v c0 ` CV
00
00\
�
I I I
� � � _ f- -,
`�
A
z Q
�v M vZ vv ---tzi
Imo_ w
v
_
UPON
w
0]
V v v A vv
vTNUJ
Ir
W \\ \\ \ \\ LEVEL SPREADER #2
\ J
\\ \\ \\
- - - - - - - - -
/ / \\ \ yq�
DITCH 3
I
_
o
\------------- ---
\
/ \
\
---
1
,-
_--- _
--- LLJ
N33056'00"W
2562.00'
L-J o' ;
w '0 '
L J
I�
,
SHIM
ENGINEERING
LAND PLANNING - PROJECT MANAGEMENT
912 E. HIGH ST. 434.227.5140
CHARLOTTESVILLE VA, 22902 JUSTIN@SHIMP-ENGINEERING.COM
Ali 70V%U.w:
Lic. 183
w
��SS�ONAL
VSMP PLAN
PERRY
RESIDENCE
ALBEMARLE COUNTY, VIRGINIA
SUBMISSION:
2020.02.28
REVISION:
1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
FILE NO.
19.024
GRADING & UTILITY PLAN
20 0 20 40 60
Scale: 1 "=20'
SHEET C3 of C8
C3
Level Spreader Design Table
Level
Spreader
Drainage
Area (ac)
10-yr Flow
WS)
Depth
Length
1
5.50
11.72
0.6'
36'
2
3.45
7.05
0.6'
55'
LEVEL SPREADER 1
C4 Scale: 1" : 10'
CROSS SECTION
VDOT #3, #357, #5, #56 OR
#57 COARSE AGGREGATE IN 7' LENGTH
GALVANIZED WIRE MESH BASKET ---SECURE WIRE MESH TO TIMBER
* FILTER CLOTH / I / /-- 6X6 TREATED TIMBER
SECURE WIRE TO GROUND II
WITH WIRE STAPLES #5 REBAR TO -
SECURREETIMBER 6" MIN. - I
1= _ I�IIIIII
T MIN. 3' =1 I I -III -I � II � I -III -III -III -III -I � I -1I I -I � I -_I
UNDISTURBED III -I I-1 1-1 1-1 1=III=III=1 l 1 -1 1I
SOIL llu IIulll-III=III i1 = -III-III-1,- 2:1 OR
FLATTER
MIN. 6-
LEVEL SPREADER WITH RIGID LIP
* MIN. PHYSICAL REQUIREMENTS OF FILTER CLOTH NOTED IN STD. & SPEC. 3.19, RIPRAP
SOURCE: VA. DSWC AND N.C. Eamon and Sediment Control Planning and Design Manual PLATE: 3.21-2
3 LEVEL SPREADER DETAILS
�4Not To Scale
DITCH 3 0
o
20
EC - 2 MATTING
VDOT #3 STONE
4 9 0_
720
f CONCRETE
LIP
55.0'
LEVEL SPREADER # 2
-48 --- `� --�- - ----
--- - ------- ------ - )6-
2 LEVEL SPREADER 2
C4 Scale: 1" : 10'
Outlet Protection Details
Culmert
Area (ac)
Flow (cfs)
Dia. (in)
Do (ft)
3Do (ft)
La (ft)
W (ft)
1
2.82
4.05
15
1.25
3.75
9
10.25
2
4.66
8.16
15
1.25
3.75
10
11.25
DITCH SECTION
SECTION
LINING
CHANNEL
CHANNEL
CHANNEL
2-Yr
10-Yr
SCC 1
EC-2
1.5
6
2.1
3.62
0.94
SCC 2
EC-3
1.5
6
2.1
4.07
1.01
SCC 3
EC-2
1.0
6
1 2.1
3.87
0.87
SCC 4 EX
EC-2
2.0
6
1 2.1
3.39
0.99
- Width -I
4 DITCH SECTION DETAIL
C4 Not To Scale
h
HIM
ENGINEERING2
LAND PLANNING - PROJECT MANAGEMENT
912 E. HIGH ST. 434.227.5140
CHARLOTTESVILLE VA, 22902 JUSTIN@SHIMP-ENGINEERING.COM
Lic. 183
A �11b �
� V �V
O ��
SSIONAL le
VSMP PLAN
PERRY
RESIDENCE
ALBEMARLE COUNTY, VIRGINIA
SUBMISSION:
2020.02.28
REVISION:
1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
FILE NO.
SWM DETAILS
19.024
SHEET C4 of C8
X,
II
II
III
II
II
III
II
III
III
1
III
I
1
III
I
lim
IEERIN ]2
PROJECT MANAGEMENT
434.227.5140
2902 JUSTIN@SHIMP-ENGINEERING.COM
M. S IMP
Lic. &183
w
vk'SIONAL ti�G
f
,ENCE
COUNTY, VIRGINIA
8
;ounty Comments
County Comments
BUSH HOGGING TO MAINTAIN DESIRED VEGETATIVE COMMUNITY 19.024
(BUT NO MORE THAN FOUR TIMES A YEAR)."
� VRRM MAP
i
100 0 100 200 300
Scale: 1 "=100'
SHEET C5 of C8
C 5
PROJECT DESCRIPTION, GENERAL NOTES, EROSION & SEDIMENT CONTROL NOTES, AND SEQUENCE OF CONSTRUCTION
PROJECT DESCRIPTION
THE PURPOSE OF THIS PROJECT IS TO BUILD A RESIDENTIAL HOUSE.
THE TOTAL AREA OF DISTURBANCE IS 3.58 ACRES.
THE PROJECT INVOLVES THE FOLLOWING WORK ACTIVITIES:
1. THE CONTRACTOR SHALL OBTAIN ALL LOCAL AND STATE EROSION AND
SEDIMENT PERMITTING REQUIREMENTS AND MAINTAIN ALL EROSION AND
SEDIMENT CONTROLS IN ACCORDANCE WITH THE PERMIT REQUIREMENTS.
2. INSTALLATION OF TEMPORARY AND PERMANENT EROSION AND SEDIMENT
CONTROL MEASURES AS SHOWN ON THE PLAN AND DETAILS.
3. GRADING AND PLACEMENT OF FILL SHALL BE IN GENERAL ACCORDANCE
WITH THE PLAN.
4. ESTABLISHMENT OF PERMANENT STABILIZATION OF ALL DISTURBED AREAS..
5. CONSTRUCTION OF ROAD, PARKING LOT, AND BUILDING PAD AS SHOWN ON
THE SITE PLAN.
6. CONSTRUCTION OF PERMANENT DITCH AND CULVERT.
EXISTING SITE CONDITIONS
THE SITE IS CURRENTLY A VACANT WOODED LOT WITH TWO EXISTING
STREAMS RUNNING THROUGH THE PROPERTY.
