HomeMy WebLinkAboutSP200500022 Legacy Document 2006-01-12COUNTY OF ALBEMARLE
EXECUTIVE SUMMARY
AGENDA TITLE:
SP 2005 — 022 Berean Baptist Church Expansion
SUBJECT/PROPOSAL/REQUEST:
The applicant is requesting a special use permit to
construct a two-story classroom addition, including a small
gymnasium, to the rear of the existing church. The
addition includes four classrooms, three offices, a nursery,
a conference room, bathrooms, and a gymnasium.
OWNER / CONTRACT PURCHASER:
Berean Baptist Church Board of Trustees
PROPOSAL -
STAFF: Dougherty
PLANNING COMMISSION DATE:
November 15, 2005
BOARD OF SUPERVISORS DATE:
December 14, 2005
Expansion of existing church to accommodate offices, bathrooms, a conference room and 46 X 46 foot gymnasium.
BACKGROUND:
The original site plan for the church was approved by the Planning Commission in1975 when churches were permitted by -
right in the Agricultural district. In 1980, an R-1 zoning designation was applied to this parcel. There is no existing special
use permit for this property. Therefore, the church is non -conforming. This special use permit will allow the church to be in
conformance with the Zoning Ordinance.
DISCUSSION/FINDINGS:
The church's worship and fellowship areas remain the same. Staff finds no impacts which need to be mitigated and
supports the proposal.
RECOMMENDATION:
Staff recommends approval with conditions
STAFF PERSON: Sean Dougherty
PLANNING COMMISSION: November 15, 2005
BOARD OF SUPERVISORS: December 14, 2005
SP -2005-022 BEREAN BAPTIST CHURCH
Applicant's Proposal:
The applicant is requesting a special use permit to construct a two-story classroom addition,
including a small gymnasium, to the rear of the existing church. The addition includes four
classrooms, three offices, a nursery, a conference room, bathrooms, and a gymnasium. The
gymnasium comprises the majority of the addition on the first floor and second floor, as it is
open from the first floor to the ceiling off the second floor. The addition will support the
existing church program, which includes a sanctuary, fellowship hall, and four small
classrooms.
The original site plan for the church was approved by the Planning Commission inl975 when
churches were permitted by -right in the Agricultural district. In 1980, an R-1 zoning
designation was applied to this parcel. There is no existing special use permit for this
property. Therefore, the church is non -conforming. This special use permit will allow the
church to be in conformance with the Zoning Ordinance.
The applicant has submitted a concept plan. The proposed expansion will be developed in
general accord with that concept plan, if the special use permit is approved. The location map
is Attachment A; the concept plan is Attachment B.
Petition
Request for special use permit to allow for expansion of an existing church in accordance
with Section 13.2.2.10 of the Zoning Ordinance which allows for churches in the R-1
residential zoning district. The property, described as Tax Map 76 Parcel 5 1 B contains 4.0
acres, is located in the Samuel Miller Magisterial District at 1284 Sunset Avenue and in the
EC Entrance Corridor Overlay District. The Comprehensive Plan designates this property as
Neighborhood Density in Neighborhood Five. General usage for Neighborhood Density is
residential (3-6 units/acre) and supporting uses such as religious institutions and schools and
other small-scale non-residential uses. General usage within the R-1 zoning district permits
low density residential development at 1 dwelling unit per acre.
Petitioners
The applicant and owner is the Board of Trustees of the Berean Baptist church represented
by architect Alton L. Carver.
Character of the Area:
The church is located at the southwest corner of Old Lynchburg Road and Sunset Avenue.
This portion of Neighborhood Five includes some residential development, with higher
density housing located closer to the Charlottesville city limits, and undeveloped areas. Non-
residential development in the area includes The Country Green Store, other religious
institutions, and the Albemarle County Office Building — 5th Street.
2
RECOMMENDATION
Staff has reviewed this request for compliance with the provisions of Section 13.2.2 of the
Zoning Ordinance and recommends approval with conditions.
Zoning History:
The parcel was zoned Agricultural prior to the 1980 Comprehensive Plan. In 1980, a R-1
residential zoning was applied to the property.
Comprehensive Plan:
The Comprehensive Plan designates this property as Neighborhood Density in Neighborhood
Five. General usage for Neighborhood Density is residential (3-6 units/acre) and supporting
uses such as religious institutions and schools and other small-scale non-residential uses.
General usage within the R-1 zoning district permits low density residential development at 1
dwelling unit per acre.
The Neighborhood Model:
Because the special use permit is for an existing property with a single building addition,
only these principles of the Neighborhood Model apply:
Pedestrian
The property is served by a multi -use asphalt path along Old
Orientation
Lynchburg Road.
