HomeMy WebLinkAboutWPO202000021 Correspondence 2020-06-10Emily Cox
From: Frank Pohl
Sent: Wednesday, June 10, 2020 3:14 PM
To: Emily Cox
Cc: Geoff Elsie; Carla Harris - CDD
Subject: RE: WPO-2020-00021 Bundoran Farm Lot B2
Emily,
No, it doesn't need a SWPPP. As mentioned, this is one where the builder wants to install the stream crossing before
submitting for the building permit. So we agreed he could submit a VESCP plan now for the stream crossing and later
when he submits the building permit he can submit the agreement in lieu of a stormwater management plan.
Please print this and save it to CountyView or include in a file somewhere.
Thanks,
Frank
Frank V. Pohl, PE, CFM
County Engineer
401 McIntire Road
Charlottesville, VA 22902
434-296-5832 (ext. 7914)
From: Emily Cox <ecox2@albemarle.org>
Sent: Wednesday, June 10, 2020 11:13 AM
To: Frank Pohl <fpohl@albemarle.org>
Subject: FW: WPO-2020-00021 Bundoran Farm Lot B2
Importance: High
Frank -
Does this plan need a SWPPP? This is the VESCP plan for Bundoran with the driveway culvert. I did not require it during
my review as it is not included in the code Sec. 17-402 for E&S plans, however, I understand we can still require them.
Please let me know!
Thanks!
Emily Cox, PE
Civil Engineer II
(434) 296-5832 Ext. 3565
401 McIntire Rd.
Charlottesville, VA 22902
www.albemarle.org
1