HomeMy WebLinkAboutZMA200500010 Staff Report 2006-04-11COUNTY OF ALBEMARLE
EXECUTIVE SUMMARY
AGENDA TITLE: STAFF:
ZMA 2005-010 Wachovia and Shops at Rio Road SEAN DOUGHERTY
SUBJECT/PROPOSAL/REQUEST: PLANNING COMMISSION DATE:
Rezone 1.836 acres from CO — Commercial April 11, 2006 Public Hearing
Office to C-1 — Commercial to allow a partial
redevelopment of the site and accommodate BOARD OF SUPERVISORS DATE:
redevelopment of an adjacent parcel. May 3, 2006
OWNER/APPLICANT: The owner is Wachovia bank represented by Steve Messing of Unicorp
National Development.
PROPOSAL:
The applicant is requesting a rezoning of 1.836 acres (the Wachovia Bank property) from CO to C-1
to allow for redevelopment of an adjacent property (zoned C-1) at the corner of Rio Road and Route
29. Specifically, the applicant would like to replace the Rio Road Superette and Heritage Memorials of
Charlottesville with a new restaurant of 4,300 square foot restaurant and 11,000 square feet of retail.
A rezoning of the bank property would be followed by a boundary line adjustment and the purchase of
about one acre of land from the bank to support the developer's plans for the adjacent property (Rio
Road Superette and Heritage Memorials). No proffers accompany this request.
BACKGROUND:
The property at the corner of Rio Road and Route 29 has been developed with the Rio Road
Superette and Heritage Memorials for several decades. The applicant would like to redevelop the site
with retail and restaurant uses by using a portion of the bank's property. This would include shared
and coordinated parking for the bank property and the redevelopment of the corner property.
Given the visibility of this site along two designated Entrance Corridors, the applicant took initial
redevelopment concepts for the bank property and corner property before the Architectural Review
Board on August 25, 2005. The ARB expressed concern regarding the initial concepts and offered the
applicant direction so that an appropriate design solution for this prominent site could be composed.
The ARB reviewed the applicant's current proposal on February 6, 2006 and unanimously approved
the applicant's revised plan.
DISCUSSION/FINDINGS:
The request is found to be consistent with the Land Use Plan and with the Neighborhood Model in
general. The plan reflects the ARB's feedback and comments.
Factors favorable to this request
The placement of the building beside the Entrance Corridor conforms to the Neighborhood
Model.
The plan effectively relegates parking.
The pedestrian connection to Fashion Square supports the Neighborhood Model.
The proposed stormwater management concepts for the site will provide better than currently
exists on the property and in excess of what the stormwater ordinance requires.
Factors unfavorable to this request
The applicant has not made a commitment to the key features illustrated on the rezoning plan.
RECOMMENDATION:
Staff recommends approval if a commitment to the proposed rezoning plan is made
STAFF PERSON: Sean Dougherty
PLANNING COMMISSION: April 11, 2006
BOARD OF SUPERVISORS: May 3, 2006
ZMA 2005-00010 WACHOVIA and Shops at Rio Road
Proposal:
The applicant is requesting a rezoning of 1.836 acres (the Wachovia Bank property) from CO to C-1
to allow for redevelopment of an adjacent property (zoned C-1) at the corner of Rio Road and Route
29. Specifically, the applicant would like to replace the Rio Road Superette and Heritage Memorials of
Charlottesville with a new restaurant of 4,300 square feet and 11,000 square feet of retail. A rezoning
of the bank property would be followed by a boundary line adjustment and the purchase of about one
acre of land from the bank to support the developer's plans for the adjacent property (Tax Map 61,
Parcel 122A; Rio Superette and Heritage Memorials). No proffers accompany this request.
Petition:
PROJECT: ZMA 2005-00010 Wachovia Bank and Shops at Rio Road.
PROPOSAL: Rezone 1.836 acres from CO (Commercial Office) zoning district which allows 15 units
per acre to C-1 (Commercial) zoning district which allows 15 units per acre to allow a partial
redevelopment of the site and accommodate redevelopment of an adjacent parcel (Tax Map 61,
Parcel 122A). No residential uses are proposed with this rezoning.
PROFFERS: No
EXISTING COMPREHENSIVE PLAN LAND USE/DENSITY: Regional Service (regional -scale retail,
wholesale, business and/or employment centers, and residential (6.01-34 units/acre) in Neighborhood
One.
ENTRANCE CORRIDOR: Yes
LOCATION: 1625 Seminole Trail (Wachovia Bank), near the southeastern corner of U.S. Rt. 29 and
Rio Road.
TAX MAP/PARCEL: Tax Map 61, Parcel 122
MAGISTERIAL DISTRICT: Rio
Character of the Area:
The parcel lies along Route 29 north and contains a Wachovia Bank near the intersection of Rio
Road on an outparcel of the Fashion Square Mall. The parcel has access from Route 29 and Rio
Road. The area is defined by Fashion Square, numerous highway commercial / strip development
outlets including retail, banks, fast food, and the major roads mentioned.