Neighborhood
Churches act as neighborhood centers.
Centers
Building and
The addition is two stories and of a similar scale to the existing
Spaces of Human
church.
Scale
Relegated Parking
Berming and mature landscaping from the church's initial site plan
work to relegate parking, though the parking is located between the
church and the Entrance Corridor. As this addition does not trigger an
addition to the parking provided, and the addition is to the rear of the
existing church, a reasonable opportunity to relegate parking does not
exist.
Site Planning that
The addition is proposed in a location that respects terrain and
Respects Terrain
generates minimal impacts to the site.
STAFF COMMENT:
The church's worship and fellowship areas remain the same. The largest area of the addition
is the gymnasium which is large enough to accommodate a half -court basketball court. This
addition does not require more parking because the areas of assembly in the church are not
expanding. In addition, a firewall is required between the existing church and the addition,
such that the fellowship and worship areas cannot be expanded.
3
The Berean Baptist congregation anticipates a fundraising drive and implementing much of
the work and construction for the addition themselves. Therefore, they are requesting an
extension of the standard time frame from two -years to five years. This is reflected in the
conditions below.
This review was conducted with consideration of The Religious Land Use and Institutionalized
Persons Act of 2000 which states:
No government shall impose or implement a land use regulation in a manner that
imposes a substantial burden on the religious exercise of a person, including a religious assembly or
institution, unless the government demonstrates that imposition of the burden on that person,
assembly, or institution — (A) is in furtherance of a compelling governmental interest; and (B) is the
least restrictive means of furthering that compelling governmental interest.
Staffs Address of each provision of Section 31.2.4.1 of the Zoning Ordinance:
The Board of Supervisors hereby reserves unto itself the right to issue all special use permits
permitted hereunder. Special use permits for uses as provided in this ordinance may be
issued upon a finding by the Board of Supervisors
that such use will not be of substantial detriment to adjacent property;.
Staff has not identified any detriment to adjacent property that would result from the new
building.
that the character of the district will not be changed therebyl
The proposal is compatible with the site and surrounding areas.
and that such use will be in harmony with the purpose and intent of this ordinance;
An expansion of the existing use, which has been in place much longer than other uses in the
vicinity, is in harmony with the purpose and intent of this ordinance.
with the uses permitted by right in the district;
Religious uses support R-1 zoning and the associated uses permitted by -right.
and with the public health, safety and general welfare.
Staff does not have concerns regarding public health, safety, and general welfare in relation
to the proposed special use permit.
Engineering and Zoning Comments
Zoning has determined that sufficient parking exists on the site. The proposed addition and
the parking regulations contained in the ordinance do not require a change in the parking
required. A minor site plan amendment will be required for the expansion if the special use
permit if approved.
The application plan notes that an old septic tank and drain field will be removed, as it is
located in the area where the addition is proposed. It is the church's intent to connect to the
public sewer system and abandon the existing septic drain field before construction begins on
the addition. The church currently uses the septic system, but is connected to public water.
al
The church is working with the Albemarle County Service Authority and VDOT to obtain
easements that would allow them to tie into an existing public sewer line located in the
adjacent Mosby Mountain subdivision (please see Attachment C for an update of the
church's efforts to tie into the public sanitary sewer). Since the proposal (addition) is
intended to support existing church programs and will not significantly increase the uses on
the site and given the applicant's pursuit of a connection to the public sewer, staff believes
that a condition requiring connection to public sewer is not necessary in this case.
SUMMARY:
Staff has identified the following factors, which are favorable to this request:
The proposed building makes efficient use of the existing church and property
2. There is adequate parking available on site to address this use.
3. The church will continue to provide a neighborhood service to surrounding residential
areas.
RECOMMENDED ACTION:
Staff has reviewed this request for compliance with the provisions set forth in Section
31.2.4.1 of the Zoning Ordinance and recommends approval with conditions.
Recommended conditions of approval:
1. The improvements and the scale and location of the improvements shall be developed in
general accord with the concept plan dated August 8, 2005.
2. The floor plan of the proposed addition will be no larger than 5,100 square feet.
3. The construction of the church expansion, as shown on the application plan dated August
8, 2005 and titled Berean Baptist Church, shall commence within five years of the approval
of this special use permit or this special use permit shall expire.
4. There shall be no daycare center or private school provided on site without approval of a
separate special use permit.
ATTACHMENTS:
A. Location Map
B. Concept Plan
C. Applicant Letter Regarding Public Sewer Connection
5