October 26, 2005
Tim Miller
Rivanna Engineering & Surveying, PLC
1350 Stony Point Road
Charlottesville, VA 22911
RE: SDP - 2005 -059 Town & Country Commercial, Phase 1, Preliminary Site Plan
Dear Tim:
On October 25t', 2005 the Planning Commission granted your request for a critical slope waiver.
On this date, the above referenced preliminary site plan has been administratively approved with
conditions.
The approval of the preliminary site plan is valid for (1) one year in accordance with Zoning
Ordinance Section 32.4.3.1. Therefore, the preliminary approval shall expire October 26, 2006. If the
preliminary site plan approval expires, a new application must be filed and processed.
Please address all of the requirements and conditions listed below and submit eight (8) tentative final
plan copies, final site plan application and fee to the Department of Community Development. This
letter must be submitted with the tentative plans, as a checklist, to document that you have addressed
all requirements or conditions, or the tentative plan will be denied.
The Erosion and Sediment Control Plan and the BMP Stormwater Management Plan, with the
associated applications and fees, may also be submitted with the eight (8) tentative Plans. Failure to do
so will result in a separate application to be filed with the Engineering Department at a later date.
After the initial tentative plan submittal, each department /agency will contact you to discuss any
remaining conditions. After all aforementioned department /agencies have granted approval of the
tentative final plans, you may submit the final mylars (2 sets) and one blueprint copy to the
Department of Community Development by 5:00 p.m. on any Monday.
Assuming that the final site plan mylars reflect all tentative approvals, signing of the plans will occur
within one week.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section 32.6),
in addition to the following conditions.
The Department of Community Development shall not accept submittal of the final site plan for
signature until tentative approvals for the following conditions have been obtained. The final site
plan shall not be signed until the following conditions are met:
A. Division of Zoning and Current Development: Zoning and Planning approval to
include:
❑ [18.4.15.13] Be aware that all signs will require separate permits under 4.15 of the zoning
ordinance.
❑ [30.6] The final plan approval is subject to the issuance of a Certificate of Appropriateness
from the Architectural Review Board.
❑ [I 8.32.5.6(n)] Show the location of all outdoor lighting on the plan.
❑ [18.32.5.6. s] This site lies in the Monticello viewshed. Please coordinate your efforts with
Kat Imhoff at 984 -9802 to determine what impacts this development will have on this
important resource.
❑ [18- 32.5.6.s] Prior to Final Site Plan approval, submit a plat for County review which shows
all proposed off -site grading easements, drainage and utility easements. This plat(s) must be
submitted under a separate application and fee and must be done prior to final site plan
approval.
❑ [18.32.6.6] The final site plan shall reflect conditions of approval of the preliminary site plan.
The final site plan shall contain all the information in this section, including and landscape
plan, in addition to all the information required on the preliminary site plan.
❑ [ 18.32.6.60)] Provide a description and photograph or diagram and show the location of each
type of outdoor luminaire that emits 3,000 or more initial lumens. Please be aware that
installation of such luminaires in the future that are not shown on this plan shall require an
amendment to this plan.
❑ [ 18.32.6.60)] [4.17.4(b)] Include a photometric plan on the site plan demonstrating that
parking area luminaires are in compliance with 4.17.4 b.
B. Division of Zoning and Current Development: Engineering approval to include:
❑ The proposed biofilter addresses SWM quality but not SWM quantity. SWM quantity needs
to be addressed before the final site plan can be approved. [18- 32.5.6k]
❑ The engineering review for current development needs to review and approve all applicable
items as specified in the Design Standards Manual, section 902, before recommending
tentative approval to the final site plan.
C. Albemarle County Service Authority approval to include:
❑ Final approval will not be granted until sewer construction drawings have been reviewed and
approved.
D. Virginia Department of Transportation approval to include:
❑ Prior to final approval the plan must have some labeling added. (12' turn lane width, CG -6,
pavement design & a typical for the improvements).
❑ In addition a plat must be prepared for a right of way dedication for the improvements. The
right of way must minimally extend one foot behind the walk.
Sincerely,
Yadira Amarante
Senior Planner
Cc: Albemarle Hotel, LLC; PO Box 8147; Charlottesville, VA 22901