By -right Use of the Property
The property is zoned CO - Commercial Office. CO districts permit development of administrative,
business and professional offices and supporting accessory uses and facilities. This district is
intended as a transition between residential districts and other more intensive commercial and
industrial districts. The current use is a 3,500 square foot bank with three drive -up bays. The bank
utilizes roughly half of the parcel. The other half, roughly an acre which also provides access to the
bank from Rio Road, could be developed with uses allowed in CO. (Uses permitted in CO include:
administrative and business offices; professional offices, including medical, dental and optical;
financial institutions; churches, cemeteries; libraries, museums; accessory uses and structures
incidental to the principal uses provided herein (copy centers, food service, etc for employees only);
ethical pharmacies, laboratories and establishments for the production, fitting and/or sale of optical or
prosthetic appliances on sites containing medical, dental or optical offices; sale/service of goods
ZMA 2005-000
Wachovia Bank ana onops at Rio Road
associated with the principal use; public uses and buildings including temporary or mobile facilities
such as schools, offices, parks, playgrounds and roads; temporary construction uses; dwellings;
temporary nonresidential mobile homes; day care, child care or nursery facility; tier I and tier II
personal wireless service facilities. A number of uses are permitted by special use permit, including
funeral homes, schools of special instruction, hotels, motels, and inns, research and development
activities, and indoor athletic facilities.)
Specifics of the Proposal:
Attachment A provides a location map. Attachment B is the rezoning plan. Attachment C contains
renderings and perspective illustrations, and Attachment D contains a diagram illustrating the
sequence that will allow the redevelopment the applicant is proposing. The proposal aims to rezone
one parcel to support redevelopment of another parcel. The parcel being rezoned from CO to C-1 will
be referred to as the "bank parcel". The parcel upon which redevelopment is aided by the rezoning
will be referred to as the "corner parcel" (currently C-1). This corner parcel currently contains the Rio
Road Superette and Heritage Memorials of Charlottesville. By rezoning the bank property to C-1, the
applicant will be able to utilize two contiguous parcels with like zoning classifications to prepare a
coordinated site plan for both parcels. Should the rezoning be approved, the boundary of each parcel
will be adjusted by the applicant. The proposal for the redevelopment of the corner parcel includes
demolishing the Rio Superette and Heritage Memorials. It has been determined that these structures
are not historically significant.
Applicant's Justification for the Request:
The applicant's justification is that this rezoning will allow for the corner to be redeveloped in a
manner that is coordinated with the bank property. This will better meet the goals of the Entrance
Corridor overlay district and Comprehensive Plan.
Planning and Zoning History:
Prior to 1980, the parcel was zoned "Commercial Business". In 1980 the parcel was designated
"Commercial Office" to be consistent with new zoning definitions and in support of the bank, which
also served as a bank operations center with offices.
Comprehensive Plan:
The Land Use Plan designates this area as Regional Service. This designation also covers the entire
Fashion Square Mall. The land use designation across Route 29 is also regional service. The
Regional Service Land Use designates the following (in italics):
• Uses allowed within this designation include regional -scale commercial, regional malls, medical centers,
mixed-use developments, hotel/motel/conference facilities, professional and corporate offices, interstate
interchange developments and uses providing retail, wholesale, business, and/or employment services to
Albemarle County and the region.
Given the small size of the parcels, staff believes the applicant has responded appropriately to this
designation by incorporating the bank with a redevelopment to include retail and a restaurant.
• Areas designated as Regional Service typically encompass a large site (+ 30 acres), arterial road
accessibility, water and sewer availability, and compatibility with adjacent land uses. Both vehicular and
pedestrian interconnections are expected to nearby residential areas.
These features are in place and are more appropriately associated with the Fashion Square parcel
than the 1.836 -acre subject parcel.
ZMA 2005-0001 o
Wachovia Bank and Shops at Rio Road
• A mixture of Urban Density Residential uses and community service uses is anticipated within this
designation.
Urban Density Residential is in place to the east of Fashion Square in Abington Crossing and
Glenwood Station. The size and location of the subject property near the intersection of Route 29 and
Rio Road suggests residential development is not appropriate. Staff believes the applicant has
responded to the general recommendations found in the Comprehensive Plan.
Specific, applicable recommendations for this property contained in the Neighborhood One
recommendations of the Comprehensive Plan are as follows:
Future development plans along Route 29 North are to be sensitive to its status as
an Entrance Corridor Roadway.
Transportation improvements include:
- Provide landscaping, walkways and bicycle facilities along Route 29 to
enhance this corridor as the County's major business district.