ADJACENT PROPERTIES
THIS PROPERTY IS BORDERED TO THE NORTH BY VACANT LAND WHICH HAS
SOME GRASS; TO THE EAST BY OTHER PROPERTY WITH VACANT WOODS
(TREES) LOT; TO THE SOUTH BY A DRIVE WAY STATE ROUTE 231 ( 50'
R/W) AND A RESIDENTIAL HOME; TO THE NORTH-WEST BY WOODS (TREES),
WHILE ON THE SOUTH WEST IS BORDERED BY GRASS.
OFF -SITE AREAS
THERE ARE NO OFFSITE ACTIVITIES.
Yill1W
THIS SITE CONTAINS THE FOLLOWING SOIL TYPES BASED ON NRCS SOIL MAPS
FOR ALBEMARLE COUNTY VIRGINIA:
12C - CATOCTIN SILT LOAM, 7 TO 15 PERCENT SLOPES. HSG: B
19C - MINNIEVILLE LOAM, 7 TO 15 PERCENT SLOPES. HSG: B
23B - YADKIN CLAY LOAM, 2 TO 7 PERCENT SLOPES. HSG: B
23C - YADKIN CLAY LOAM, 2 TO 15 PERCENT SLOPES. HSG: B
25B - DYKE SILT LOAM, 2 TO 7 PORCENT SLOPES. HSG: B
51C - BUGLEY CHANNERY SILT LOAM, 7 TO 15 PERCENT SLOPES. HSG: D
57B - MOUNT LUCAS SILT LOAM, 2 TO 7 PERCENT SLOPES, HSG: D
62B - BUFFSTAT SILT LOAM, 2 TO 7 PERCENT SLOPES, HSG: B
72133- RABUN CLAY, 2 TO 7 PERCENT SLOPES, SEVERELY ERODED, HSG: B
72C3- RABUN CLAY, 7 TO 15 PORCENT SLOPES, SEVERELY ERODED, HSG: B
CRITICAL EROSION AREAS
THE EXISTING STREAM IS A CRITICAL EROSION AREA.
EROSION & SEDIMENT CONTROL NOTES:
1. ALL VEGETATIVE AND STRUCTURAL EROSION & SEDIMENT
CONTROL (E&S) PRACTICES WILL BE CONSTRUCTED AND
MAINTAINED IN ACCORDANCE WITH THE MINIMUM SPECIFICATIONS
OF THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK
AND VIRGINIA REGULATION 9VAC25-840-40.
2. THE PLAN APPROVING AUTHORITY MUST BE NOTIFIED ONE WEEK
PRIOR TO THE PRE -CONSTRUCTION CONFERENCE, ONE WEEK
PRIOR TO COMMENCEMENT OF LAND DISTURBING ACTIVITY AND
ONE WEEK PRIOR TO FINAL INSPECTION. THIS REQUIREMENT CAN
BE WAIVED AT THE DISCRETION OF THE PLAN APPROVING
AUTHORITY.
3. ALL EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE
PLACED PRIOR TO OR AS THE FIRST STEP IN CLEARING.
4. A COPY OF THE APPROVED EROSION AND SEDIMENT CONTROL
PLAN SHALL BE MAINTAINED ONSITE AT ALL TIMES.
5. PRIOR TO COMMENCING LAND DISTURBING ACTIVITIES IN AREAS
OTHER THAN INDICATED ON THESE PLANS (INCLUDING BUT NOT
LIMITED TO, OF -SITE BORROW OR WASTE AREAS), THE
CONTRACTOR SHALL SUBMIT A SUPPLEMENTRY EROSION AND
SEDIMENT CONTROL PLAN TO THE OWNER FOR REVIEW AND
APPROVAL BY THE PLAN REVIEWING AUTHORTY.
6. THE CONTRACTOR IS RESPONSIBLE FOR INSTALLATION OF ANY
ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES
NECESSARY TO PREVENT EROSION AND SEDIMENTATION AS
DETERMINED BY THE PLAN REVIEWING AUTHORITY.
7. ALL DISTURBED AREAS ARE TO DRAIN TO APPROVED SEDIMENT
CONTROL MEASURES AT ALL TIMES DURING LAND DISTURBING
ACTIVIES AND DURING SITE DEVELOPMENT UNTIL FINAL
STABALIZATION IS ACHEIVED.
8. DURING DEWATERING OPERATIONS, WATER WILL BE PUMPED INTO
AN APPROVED FILTERING DEVICE.
9. THE CONTRACTOR SHALL INSPECT ALL EROSION CONTROL
MEASURES PERIODICALY AND AFTER EACH RUN-OFF PRODUCING
STORM EVENT. ANY NECESSARY REPARIS OR CLEANUP TO
MAINTAIN THE EFFECTIVENESS OF THE EROSION CONTROL DEVICES
SHALL BE MADE IMMEDIATELY.
10. INSTALL AND MAINTAIN CONSTRUCTION ENTRANCES FOR ENTIRE
PROJECT AT ALL LOCATIONS WHERE VEHICLES ENTER/LEAVE THE
WORK AREA AND WHERE SOIL IS STOCKPILED.
11. MAINTAIN ALL EROSION AND SEDIMENT CONTROL UNTIL THE
COMPLETION OF FINAL STABILIZATION. UNLESS OTHERWISE NOTED
ON THE PLANS REMOVE ALL EROSION & SEDIMENT CONTROLS
FOLLOWING THE ESTABLISHMENT OF A PERMANENT VEGETATIVE
COVER AND COMPLETION OF FINAL STABILIZATION.
EROSION & SEDIMENT CONTROL PERMITTING
1. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ALL LOCAL
AND STATE EROSION AND SEDIMENT CONTROL PERMITS AND
MAINTAINING ALL EROSION AND SEDIMENT CONTROLS IN
ACCORDANCE WITH THE PERMIT REQUIREMENTS.
EROSION & SEDIMENT CONTROLS
UNLESS OTHERWISE INDICATED, ALL EROSION AND SEDIMENT CONTROL PRACTICES
WILL BE CONSTRUCTED AND MAINTAINED ACCORDING TO THE MINIMUM
STANDARDS AND SPECIFICATIONS AS SET FORTH IN THE VIRGINIA EROSION AND
SEDIMENT CONTROL HANDBOOK, LATEST EDITION. THE MINIMUM STANDARDS OF
THE VIRGINIA EROSION AND SEDIMENT CONTROL REGULATIONS SHALL BE
ADHERED TO UNLESS OTHERWISE WAIVED OR APPROVED BY VARIANCE.
TEMPORARY CONSTRUCTION ENTRANCE (CE) - 3.02
AN ASPHALT PAD WILL BE CONSTRUCTED AT THE ENTRANCE THE SITE TO
PROVIDE A MEANS OF REMOVING SEDIMENT FROM THE TIRES OF
CONSTRUCTION VEHICLES LEAVING THE WORK SITE. THE CONTRACTOR SHALL
REMOVE ANY MUD FROM THE EXISTING ROAD SURFACE BY MEANS OF
SWEEPING AND SHOVELING.
SILT FENCE (SF) - 3.05
SILT FENCING WILL BE INSTALLED AS A FIRST STEP IN CONSTRUCTION
ACTIVITIES. LOCATION AND DETAILS ARE SHOWN ON THE PLANS.
