Loading...
HomeMy WebLinkAboutSUB201900170 Correspondence 2020-09-03® ROUDABUSH, GALE & ASSOCIATES, INC. September 2, 2020 Mr. David James Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Project title: Belvedere Phase 5A Project file number: SUB-2019-00170 Road Plan Review #3 Project file number: SDP-2020-00036 Final Site Plan Review #2 Dear David, Please find attached the revised plans. The plans have been revised to address the comments in accordance with the comments received on the Road Plan and the Final Site Plan. CDD Inspections — Michael Dellinger No Obje CDD E911 — Brian Becker No Objec— Rivanna Water and Sewer Authority — Victoria Fort No objection. Fire Rescue — Shawn Maddox No objection. Virginia Department of Transportation — Max Greene (SDP-2020-00036 & SUB-2019- 00170). Comments received July 16, 2020. ivo objection. Leiter receivea uuiy io, zuzu. "The Department of Transportation, Charlottesville Residency Transportation and Land Use Section, has reviewed the above referenced plan as submitted by Roudabush, Gale, & o 1—f o„ 4�f-A June 22, 2VrI —1 1.—' it t ho no —Ik, I ---- table.,, Countv Plannina — Cameron Lanaille (SUB-2019-00170). Comments dated Julv 23. 2020 1. [General Comment] Please be aware that Planning staff are not reviewing notes and calculations related to certain Zoning Ordinance and Subdivision Ordinance requirements that do not pertain to improvements or land disturbances unrelated to the actual road construction. For example, the allowable density calculations and building height notes on Sheet 1 have not been checked. Comment acknowledged. 2. [4.12.6] One guest parking space per four units is required for single-family attached units that are providing parking on individual lots. Please clarify the required parking notes on Sheet 1; the calculation should state 1 guest parking space per every 4 attached single-family units" and state the required number (10 spaces, fractions must be rounded up). Comment addressed. a. Under "Parking Provided" on Sheet 1, state that 18 on -street guest spaces are provided. Comment addressed. 3. [32.7.9.5 (d)] Street trees must be provided within the 6' landscaping strip within the public right-of-way, and cannot be provided on private lots within a landscaping easement unless VDOT specifically says the trees have to be located outside of the ROW. Conflicts with proposed utilities is a reason that street trees can be located on private lots under Section 32.7.9.5; this is a design issue that must be rectified. Trees on lots 2, 4, 8, 33, 34, 35, 36, 39, 42, and 43 need to be relocated so that they are within the landscaping strip within the street right-of-way. Comment addressed. 4. [32.7.9.5 (d)] Revise the street tree calculation for Fowler Street and Fowler Circle on Sheet 19. Fractions should be rounded up. 28 trees are required for Fowler Street and 24 trees are required for Fowler Circle. Comment addressed. 5. [32.7.9.5] Remove the callout for the 8 TC trees at the southeast end of Fowler Street on Sheet 17, they are not being provided/shown on the plans. Comment addressed. County Engineering — David James (SUB-2019-00170). Comments dated July 17, 2020. Revision #2. 1. Sheet 1: a. Accurate current existing topography and conditions should be field verified within the last year. b. Topography may need to be resurveyed (2016 - Last aerial survey). (Rev.1) Acknowledged. 2. Include County's'General Construction Notes for Public Streets'. (Rev.1) Not addressed. (Rev.2) Acknowledged. 3. Sheet 13: a. Check that the inlet design is correct (LD-204 worksheet). Inlet 23 shows no DA; Inlet 3 Cross SI (Sx). Show correct ID downstream. What is Q intercepted/bypassed, C values (LD-204, Show similar form data)? [Refer to Table 9.1 of VDOT DM] (Rev.1) Addressed. b. Correct pipes with velocity under 3 fps (LD-229 worksheet). Show similar form data. [9.3.5, VDOT DM]. (Rev.1) Not addressed. The minimum scour velocity is 3 fps. Response: The pipe velocity has been increased where possible. The remaining pipes with velocity under 3 fps are short pipes that join into the system from the other side of the road. The slopes in these pipes have been increased to over 7% minimum to aid in the flushing of sediment through the pipes. The velocity is under 3 fps due the small drainage areas serving these inlets. Multiple inlets are necessary due to the space restrictions between driveways. Please see the email from Max Greene, VDOT, on 6/8/2020 where he agrees with the design of the system as shown. Inlet shaping is called in the structures to prevent standing water. (Rev.2) Acknowledged. c. Reduce pipe outlet velocity to 10 fps or less (LD-229 worksheet). (Rev.1) Addressed. d. Provide HGL computations (LD-347). (Rev.1) Addressed. e. Add note or callout to include IS-1, inlet shaping at flow intersections (Str 3, 14, 15, 16, 17). (Rev.1) Addressed. 