HomeMy WebLinkAboutWPO202000027 Review Comments WPO VSMP 2020-06-12COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Project title:
Project file number:
Plan preparer:
Owner or rep.:
Plan received date:
SWM Plan:
Date of comments:
SWM Plan:
Reviewers:
VSMP Permit plan review
ELDON FARM RESIDENCE - VSMP - DIGITAL
WPO202000027
Shimp Engineering P.C. [Justin@shimp-engineering.com]
Eldon Farm, LLC
Troy Wade [troy@jamisondaviscompany.com]
Shelter Associates [JD@shelterltd.com]
[laina@shelterltd. com]
12 May 2020
09June 2020
09 June 2020
12 June 2020
Emily Cox
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESOP, (3) a SWMP, and (4) any TMDL measures necessary.
SWPPP not provided. A registration statement was provided, but no SWPPP. Here is a template:
http://www.albemarle.org/upload/images/forms center/departm
ents/Community Development/forms/Engineering and WPO Forms/
Stormwater Pollution Prevention Plan SWPPP template.pdf
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. PPP not provided. Please ensure a plan is provided and all items in County Code section 17-404
are addressed.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. A SWM maintenance agreement will be necessary before plan approval. Please contact Ana
Kilmer (akilmer(c�r�,albemarle.org) to begin that process.
Engineering Review Comments
Page 2 of 3
2. Please show a graphic of the 2.76 acres to be recorded in an easement. Label it as "SWM forest &
open space. Please note the plat must be recorded before the plan can be approved.
3. Add the following note on the plan and plat, "The SWM Forest and Open Space Easement is
subject to the guidance set forth by DEQ in the Virginia Stormwater Management Program. The
areas will remain undisturbed in a natural, vegetated state, except for activities as approved by the
local program authority, such as forest management, control of invasive species, replanting and
revegetating, passive recreation (e.g., trails), and limited bush hogging to maintain desired
vegetative community (but no more than four times a year)."
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion
control plan content requirements can be found in County Code section 17-402.
1. Silt fence in such short lengths on the southwestern end of the site does not seem effective.
2. Please provide a construction entrance with a wash rack and the appropriate detail from page 8 of
the design standards manual:
http://www.albemarle.org/upload/images/forms center/departm
ents/community development/forms/design standards manual/Al
bemarle County Design Standards Manual 2014-12-02.pdf
3. Ensure there are sufficient perimeter controls. Specifically, Phase 1, on the NW end — culvert and
pavement removal do not appear to be covered.
4. The culvert between ST 1 and ST 3 needs to have outlet protection. Where is it draining to, ST1
or ST3?
5. Please label contours for ST 3.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process:
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
Engineering Review Comments
Page 3 of 3
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves
the application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
hllp://www.albemarle.ora/deptfonns.asp?department=cdenaw2o