INLET PROTECTION (IP) - 3.07
INLET PROTECTION MEASURES AROUND THE NEW INLETS SHALL BE
PROVIDED IN ACCORDANCE WITH STD. AND SPEC 3.07. SILT FENCE OR
TEMPORARY STONE APPLICATIONS SHALL BE APPLIED AS APPROPRIATE FOR
CURRENT GRADE CONDITIONS.
OUTLET PROTECTION (OP) -3.18
THE INSTALLATION OF RIPRAP CHANNEL SECTIONS AND/OR STILLING BASINS
BELOW STORM DRAIN OUTLETS TO REDUCE EROSION AND UNDER -CUTTING
FROM SCOURING AT OUTLETS AND TO REDUCE FLOW VELOCITIES BEFORE
STORMWATER ENTERS RECEIVING CHANNELS BELOW THESE OUTLETS.
ROCK CHECK DAMS (CD) -3.20
SMALL, TEMPORARY STONE DAMS CONSTRUCTED ACROSS A DRAINAGE DITCH
TO REDUCE THE VELOCITY OF CONCENTRATED FLOWS, REDUCING EROSION OF
THE SWALE OR DITCH. LIMITED TO USE IN SMALL OPEN CHANNELS WHICH
DRAIN 10 ACRES OR LESS, SHOULD NOT BE USED IN LIVE STREAMS. STD.
AND SPEC. 3.20
PERMANENT STABILIZATION
TEMPORARY SEEDING (TS) - 3.31
TEMPORARY SEEDING SHALL BE APPLIED TO ALL DENUDED AREAS WITHIN
SEVEN (7) DAYS TO DENUDED AREAS THAT MAY OR MAY NOT BE AT FINAL
GRADE BUT WILL REMAIN DORMANT (UNDISTURBED) FOR LONGER THAN 14
DAYS, TEMPORARY SEEDING SHALL BE APPLIED IN CONFORMANCE WITH STD.
AND SPEC. 3.31.
PERMANENT SEEDING (PS) - 3.32
ALL DITCHES AND ADJACENT AREAS WITHIN 15 FT OF THE EDGE OF THE
DITCHES SHALL BE SEEDED IN CONFORMANCE WITH STD. AND SPEC. 3.32.
PERMANENT SEEDING SHALL BE APPLIED TO AREAS DELINEATED ON THESE
PLANS WITHIN SEVEN (7) DAYS AFTER FINAL GRADE IS REACHED ON ANY
PORTION OF THE SITE. PERMANENT SEEDING STABILIZES DISTURBED AREAS
AND ENHANCES THE BEAUTY OF THE SITE.
MULCHING (MU) - 3.35
APPLICATION OF PLANT RESIDUES OR OTHER SUITABLE MATERIALS TO THE
SOIL SURFACE TO PREVENT EROSION AND FOSTER THE GROWTH OF
VEGETATION. ORGANIC MULCHES (STRAW) HAVE BEEN FOUND TO BE THE
MOST EFFECTIVE.
STORMWATER MANAGEMENT:
STORMWATER QUANTITY IS MANAGED ON SITE THROUGH THE UTILIZATION OF
SHEETFLOW WHERE POSSIBLE & BY PROVIDING (2) TWO LEVEL SPREADERS WHICH
WILL ALLOW CONCENTRATED FLOW TO LEAVE THE SITE IN SHEETFLOW
CONDITIONS. DOWNSTREAM PROPERTIES HAVE BEEN EVALUATED FOR POTENTIAL
IMPACTS FROM INCREASED SHEETFLOW VOLUME AND IT WAS DETERMINED THAT
THE MINOR INCREASE IN SHEET FLOW WILL NOT CAUSE EROSION OF
DOWNSTREAM CHANNELS OR FLOODING.
STORMWATER QUALITY FOR THIS SITE IS MANAGED THROUGH THE DEDICATION OF
3.28 ACRES OF FOREST/OPEN SPACE
PERMANENT SEEDING SPECIFICATIONS
February 16 through April 30:
Kentucky 31 Fescue - 128 lbs/acre;
Red Top
Grass - 2 lbs/acre;
Annual Rye - 20 lbs/acre. Add 20
lbs/acre
Indian grass when slopes
are greater than 3:1.
May 1 through August 15:
Kentucky 31 Fescue - 128 lbs/acre;
Red Top
Grass - 2 lbs/acre;
Foxtail Millet - 20 lbs/acre. Add 20 lbs/acre Indian grass when
slopes are greater than 3:1.
August 16 through October 31:
Kentucky 31 Fescue - 128 lbs/acre;
Red Top
Grass - 2 lbs/acre;
Annual Rye - 20 lbs/acre. Add 20
lbs/acre
Indian grass on slopes
greater than 3:1.
November 1 through February 15:
Kentucky 31 Fescue - 128 lbs/acre; Red Top Grass - 2 lbs/acre; Winter
Rye - 20 lbs/acre. Add 20 lbs/acre Indian grass on slopes greater
than 3: 1.
MULCHING SPECIFICATIONS:
Straw or hay at a rate of 2 tons/acre. Must be anchored. Spread with
mulch blower or by hand.
LIME AND FERTILIZER SPECIFICATIONS:
Lime and fertilizer needs should be determined by soil tests. Soil tests
may be preformed by the Cooperative Extension Service Soil Testing
Laboratory at VPI&SU, or by a reputable commercial laboratory.
Information concerning the State Soil Testing Laboratory is available from
CITY Extension Agents. Under unusual conditions where it is not possible
to obtain a soil test, the following soil amendments will be applied:
For Permanent Seeding: Seeded areas shall be limed at a rate of 2 tons
per acre, and fertilized at a rate of 1,000 lbs. per acre of 10-20-10 (10
lbs. per 1,000 square feet) or equivalent.
For Temporary Seeding: Seeded areas shall be limed at a rate of 2 tons
per acre, and fertilized at a rate of 600 lbs. per acre of 10-20-10 (10
lbs. per 1,000 square feet) or equivalent.
GENERAL NOTES
1. THE INFORMATION AND DATA SHOWN OR INDICATED WITH RESPECT TO THE
EXISTING UNDERGROUND UTILITIES AT OR CONTIGUOUS TO THE SITE ARE
BASED ON INFORMATION AND DATA FURNISHED TO THE OWNER AND
ENGINEER BY THE OWNERS OF SUCH UNDERGROUND FACILITIES OR OTHERS.
THE OWNER OR ENGINEER SHALL NOT BE RESPONSIBLE FOR THE
ACCURACY OR COMPLETENESS OF SUCH INFORMATION OR DATA. THE
CONTRACTOR SHALL HAVE FULL RESPONSIBILITY FOR CONFIRMING THE
ACCURACY OF THE DATA, FOR LOCATING ALL UNDERGROUND UTILITIES, FOR
COORDINATION OF THE WORK WITH OWNERS OF SUCH UNDERGROUND
UTILITIES DURING CONSTRUCTION, FOR THE SAFETY AND PROTECTION
THEREOF AND REPAIRING ANY DAMAGE THERETO RESULTING FROM THE
WORK. ALL OF THESE CONDITIONS SHALL BE MET AT NO ADDITIONAL
COST TO THE OWNER. THE CONTRACTOR SHALL CONTACT "MISS UTILITIES"
OF VIRGINIA AT 1-800-552-7001 PRIOR TO THE START OF WORK.