4. Show/label angle of intersection at entrances. -80 degrees (Min)? [14-410] (Rev.1) Please add label to both intersections showing the angle. (Rev.2) Acknowledged. 5. Show offsite grading easement for the temporary fire access road grading proposed. -how f - nporary access easement for the road as well. (Rev.1) Ar'- A. 6. Record access easement prior to road plan approval. (Rev.1/2) Acknowledged; Comment still valid. Plat undergoing review. Response: Acknowledged, the easement plat has been submitted for review. The grading easement at the entrance of Fowler has been added and the widths of the storm easements have been updated. 7. Submit an amendment to any grading plans affected by the proposed access road construction. They will have to be reviewed/approved prior to road plan approval. Response: No amendments are necessary. (Rev.1) Acknowledged. 8. Sheet 7: Show width of on -street parking. Response: Dimensions have been added to the Site Plan sheet 4. (Rev.1) Addressed. 9. Sheet 9: Show any pipe/utility crossings in the profiles. (Rev.1) Addressed. 10. Sheet 10: Add cross -drains or underdrain at sag. (Rev.1) Stormwater will be impounded by the access road. Temporary E&SC controls would be needed and a WPO plan would need to be submitted. (Rev.2) Currently addressed. 11. Sheet 11: It appears that sight distance easements need to be shown for those outside of the ROW. (Rev.1) Addressed. Submit a plat to recorded them prior to FSP approval. 12. Sheet 12: Where does the road drainage go beyond storm str 12? Show inlets. (Rev.1) Acknowledged. Submit a WPO plan approval required prior to FSP approval. Rev.2) Currently addressed. 13. Provide earthwork vol. estimates of cut & fill for the roads & access grading. Response: The entire parcel will require 119 cubic yards of import. (Rev.1) Acknowledged. 14. (Rev.1) The grade for the emergency access needs to be 10% or less. [18-4.12.17] (Rev.2) Addressed. 15. (Rev.1) The minimum recommended storm size pipe is 15" dia. Initial pipe runs can use 12" dia. if the length of pipe is 50' or less. The max access hole spacing is 50' for 12" dia. 300' for 15-42" dia. pipe. [VDOT DM 9.3.5, 9.3.6, table 9-3] (Rev.2) Addressed. Albemarle County Service Authority — Jeremy Lynn (SDP-2020-00036 & SUB-2019-00170). Comments received July 6, 2020 Sheet 1 1. Final dedication of Belvedere Phase 2B required prior to final plan approval. Response: Acknowledged. 2. Eliminate the following sheets from the ACSA submittal: 12, 17, 21, and 21. Response: Acknowledged. Sheet 6 (revised to sheet 7) 1. Eliminate sanitary sewer pipe material references to avoid any discrepancies. Response: The pipe "call outs" on sheet 6 has been removed. 2. Water meters for Lots 37-42 need to be placed in front of the sidewalks. Response: The water meters have been moved in accordance with email exchange with ACS on 11 August 2020. 3. Clarify which lots are being served by the meters along Fowler Street (behind Lots 34-43). Response: Labels have been added for clarity. 4. No part of the footing, overhang or structure for Lot 31 can fall within the proposed ACSA easement. Response: Acknowledged, neither the overhang nor the footing is within the easement. Sheet 16 (revised to sheet 17) 1. Sanitary sewer between MH's G and H shall be ductile iron. Response: Pipe H — G has been labeled as ductile iron. 2. Call out 60-inch diameter manhole with internal drop for MH A. Response: Call out has been added. Sheet 18 (revised to sheet 19) 1. Eliminate conflicts between street trees and ACSA utilities. Trees in front of Lots 21, 27, 30, and 31 are closer than 10-feet to the ACSA's sanitary sewer main. Response: Landscaping has been revised. We thank you for taking the time to review these plans and trust the above adequately addresses your comments. However, please let me know if you have any questions or require additional