HomeMy WebLinkAboutWPO202000031 Bond Estimates 2020-06-24Project Name: VESCP Plan for Byers Fill Site
WPO file M WP02020-00031
TMP(s): 04700-00-00-001CO3 04600-00-00-033HO
Date Estimate Completed: 06/11/20, K.Rucker - chk. JA 06/12/20
Erosion and Sediment Control Bond Estimate
Item
Item
No. Unit
Unit Cost
Cost
Number
installed
1
stablization (PS, TS)
acres
$5,000.00
$4,950.00
2
silt fence (SF)
ft
$5.00
$5.00
3
safety fence (SAF)
ft
$5.00
$0.00
4
diversion (DID, FD, RWD)
_ ft
$13.00
$13.00
5
temporary slope drain (TSD)
pipe length
0 ft
pipe diameter 0 in
$0.00
$0.00
9
Sediment Trap #1
10
earthwork for trap/basin
11
height of dam at toe
4 ft
cut at high side 12 ft
12
height of fill at face
3 ft
cut at face 1 ft
13
length of dam
llllllllllllllllll�ft
length of cut -ft
14
top width
4 ft
width of cut 15 ft
15
(aru- _ jove transition
30 sf
(area below transiti( 17 sf
16
(total width of dam)
8 ft
(total width of cut) 41 ft
17
(height below transitio
1 ft
(depth below transit 11 ft
18
(area below transition;
3 sf
(area above transifi 104.5 sf
19
(total fill volume)
0.0 cy
(total fill volume) 0.0 cy
20
length of spillway
�ft
(TOAL CY estimate 0 cy
$13.00
$0.00
21
width of spillway
ft
(spillway stone tons 0 tons
$50.00
$0.00
22
structures for basin
23
riser height
ft
24
riser diameter
in
(riser unit price) $0.00
$0.00
25
barrel length
ft
base plate or fdn
$200.00
$0
26
barrel diameter
4A in
(barrel unit price) $0.00
$0.00
27
barrel collars
$200.00
$0
28
baffle length Wft
$50.00
$0
50
silt fence inlet protection (IP)
0
$100,00
$0.00
51
stone inlet protection (IP)
0
$200.00
$0.00
52
outlet protection (OP)-Trap#1
length
0 ft
width -ft
0
$0.00
$0.00
6/16/2020