2. WHEN WORKING ADJACENT TO EXISTING STRUCTURES, POLES, ETC., THE
CONTRACTOR SHALL USE WHATEVER METHODS THAT ARE NECESSARY TO
PROTECT STRUCTURES FROM DAMAGE. REPLACEMENT OF DAMAGED
STRUCTURES SHALL BE AT THE CONTRACTOR'S EXPENSE.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ALL EXISTING
SITE STRUCTURES FROM DAMAGE AND COORDINATING WORK SO THAT THE
OWNER CAN MAKE NECESSARY ARRANGEMENTS TO MODIFY/PROTECT
EXISTING STRUCTURES FROM DAMAGES.
4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFYING ALL UTILITY
OWNERS, ADJACENT LAND OWNERS WHOSE PROPERTY MAY BE IMPACTED AND
THE VIRGINIA DEPARTMENT OF TRANSPORTATION PRIOR TO COMPLETING ANY
OFF -SITE WORK.
5. CONTRACTOR SHALL NOTIFY AND COORDINATE ALL WORK INVOLVING
EXISTING UTILITIES WITH UTILITY OWNERS, AT LEAST 72 HOURS PRIOR TO THE
START OF CONSTRUCTION.
6. CONTRACTOR SHALL IMMEDIATELY REPORT ANY DISCREPANCIES BETWEEN
EXISTING CONDITIONS AND CONTRACT DOCUMENTS TO THE OWNER AND
ENGINEER.
8. CONTRACTOR SHALL ADJUST ALL APPURTENANCES AS REQUIRED TO
MATCH NEW GRADES. THE EXACT LOCATION OF APPURTENANCES SHALL BE
COORDINATED WITH THE OWNER.
9. CONTRACTOR SHALL SUBMIT FOR THE APPROVAL OF THE OWNER
SUBMITTALS OF ALL SPECIFIED MATERIALS LISTED IN THE PLANS, TO
INCLUDE SHOP DRAWINGS, MANUFACTURER'S SPECIFICATIONS AND
LABORATORY REPORTS. THE OWNER'S APPROVAL OF SUBMITTALS WILL BE
GENERAL AND WILL NOT RELIEVE THE THE CONTRACTOR FROM THE
RESPONSIBILITY OF ADHERENCE TO THE CONTRACT AND FOR ANY ERROR
THAT MAY EXIST.
TABLE 3.35-A
ORGANIC MULCH MATERIALS AND APPLICATION RATES
RATES:
MULCHES:
NOTES:
Per Acre
Per 1000 sq. ft.
Straw or Hay
1 k - 2 tons
70 - 90 lbs.
Free from weeds and coarse
(Minimum 2
matter. Must be anchored.
tons for
Spread with mulch blower
winter cover)
or by hand.
Fiber Mulch
Minimum
35 lbs.
Do not use as mulch for
1500 lbs.
winter cover or during hot,
dry periods.* Apply as
slurry.
Corn Stalks
4 - 6 tons
185 - 275 lbs.
Cut or shredded in 4-6"
lengths. Air-dried. Do not
use in fine turf areas. Apply
with mulch blower or by
hand.
Wood Chips
4 - 6 tons
185 - 275 lbs.
Free of coarse matter. Air-
dried. Treat with 12 lbs
nitrogen per ton. Do not
use in fine turf areas. Apply
with mulch blower, chip
handler, or by hand.
Bark Chips
50 - 70 cu.
1 2 cu. yds.
Free of coarse matter. Air -
or
yds.
dried. Do not use in fine
Shredded
turf areas. Apply with
Bark
mulch blower, chip handler,
or by hand.
When fiber mulch is the only available mulch during periods when straw
should be used, apply at a minimum rate of 2000 lbs./ac. or 45 lbs./1000 sq. ft.
Source: Va. DSWC
MANAGEMENT STRATEGY AND SEQUENCE OF CONSTRUCTION
THE FOLLOWING ARE THE PROPOSED MANAGEMENT STRATEGIES AND DETAILED
SEQUENCE OF CONSTRUCTION. REQUIRED PERMITS MUST BE IN -HAND BEFORE
WORK BEGINS:
PHASE 1
1. INSTALL CONSTRUCTION ENTRANCE. TRUCKS SHALL BE CLEANED PRIOR TO
LEAVING THE SITE.
2. INSTALL SILT FENCE, INLET PROTECTION, OUTLET PROTECTION AND CHECK
DAMS AS SHOWN ON SHEET C7
PHASE 2
1. CONTACT THE ENGINEER AND ALBEMARLE COUNTY FOR INSPECTION AND
APPROVAL OF ALL E&S CONTROL MEASURES.
PHASE 3
1. UPON APPROVAL OF E&S CONTROL MEASURES, BEGIN WHOLESALE CLEARING,
AND GRADING
2. MAINTAIN PERIMETER CONTROLS UNTIL ROAD CONSTRUCTION IS COMPLETED
AND AREA HAS ACHIEVED TEMPORARY STABILIZATION.
3. AS AREAS ARE BROUGHT TO GRADE, APPLY MULCHING, TEMPORARY SEEDING
AND PERMANENT SEEDING AS SHOW ON SHEET C5..
5. AS STORM STRUCTURES ARE CONSTRUCTED, INSTALL INLET PROTECTION AND
OUTLET PROTECTION..
PHASE 4
1. INSTALL LEVEL SPREADERS WHEN UPSTREAM GRADING IS COMPLETED AND
HAS ACHIEVED STABILIZATION.
2. ESTABLISH AND MAINTAIN PERMANENT STABILIZATION, INCLUDING VEGETATION
OF ALL SLOPES AND GRASSED AREAS.
3. ONCE SITE HAS REACHED STABILIZATION, REMOVE PERIMETER CONTROLS.
4. CLEAN OUT ALL SEDIMENT BUILD UP FROM STORM CULVERTS AND LEVEL
SPREADERS..
CONSTRUCTION MAINTENANCE
THE FOLLOWING CONSTRUCTION MAINTENANCE PRACTICES SHALL BE FOLLOWED
AT THE SITE.
1. ALL E&S CONTROL MEASURES WILL BE CHECKED DAILY AND AFTER EACH
SIGNIFICANT RAIN EVENT. ALL DEFICIENCIES IDENTIFIED DURING THESE
INSPECTIONS SHALL BE CORRECTED AS SOON AS PRACTICABLE.
2. THE SILT FENCE BARRIER SHALL BE REGULARLY CHECKED FOR UNDERMINING,
DETERIORATION OR SIGNIFICANT EROSION. SEDIMENT SHALL BE REMOVED
AFTER EACH STORM EVENT AND WHEN THE LEVEL OF SEDIMENT DEPOSITION
REACHES HALF THE HEIGHT OF THE CONTROL.