information. Respectfully, Riki Van-Niekerk ® ROUDABUSH, GALE & ASSOCIATES, INC. September 2, 2020 Mr. David James Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Project title: Belvedere Phase 5A Project file number: SUB-2019-00170 Road Plan Review #3 Project file number: SDP-2020-00036 Final Site Plan Review #2 Dear David, Please find attached the revised plans. The plans have been revised to address the comments in accordance with the comments received on the Road Plan and the Final Site Plan. CDD Inspections — Michael Dellinger No Obje CDD E911 — Brian Becker No Objec— Rivanna Water and Sewer Authority — Victoria Fort No objection. Fire Rescue — Shawn Maddox No objection. Virginia Department of Transportation — Max Greene (SDP-2020-00036 & SUB-2019- 00170). Comments received July 16, 2020. ivo objection. Leiter receivea uuiy io, zuzu. "The Department of Transportation, Charlottesville Residency Transportation and Land Use Section, has reviewed the above referenced plan as submitted by Roudabush, Gale, & o 1—f o„ 4�f-A June 22, 2VrI —1 1.—' it t ho no —Ik, I ---- table.,, Countv Plannina — Cameron Lanaille (SUB-2019-00170). Comments dated Julv 23. 2020 1. [General Comment] Please be aware that Planning staff are not reviewing notes and calculations related to certain Zoning Ordinance and Subdivision Ordinance requirements that do not pertain to improvements or land disturbances unrelated to the actual road construction. For example, the allowable density calculations and building height notes on Sheet 1 have not been checked. Comment acknowledged. 2. [4.12.6] One guest parking space per four units is required for single-family attached units that are providing parking on individual lots. Please clarify the required parking notes on Sheet 1; the calculation should state 1 guest parking space per every 4 attached single-family units" and state the required number (10 spaces, fractions must be rounded up). Comment addressed. a. Under "Parking Provided" on Sheet 1, state that 18 on -street guest spaces are provided. Comment addressed. 3. [32.7.9.5 (d)] Street trees must be provided within the 6' landscaping strip within the public right-of-way, and cannot be provided on private lots within a landscaping easement unless VDOT specifically says the trees have to be located outside of the ROW. Conflicts with proposed utilities is a reason that street trees can be located on private lots under Section 32.7.9.5; this is a design issue that must be rectified. Trees on lots 2, 4, 8, 33, 34, 35, 36, 39, 42, and 43 need to be relocated so that they are within the landscaping strip within the street right-of-way. Comment addressed. 4. [32.7.9.5 (d)] Revise the street tree calculation for Fowler Street and Fowler Circle on Sheet 19. Fractions should be rounded up. 28 trees are required for Fowler Street and 24 trees are required for Fowler Circle. Comment addressed. 5. [32.7.9.5] Remove the callout for the 8 TC trees at the southeast end of Fowler Street on Sheet 17, they are not being provided/shown on the plans. Comment addressed. County Engineering — David James (SUB-2019-00170). Comments dated July 17, 2020. Revision #2. 1. Sheet 1: a. Accurate current existing topography and conditions should be field verified within the last year. b. Topography may need to be resurveyed (2016 - Last aerial survey). (Rev.1) Acknowledged. 2. Include County's'General Construction Notes for Public Streets'. (Rev.1) Not addressed. (Rev.2) Acknowledged. 3. Sheet 13: a. Check that the inlet design is correct (LD-204 worksheet). Inlet 23 shows no DA; Inlet 3 Cross SI (Sx). Show correct ID downstream. What is Q intercepted/bypassed, C values (LD-204, Show similar form data)? [Refer to Table 9.1 of VDOT DM] (Rev.1) Addressed. b. Correct pipes with velocity under 3 fps (LD-229 worksheet). Show similar form data. [9.3.5, VDOT DM]. (Rev.1) Not addressed. The minimum scour velocity is 3 fps. Response: The pipe velocity has been increased where possible. The remaining pipes with velocity under 3 fps are short pipes that join into the system from the other side of the road. The slopes in these pipes have been increased to over 7% minimum to aid in the flushing of sediment through the pipes. The velocity is under 3 fps due the small drainage areas serving these inlets. Multiple inlets are necessary due to the space restrictions between driveways. Please see the email from Max Greene, VDOT, on 6/8/2020 where he agrees with the design of the system as shown. Inlet shaping is called in the structures to prevent standing water. (Rev.2) Acknowledged. c. Reduce pipe outlet velocity to 10 fps or less (LD-229 worksheet). (Rev.1) Addressed. d. Provide HGL computations (LD-347). (Rev.1) Addressed. e. Add note or callout to include IS-1, inlet shaping at flow intersections (Str 3, 14, 15, 16, 17). (Rev.1) Addressed. 