SCHEDULE OF COMPLETION FOR BONDED IMPROVEMENTS
PROJECT NAME: Georgetown Hydraulic Professional Offices
(as on bond estimate request form and approved plan)
This form is intended to facilitate the completion of bonded improvements in a timely manner by assuring the
developer has a schedule in place, and by providing this Department a means to assess the developer's ability to
meet the completion date stated in the bond agreement. The developer must provide a completion date for each
milestone listed below.
Date
Milestone
Public Roads
Oct. 1, 2020
Start of construction.
June 19, 2020
Submit all paperwork in accordance with the County's "Public Road Acceptance Procedure"
(certificate of completion, as -built plans, recorded plats, professional engineer certification
for completed improvements, etc.).
VDOT documentation of acceptance (request to Board of Supervisors to adopt
resolution to accept road(s) into secondary road system).
Private Roads
Oct. 1, 2020
Start of construction.
June 19, 2020
Submit all paperwork in accordance with County's "Private Road Acceptance Procedure"
(compiled report of CBR tests, stone depth inspections, and fill compaction tests,
certified by a professional engineer, certificate of completion, as -built plans, recorded plats,
professional engineer certification for completed improvements, etc.).
Request 45-day inspection from County.
Request final inspection from County.
Water & Sewer Improvements
Sept. 1, 2020 Improvements dedicated and "acceptance" letter issued by the Albemarle County Service
Authority.
Additional Bonded Subdivision Improvements (landscaping, pedestrian paths, sidewalks, etc.)
March 1, 2021 Submit signed and sealed letter from a professional engineer listing and certifying that
completed improvements are built according to approved plans and request inspection
from County.
Revised 11/10/2010
Page 1 of 2
SCHEDULE OF COMPLETION FOR BONDED IMPROVEMENTS
By signing below, the owner/developer agrees to complete the bonded improvements in accordance
with the above schedule. If, during the course of construction, the owner/developer finds they will
be unable to meet the schedule, they must provide written justification to the County Engineer of
the reasons preventilncompletion along with a revised completion schedule.
Signature ner/Developer
Robert Noll, on behalf of Hydraulic Georgetown LLC June 15, 2020
Print Name Date
SCHEDULE OF COMPLETION ACCEPTED:
County Engineer Date
Subdivision/Road Performance Bond Completion Date