3. THE CONTRACTOR IS RESPONSIBLE FOR ADHERING TO ALL MAINTENANCE
REQUIREMENTS SET FORTH IN THE CURRENT EDITION OF THE VIRGINIA
SEDIMENT AND EROSION CONTROL MANUAL, OTHER APPLICABLE
COMMONWEALTH OF VIRGINIA REGULATIONS AND THE PROJECT
SPECIFICATIONS.
4. ALL SEEDED AREAS WILL BE REGULARLY CHECKED TO ENSURE THAT A GOOD
STAND OF GRASS IS MAINTAINED.
5. ALL AREAS SHALL BE MAINTAINED IN ACCORDANCE WITH THE REQUIREMENTS
OF THIS E&S CONTROL PLAN.
ENVIRONMENTAL CONTROLS
1. CONTRACTOR SHALL PROVIDE AND MAINTAIN ALL ENVIRONMENTAL CONTROL
MEASURES SO AS TO COMPLY WITH LOCAL ORDINANCES, STATE AND FEDERAL
LAWS AND REGULATIONS APPLICABLE TO WATER POLLUTION IN WATERS OF
THE STATE AND IN INTERSTATE WATERS.
2. CONTRACTOR SHALL MINIMIZE THE POTENTIAL FOR AIR POLLUTION BY THE
USE OF EMISSION CONTROL EQUIPMENT ON CONTRACTOR OPERATED
EQUIPMENT, SHUT -DOWN OF MOTORIZED EQUIPMENT WHEN NOT IN USE, AND
ACTIVELY CONTROLLING DUST EMISSIONS THROUGHOUT THE PROJECT.
3. ANY WASTE DISCOVERED DURING THE PROJECT SHALL NOT BE MOVED WITH
OUT PRIOR AUTHORIZATION OF THE OWNER AND BE DIRECT -LOADED INTO
COVERED ROLL -OFF CONTAINERS FOR TEMPORARY STORAGE PRIOR TO
DISPOSAL IN A PERMITTED LANDFILL.
■S•AXt0014WE11a sIT, r_l1►IIailkEdaIlywe] ago] :416*11
❑ SPREADER LIP SHOULD BE FLAT.
❑ CHECK FOR SEDIMENT BUILDUP AND STRUCTURAL DAMAGE. NOTE IF ANY
SEDIMENT NEEDS TO BE REMOVED.
❑ EVALUATE THE VEGETATIVE QUALITY OF THE ADJACENT GRASS BUFFER AND
PERFORM SPOT -RESEEDING IF THE COVER DENSITY IS LESS THAN 90%.
❑ GENERALLY INSPECT THE UPLAND CONTRIBUTING DRAINAGE AREA FOR ANY
CONTROLLABLE SOURCES OF SEDIMENT OR EROSION.
❑ LOOK FOR WEEDY GROWTH ON THE STONE SURFACE THAT MIGHT INDICATE
SEDIMENT DEPOSITION OR CLOGGING.
❑ LONG-TERM MAINTENANCE INSPECTIONS SHOULD OCCUR AT LEAST ONCE
EVERY TWO YEARS.
TABLE 3.31-C
TEMPORARY SEEDING PLANT MATERIALS, SEEDING RATES, AND DATES
SEEDING RATE
NORTHa
SOUTH'
PLANT
311
5/1
S/IS
2/IS
111
911
SPECIES
CHARACTERISTICS
Acre
I" ft,
to
to
to
to
to
to
4/30
8/15
11/1
4/30
9/1
11115
OATS
3 bu. (up to 100 lbs.,
2 lbs.
X
-
-
X
-
-
Use spring varieties (e.g., Noble).
(Avena sativa)
not leas than 50 lbs.)
RYE4
2 bu. (up to 110 Ibs.,
2.5 lbs.
X
-
X
X
-
X
Use for late fall seedings, winter
(sec.] e cereale)
not less than 50 lbs.)
cover. Tolerates cold and low
moisture.
GERMAN MILLET
50 lbs.
approx. I lb.
-
X
-
-
X
-
Warm-seasm annual. Dies at first
(Setarie italics)
frost. May be added to summer
mixes.
ANNUAL RYEGRASSc
60 lbs.
1'h lbs.
X
-
X
X
-
X
May be added in mixes. Will
Lo( lium multi-flomm)
mow out of most stands.
WEEPING
IS Ibs.
5'h ors.
-
X
-
-
X
perennial.
-sToenes
LOVEGRASSdry
bunch. ht, slopes
(Emarostis -la l
and acid, infertile soils. May be
added to mixes.
KOREAN
25 lbs.
ppm.. 1'h
X
X
-
X
X
-
Warm season annual legume.
LESPEDEZA`
lbs.
Tolerates wid soils. May be
(Lesoed- sti lacea)
added to mixes.
a Northern Piedmont and Mountain region. See Plates 3.22-1 and 3.22-2.
b Southern Piedmont and Coastal Plain.
` May be used as a cover crop with spring seeding.
d May be used as a cover crop with fall seeding.
X May be planted between these dates.
- May n_Qt be planted between these dates.
MINIMUM STANDARDS (MS)
All applicable Virginia Erosion and Sediment Control Regulations and Minimum
Standards shall be adhered to during all phases of construction. These
include, but are not limited to the following:
1. STABLIZATION OF DENUDED AREAS:
Permanent or temporary soil stabilization shall be applied to bare areas
within seven days after final grade is reached on any portion of the site.
Temporary soil stabilization shall be applied within seven days to denuded
areas that may not be at final grade, but will remain dormant or
undisturbed for longer than 7 days. Permanent stabilization shall be
applied at areas that are to be left dormant for more than 1 year.
2. STABILIZATION OF SOIL STOCKPILES:
During construction of the project, soil stockpiles shall be stabilized or
protected with sediment trapping measures. The applicant is responsible for
temporary protection and permanent stabilization of all soil stockpiles on
site as well as soil intentionally transported from the project site.
3. PERMANENT VEGETATIVE COVER
A permanent vegetative cover shall be established on denuded areas not
otherwise permanently stabilized. Permanent vegetation shall not be
considered established until a ground cover is achieve that, in the opinion
of the city Inspector, is uniform and mature enough to survive to inhibit
erosion.
4. TIMING & STABILIZATION OF SILT TRAPPING MEASURES:
Sediment basins and traps, perimeter dikes, sediment barriers and other
measures intended to trap sediment shall be constructed as a first step in
any land disturbing activity and shall be made functional before upslope
land disturbance takes place.
5. STABILIZATION OF EARTHEN STRUCTURES:
Stabilization measures shall be applied to earthen structures such as
dams, dikes and diversions immediately after installation.
6. SEDIMENT TRAPS AND BASINS:
A sediment basin shall control surface runoff from disturbed areas that is
comprised of flow from drainage areas greater than or equal to three acres.