4. Show/label angle of intersection at entrances. -80 degrees (Min)? [14-410] (Rev.1) Please add label to both intersections showing the angle. (Rev.2) Acknowledged. 5. Show offsite grading easement for the temporary fire access road grading proposed. -how f - nporary access easement for the road as well. (Rev.1) Ar'- A. 6. Record access easement prior to road plan approval. (Rev.1/2) Acknowledged; Comment still valid. Plat undergoing review. Response: Acknowledged, the easement plat has been submitted for review. The grading easement at the entrance of Fowler has been added and the widths of the storm easements have been updated. 7. Submit an amendment to any grading plans affected by the proposed access road construction. They will have to be reviewed/approved prior to road plan approval. Response: No amendments are necessary. (Rev.1) Acknowledged. 8. Sheet 7: Show width of on -street parking. Response: Dimensions have been added to the Site Plan sheet 4. (Rev.1) Addressed. 9. Sheet 9: Show any pipe/utility crossings in the profiles. (Rev.1) Addressed. 10. Sheet 10: Add cross -drains or underdrain at sag. (Rev.1) Stormwater will be impounded by the access road. Temporary E&SC controls would be needed and a WPO plan would need to be submitted. (Rev.2) Currently addressed. 11. Sheet 11: It appears that sight distance easements need to be shown for those outside of the ROW. (Rev.1) Addressed. Submit a plat to recorded them prior to FSP approval. 12. Sheet 12: Where does the road drainage go beyond storm str 12? Show inlets. (Rev.1) Acknowledged. Submit a WPO plan approval required prior to FSP approval. Rev.2) Currently addressed. 13. Provide earthwork vol. estimates of cut & fill for the roads & access grading. Response: The entire parcel will require 119 cubic yards of import. (Rev.1) Acknowledged. 14. (Rev.1) The grade for the emergency access needs to be 10% or less. [18-4.12.17] (Rev.2) Addressed. 15. (Rev.1) The minimum recommended storm size pipe is 15" dia. Initial pipe runs can use 12" dia. if the length of pipe is 50' or less. The max access hole spacing is 50' for 12" dia. 300' for 15-42" dia. pipe. [VDOT DM 9.3.5, 9.3.6, table 9-3] (Rev.2) Addressed. Albemarle County Service Authority — Jeremy Lynn (SDP-2020-00036 & SUB-2019-00170). Comments received July 6, 2020 Sheet 1 1. Final dedication of Belvedere Phase 2B required prior to final plan approval. Response: Acknowledged. 2. Eliminate the following sheets from the ACSA submittal: 12, 17, 21, and 21. Response: Acknowledged. Sheet 6 (revised to sheet 7) 1. Eliminate sanitary sewer pipe material references to avoid any discrepancies. Response: The pipe "call outs" on sheet 6 has been removed. 2. Water meters for Lots 37-42 need to be placed in front of the sidewalks. Response: The water meters have been moved in accordance with email exchange with ACS on 11 August 2020. 3. Clarify which lots are being served by the meters along Fowler Street (behind Lots 34-43). Response: Labels have been added for clarity. 4. No part of the footing, overhang or structure for Lot 31 can fall within the proposed ACSA easement. Response: Acknowledged, neither the overhang nor the footing is within the easement. Sheet 16 (revised to sheet 17) 1. Sanitary sewer between MH's G and H shall be ductile iron. Response: Pipe H — G has been labeled as ductile iron. 2. Call out 60-inch diameter manhole with internal drop for MH A. Response: Call out has been added. Sheet 18 (revised to sheet 19) 1. Eliminate conflicts between street trees and ACSA utilities. Trees in front of Lots 21, 27, 30, and 31 are closer than 10-feet to the ACSA's sanitary sewer main. Response: Landscaping has been revised. We thank you for taking the time to review these plans and trust the above adequately addresses your comments. However, please let me know if you have any questions or require additional information. Respectfully, Riki Van-Niekerk