The sediment basin shall be designed and constructed to accommodate the
anticipated sediment loading for the land disturbing activity. The outfall
device or system device shall take into account the total drainage area
flowing through the disturbed area to be served by the basin.
7. CUT AND FILL SLOPES:
Cut and fill slopes shall be designed and constructed in a manner that
will minimize erosion. Slopes that are found to be eroding excessively
within one year of permanent stabilization shall be provided with additional
slope stabilizing measures until the problem is corrected.
& CONCENTRATED RUN-OFF DOWN CUT OR FILL SLOPES:
Concentrated runoff shall not flow down cut or fill slopes unless contained
within an adequate temporary or permanent channel, flume, or slope drain
structure.
9. WATER SEEPS FROM A SLOPE FACE:
Whenever water seeps from a slope face, adequate drainage or other
protection shall be provided.
10. STORM SEWER INLET PROTECTION:
All storm sewer inlets that are made operable during construction shall
be protected so that sediment -laden water cannot enter the conveyance
system without first being filtered or otherwise treated to remove sediment.
11. STABILIZATION OF OUTLETS:
Before newly constructed stormwater conveyance channels are made
operational, adequate outlet protection and any required temporary or
permanent channel lining shall be installed in both the conveyance channel
and receiving channel.
12. WORK IN LIVE WATERCOURSES:
When work in a live watercourse is performed, precautions shall be taken
to minimize encroachment, control sediment transport and stabilize the work
area to the greatest extent possible during construction. Nonerodible
material shall be used for the construction of causeways and cofferdams.
Earthen fill may be used for these structures if armored by nonerodible
cover materials.
11CROSSING A LIVE WATERCOURSE:
When a live watercourse must be crossed by construction vehicles more
than twice in any six month period, a temporary stream crossing
constructed of nonerodible materials shall be provided.
14. APPLICABLE REGULATIONS:
All applicable federal, state and local regulations pertaining to working in
or crossing live watercourses shall be met.
15. STABILIZATION OF BED AND BANKS
The bed and banks of a watercourse shall be stabilized immediately after
work in the watercourse is completed.
16. UNDERGROUND UTILITIES:
Underground utilities shall be installed in accordance with the following
standards in addition to other criteria:
a.No more than 500 linear feet of trench may be opened at one time.
b. Excavated material shall be placed on the uphill side of trenches
c. Effluent for dewatering operations shall be filtered or passed through
approved sediment trapping device, or both, and discharged in a manner
that does not adversely affect flowing streams or offsite property.
d.Material used for backfilling trenches shall be properly compacted in order
to minimize erosion and promote stabilization.
e.Restabilization shall be accomplished in accordance with these regulations.
f. Applicable safety regulations shall be complied with.
17. CONSTRUCTION ACCESS ROUTES:
Where construction vehicle access routes intersect paved public roads,
provisions shall be made to minimize the transport of sediment by vehicular
tracking onto paved surfaces. Where sediment is transported on to a
public road surface, the road shall be cleaned thoroughly at the end of
each day. Sediment shall be removed by shoveling or sweeping and
transported to a sediment control disposal area. Street washing shall be
allowed only after sediment is removed in this manner. This provision shall
apply to individual lots as well as to larger land disturbing activities.
18. TEMPORARY E&S CONTROL MEASURE REMOVAL:
All temporary erosion and sediment control measures shall be removed
within 30 days after final site stabilization or after temporary measures are
no longer needed, unless otherwise authorized by the local program
authority. Trapped sediment and the disturbed soil areas resulting from the
disposition of temporary measures shall be permanently stabilized to prevent
further erosion and sediment.
19. ADEQUACY OF RECEIVING CHANNELS:
Properties and waterways downstream from the development site shall be
protected from sediment deposition, erosion and damage, due to increases
in volume, velocity and peak flow rates of stormwater runoff for the stated
frequency storm of 24-hour duration.
SHIMP
ENGINEERING
LAND PLANNING - PROJECT MANAGEMENT
912 E. HIGH ST. 434.227.5140
CHARLOTTESVILLE VA, 22902 JUSTIN@SHIMP-ENGINEERING.COM
Lic. 183
O `
��SSJONAL 1�G
VSMP PLAN
PERRY
RESIDENCE
ALBEMARLE COUNTY, VIRGINIA
SUBMISSION:
2020.02.28
REVISION:
1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
FILE NO.
E & SC NARRATIVE
19.024
PERMANENT SEEDING PS
C5 Not To Scale
2 MULCHING MU
C5 Not To Scale
3 TEMPORARY SEEDING TS
C5 Not To Scale
SHEET C5 of C7
SOIL EROSION & SEDIMENT CONTROL SYMBOLS
SYMBOL N0. TITLE KEY
SEE NOTE I'---
i
------ ------------
1` - - - - - - - - - - - - - - - - - -
I I � LIMITS OF \
Go
i.------------------------ _----- DISTURBANCE
---- 3.58
- - - - - - -
/114
/ -
92 4g0 Cx —x —X— -x
94
96 ' I \\
98
98
/ I
4 - �o SF
40,
00,
/ 96 I - ---------" __-
♦♦♦ / SF/ TOtKPIL
♦ / +' /� / / 92/
90
88
/ ___----- v
Ex. - - - /
E // 82/ X i SEE NOTE I
TREELIN\\\ \
/ ,I I \
78 `� ♦ `ti
OP
\ \ \ IP / ♦ /
v v v A v vv vv ` I 60- v15" HDPE + v /6—
vv vv vv \ vv vv v I Cu pv0 6.7% � <'
82
\ \ \ \ 'r9 `
I
82
' 1
/ 1,
CD
_ 1
_ 7
- - — — 480�
SF
IP
52 CF
DD�ufRr #7�SU NDP
f
Sl�3.12 ,3
s w S
�q �e 4.
RoWe
(50' 2� 35
�
R/W)
CD
�, \
\
/ ;
I
x.
/
TREELINE
I I
I �
,
6 j
I
EX DIRT
1
DRIVEWAY,/
470
-- -----
-`,
.•. r. r. r. r. r. r..
BENCHMARK
ELEV= 486.88
e
EXISTING
STREAM
NOTE 1:
UNDISTURBED AREAS DOWNSTREAM OF LEVEL SPREADERS MUST
NOT RECEIVE RUNOFF UNTIL FULL STABILIZATION IS ACHIEVED UP
STREAM.
3.02 CONSTRUCTION ENTRANCE CE
3.05
SILT FENCE
SF
3.07
INLET PROTECTION
IP
3.18
OUTLET PROTECTION
OP
3.20
CHECK DAMS
CD
3.31
TEMPORARY SEEDING
TS
3.32
PERMANENT SEEDING
PS
3.35
MULCH
MU
LIMITS OF DISTURBANCE
EC-2 MATTING SCC
EC-3 MATTING SCC
SHIM
ENGINEERING
LAND PLANNING - PROJECT MANAGEMENT
912 E. HIGH ST. 434.227.5140
CHARLOTTESVILLE VA, 22902 JUSTIN@SHIMP-ENGINEERING.COM
!Jli i LTIuv 3aiTiF
Lic. 183
1.6 � I
�O �
�411SS70NAL '�
VSMP PLAN
PERRY
RESIDENCE
ALBEMARLE COUNTY, VIRGINIA
SUBMISSION:
2020.02.28
REVISION:
1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
FILE NO.
19.024
EROSION & CONTROL
PLAN
SHEET C6 of C7
GRAVEL CURB INLET SEDIMENT PIPE OUTLET CONDITIONS TYPICAL TREATMENT _ I TYPICAL ORIENTATION OF
FILTER STAKING DETAIL EC-3 TYPICAL INSTALLATION AT ENO OF PIPE A A (SOIL STABILIZATION BLAN ET) TREA THE T _ I
SOIL STABILIZATION MAT MAY BE
USED TNCONJUNCTION WITH STANDARD �' TALLA T CRITERIA
(SOIL STABILIZATION LA E T�
EC•t EROSION CONTROL STONE AT OUTLET END OFF PIPE. I I I
JL
f I
BETWEEN ROLLS � 3T� CES OR PINS 3 d o
Ido
d o SHALLOW
Fe�
ANCHOR SLOT SLOPE
PIPE OUTLET TO FLAT
J r �'p' ENTRENCH EDcesA - AREA WITH NO DEFINED
OF MATERIELS B". NOTES
I ON SHALLOW SLOPES, STRIPS OF
CHANNEL -III-III_, IIII NETTING PROTECTIVE COVERINGS
PLAN VIEW APPROXIMATELY 200 STAPLES REQUIRED -1111i
PER 100 SLOTS,
, J C MATERIAL ROLL. III-_ MAY L APPLIED ACROSS
CHECK sLOT 25'o.c. ANCHOR SLOTS, JUNCTION SLOTS &-Ill,il � III= THE SLOPE.
I CHECK SLOTS TO BE BURIED 6" TO 12".
TRANSVERSE I L a 12" MAX. 4:1 OR FLATTER
CL05E❑ CHECK SLOT I. OVERLAP JUNCTION SLOT 6" MAX. STEEPER THAN 4:1 T
3" � I~
END JOINTS
GRAVEL FILTER* 12" LS 7p 8„ 0 % CHECK SLOT * TOGBEAND SNUGLY ABUTTED I I I I I I I I I JL-III=III-BERM
- WHERE THERE IS A BERM AT THE TOP OF THE SLOPE, III -III -III-
RUNOFF WATER WIRE MESH
d TERMINAL FOLD JUTE MESH WILL HAVE I BRING THE MATERIAL OVER THE BERM AND ANCHOR IT ]� JLI=III=III
'TRANSVERSE CHECK SLOT TD BE III -� ( I BEHIND THE BERM. III=III=III-]�
FILTERED WATER CONSTRUCTED IN ADODRDANCE WITH $ STAPLED LAP JOINT INTJ-LI-III=III-1�7-T]-�7T-
7FE MIWJFgCTURER'S RECOMMENDATION I III=III-
FOR PREFERRED INSTALLATION. .,� LAP JOINT 2" MIN. LIEU OF EDGE JOINT)
° 4 TRANSVERSE �� SECTION A -A FILTER CLOTH KEY IN 6"-9"; RECOMMENDED FOR ENTIRE PERIMETER (JUTE MESH ONLY) I I I �� � ;=7
OPEN CHECK SLOT
e V DITCH TAMP FIRMLY I STEEP
0 0 - ANCHOR SLOT I I SLOPE
I o � 5' MAX. 4:1 OR FLATTER
_ D iff
NOTES! A 3' MAX. STEEPER THAN 4:1
II I r 2' -
p D d T, STAKES SHALL BE WOOD OR METAL AS RECOMIENDED BY THE MANUFACTURER AND SHALL BE A MNIWUM I I
OF 12" IN LENGTH- IN SANDY SOILS METAL STAKES A MMAMDN OF 7B" 1N LENGTH SHALL BE DSEO- J1-fll-III-II ON STEEP SLOPES, APPLY
SOIL
STABILIZATION MAT TYPE A AWp p ARE TO BE IN ACCORONcE WITH THE APHROVEA PRODUCTS Lt$T, _ ll lll I I _ PROTECTIVE COVERING PARALLEL
�041a `� 3d o (MIN.)I�I 6" TO 12" 1 1 1 1 1 I 1 TO THE DIRECTION OF FLOW
_ _ - 3. THE EMBEDDED
8' MAT SHpLIO 6E BOTH
SIDES
F THE DITCH
BREAK PONT D E7[ITHE GROUND A -�-� i7�i7777777�777 AND ANCHOR SECURELY.
SEDIMENT d AAall I ELEVA�N�SDDEi7 B MATERIAL ON BOTH SIDES OF THE DITCH SHALL BE INSTALLED TO THE SAME -lll- 1 I I I I I T111-III
. .. 4-IF MORE THAN 3 LINES OF MATERNAL ARE REQUIRED PARALLEL TO THE � OF THE DITCH, MATERIAL SHALL
BE INSTALLED PERPENDICULAR TO THE CENTER LINE OF THE DITCH. STARTING AT THE LOWEST C ELEVATION d
CONCRETE GUTTER OF THE DITCH. o * 1 1 1 1 1 1
12" CURB INLET 5. FOR SOURCES OF APPROVED MATERIALS SEE VDOT'S APPROVED PRODUCTS LIST FOR SPD.EC-3. CHECK SLOT - -
UPSTREAM AND DOWNSTREAM TERMINAL TYPE A OR B.
PIPE OUTLET TO WELL
SPECIFICATION DEFINED CHANNEL TAMP 1 TO 2
lypQE CHECK SLOT I I I I I
REFERENCE SOIL STABILIZATION MAT FIRMLY
DITCH INSTALLATION TYPE A OR B ROAD AND HRIDrX STAWARDS PLAN VIEWT; SPECIFIC APPLICATION 3RF REVISION DATE SHEET I aF a VAR. VAR. I 4"
F.I'F. VIRGINIA DEPARTMENT OF TRANSPORTATK)N 133.03 VIEW 6" 112" 6 TO 8 PLAN d IEW TERMINATING RTHE DI INSTALLATION. TURNTHEBENDRE --��
THIS METHOD OF INLET PROTECTION IS APPLICABLE AT CURB INLETS
L a - STAPLING DIAGRAM UNDER 4" AND STAPLE AT 12" INTERVALS. 12
WHERE PONDING IN FRONT OF THE STRUCTURE IS NOT LIKELY TO CAUSE
INCONVENIENCE OR DAMAGE TO ADJACENT STRUCTURES AND UNPROTECTED STAPLE FORMED FROM N0.11 STEEL WIRE. *CHECK SLOTS AT MIN.
AREAS. 50' C-C INTERVALS;
2 EC - 3 MATTING DETAIL 0 % 8" STAPLE MIN. LENGTH FOR SANDY SOIL. NOT REQ.'D WITH ALL
6" STAPLE MIN. LENGTH FOR OTHER SOIL. "COMBINATION"BLANKETS DITCH FLOW
* GRAVEL SHALL BE VDOT #3, #357 OR 5 COARSE AGGREGATE. = d IN DITCHES, APPLY PROTECTIVE COVERING
C8 Not To Scale III - PARALLEL TO THE DIRECTION OF FLOW.
�� JUNCTION SLOT TAMP USE CHECK SLOTS AS REQUIRED. AVOID
SECTION A -A
GRAVEL AND WIRE , `ESN TERMINAL FOLD - - JOINING MATERIAL THE CENTER OF
�/ 1� FILTER CLOTH KEY IN 6"-9"; RECOMMENDED FOR ENTIRE PERIMETER 2 FIRMLY � THE DITCH IF AT ALL L POSSIBLE.
[TAMP FI MLY12 6 TO 12IT�ITI-
DROP INLET SEDIMENT NOTES: 1. APRON LINING MAY C RIPRAP, GROUTED RIPRAP, GABION 4»
BASKET, OR CONCRETE.
FILTER bD 2. La IS THE LENGTH OF THE RIPRAP APRON AS CALCULATED -III- 11=III=1
III- -III=1 I I-1 11=
USING PLATES 3.18-3 AND 3.18-4. --
u-�-�-� 2I-
18" MIN. * 3. d - 1.5 TIMES THE MAXIMUM STONE DIAMETER, BUT NOT - -III-I11 ll1-_ _ _ _ -III=11�11�111=III=III=III=III=III=1''
( ) LESS THAN 6 INCHES.-11�11111-III-III=III=III=III-
GRAVEL 12"MIN. DEPTH 1-ll1-ll1-ll1-ll1-ll1- I
1 1Jl lll lll lll lll - - ll1 ll1 ll1 ll1 ll
,,, ,,,111-111-111-111-111„
RUNOFF WATER
WITH SEDIMENT Paved construction entrance for erosion control plans Source: Va. DSWC Plate 3.18-1
Outlet Protection Details
Culvert Area (ac) Flow (cis} Dia. (in) Do (ft) 3Do (ft) La (it} W (ft) SOURCE: VDOT ROAD AND BRIDGE STANDARDS PLATE: 3.36-2
STONE -70' MIN, 5 EC -2 INSTALLATION DETAIL
III CONSTRUCTION 1 2.82 4.05 15 1.25 3.75 9 10.25
a ACCESS 3" SM-2A ASPHALT TOP 2 4.66 8.16 15 1.25 3.75 10 11.25 C8 Not To Scale
- cv
- IIII� 1I III -°RE -2%- EXISTING 4 INSTALLATION DETAIL
SEDIMENT n WIRE MESH ;..�---:_.: :..; ,.�:.::� 3 OUTLET PROTECTION OP Q
' Ltf
FILTERED Q Not To Scale
WATER ''` � - - w - �-� C8 Not To Scale C8
SPECIFIC APPLICATION 5" '.1 N. 2 A AGGR`_GAl -- NASE
THIS METHOD OF INLET PROTECTION IS APPLICABLE
WHERE HEAVY CONCENTRATED FLOWS ARE EXPECTED PROFILE
BUT NOT WHERE PONDING AROUND THE STRUCTURE SHIM
MIGHT CAUSE EXCESSIVE INCONVENIENCE OR DAMAGE
'' jNE N. CONSTRUCTION OF A SILT' FENCE E N G I N E E R I N G
�OCNESTRUCTION r-ASPHALT PAVE`' (WITHy IRE S UPPOR T� DOCK CHECK
CK DA �j � LAND PLANNING -PROJECT MANAGEMENT
wASHRAcJ( J( 14/1
TO ADJACENT STRUCTURES AND UNPROTECTED AREAS.
C`C 912 E. HIGH ST. 434.227.5140
* GRAVEL SHALL BE VDOT #3, #357 OR #5 COARSE r r- EXIS7 F2 ACRES OR LESS OF DRAINAGE AREA
AGGREGATE. 2% PAI'F':'I ''.'T CHARLOTTESVILLE VA, 22902 JUSTIN@SHIMP-ENGINEERING.COM
a 27 12' MIN.* '- 1. SET POSTS AND EXCAVATE A 4"X4" 2. STAPLE WIRE FENCING TO THE POSTS.
SOURCE: VA. DSWC PLATE. 3.07-2 i TRENCH UPSLOPE ALONG THE LINE
OF POSTS.
6„
N LET P ROTECTI 0 N (IP) ``:'I EXTEND FILL tNIOTH �0 ',-POSITIVE TSEDIMENT
:I NGRESS AND EGRESS 3' TRAPPING DEVICE
C8 Not To Scale OPERATION
-� � � FILTER CLOTH OF G
PLAN o� r
(OPTIONAL)�Ci
(DOWNSTREAM VIEW) 12' v
�� VDOT # 1 M. S IMP
MIN. DRAINAGE� TO SEDIMENT � ( I � � COARSE AGGREGATE Lic. 183
2% IRAPPING DEVICE
FLOW
FILTC•< CL'u-I I �
SECTION A -A FLOW II n II n
4"
A 1lllllilnl1111 water tap of 1 hich must be histallecl %itfi a lllillllnlun 1 inch vallcock
81111tOffNYal-Ve 811pp1si11 a w'aSh ho-e ww'it11 a c11a111eter of 1.5 for adequate 3. ATTACH THE FILTER FABRIC TO THE WIRE 4. BACKFILL AND COMPACT THE 2 -1 0 ACRES OF DRAINAGE AREA: VSMP PLAN
constant pl'essme. Wash water L11113t be carried away from the entrallce to all FENCE AND EXTEND IT INTO THE TRENCH. EXCAVATED SOIL.
approw-ed �ettlhiga area to 1•enio-w-e �edu11e11t. -11 seclil11eiit ,311allUe prevented frolic PERRY
elltedim storm cll'all1S, ditclle ww- or atercimur es.
� 6"
PAYED WASH LACK II
3RESIDENCE
NO SCA' E { � FILTER CLOTH
i'`s+i'IIII �� (OPTIONAL)
ALBEMARLE COUNTY, VIRGINIA
ill VD(DOWNSTREAM VIEW) VDOT #1 SUBMISSION:
r COARSE AGGREGATE �2020.02.28 FLOW / II I-
_ FLOW ?. REVISION:
6 PAVED CONSTRUCTION ENTRANCE(PCE)-I I11 �11 „ _III 3
C8 Not To Scale I= I III 1. 04/07/2020 County Comments
2. 06/08/2020 County Comments
EXTENSION OF FABRIC AND WIRE INTO THE TRENCH.
FILTER FABRIC CLASS I RIPRAP
SOURCE: VA. DSWC PLATE. 3.20-1
-� WIRE
JI1J I I- -
I1 FILE NO.
� 8 1ROCK CHECK DAM (CDC 19.024
TITFNF Cg Not To scale SITE DETAILS 1
C$ Not To Scale
SHEET C8 of C8