Staff believes the applicant has responded to these specific recommendations
Architectural Review Board
The ARB reviewed the applicant's current proposal on February 6 and were pleased with the
applicant's revisions. To clarify the acceptability of the building and parking location, the ARB
forwarded the following to the Planning Commission with respect to the rezoning and overall
treatment of both parcels:
The ARB has no objection to the proposed building location or parking location illustrated on
Sheet C2.0 dated June 27, 2005 entitled "Site Layout for Wachovia Bank at Shops at Rio" by
Hurt & Proffit Inc.
Rezoning Plan
The applicant has not committed to the key features of this plan. Therefore, there is no guarantee
within C-1 zoning that this rezoning will not result in a different plan for the site. The key features staff
considers important are:
The location of the buildings and parking
The location and number of vehicular entrances
The location and construction of the pedestrian connection to the mall
The internal pedestrian and vehicular network
The proposed conceptual plan for stormwater management.
Other matters, such as landscaping and architectural detail, will be brought before the ARB during the
site plan stage. The most practical mechanism for guaranteeing the important key features will
accompany the site's redevelopment would be to proffer the plan. Alternatively, the applicant could
commit to these features in proffers.
In discussing these options with the applicant, he indicated he is not interested in proffering the plan
because that may make it more problematic for him to alter or further develop the property in the
ZMA 2005-00010
Wachovia Bank and Shops at Rio Road
future. The applicant further indicated he would like to make that decision based on feedback from
the Commission during the public hearing. The following comment is offered based on the applicant's
rezoning plan as submitted (without commitment).
Places 29 Masteralan
The Places 29 Masterplan coordinator has reviewed the applicant's redevelopment concept and has
indicated that the proposal is in keeping with the Masterplan's Guiding principles and the emerging
themes of that study.
Conformity with the Neighborhood Model and Guidelines:
Pedestrian
The applicant is providing a pedestrian connection from the
Orientation
southeast corner of the site (closest to Fashion Square Mall) in
support of pedestrian connectivity. The applicant is providing
Neighborhood
sidewalks along Route 29 and connecting into both parcels which
Centers
include ample pedestrian facilities internal to the parcel. The plan
illustrates pedestrian connections between the proposed retail /
restaurant building and the existing Wachovia Bank. Staff believes
Buildings and
this response is appropriate but seeks a commitment to these
Spaces of Human
concepts in addition to those discussed in this section.
Neighborhood
No new streets are proposed. The travelway extending from the
Friendly Streets and
entrance on Route 29 provides a connection to Fashion Square. By
Paths
not offering a direct route, but requiring several turns, the plan
works to reduce the speeds of cut -through traffic. The rezoning plan
identifies pedestrian crosswalks across/through travelways.
Interconnected
The proposal includes one vehicular and one pedestrian connection
Streets and
to Fashion Square. This is an adequate response to the
Transportation
Neighborhood Model given the site's location and constraints
Networks
corner property along the road and moves parking toward the rear.
Parks and Open
The proposal for the restaurant (at the corner on the corner parcel)
Space
may include outdoor seating. The scope of this request does not
warrant the provision of parks or open space.
Neighborhood
The proposal is adjacent to Fashion Square Mall, which serves as
Centers
a neighborhood center. The pedestrian connection at the
southeast corner of the site will work to activate a better
relationship between the center and these outparcels.
Buildings and
The applicant proposes buildings and spaces of human scale. The
Spaces of Human
proposed redevelopment of the corner property includes buildings
Scale
that are 24 feet tall with 33 foot tall tower elements that include
clerestory windows. See Attachment C for a perspective
illustration of the applicant's proposal for the site's redevelopment.
The combined parcels are roughly 240X650 feet and relatively flat.
Therefore, the entire site is contained within a reasonable walking
distance at a pedestrian -friendly grade.
Relegated Parking
Relegated parking is considered that which is located behind and
to the side of buildings. This proposal places the building on the
corner property along the road and moves parking toward the rear.
The applicant has achieved an appropriate response to this
principle.
ZMA 2005-00010
Wachovia Bank and Shops at Rio Road
Mixture of Uses
The uses on both parcels will now include a bank, a restaurant,
and almost 11,000 square feet of retail. This represents a good
mix of uses for a relatively small site.
Redevelopment
The rezoning of the bank parcel will allow for the redevelopment of
the corner parcel, representing an excellent response to the
Neighborhood Model.
Site Planning that
The parcel is relatively flat and the proposed development
Respects Terrain
responds appropriately to it.
Clear Boundaries
The parcel is far from the edge of the Development Area. This
with the Rural Areas
principle does not apply.
Staff Comment:
Relationship between the application and the purpose and intent of the reauested zonina district
The rezoning is a change from CO: Commercial Office to C-1: Commercial. Relatively speaking, this
is a shift in zoning rather than an outright change. However, the change does allow for additional
uses on the subject property. The additional uses allowed in C-1, but not permitted in CO are retail
sales, clubs and lodges, health spas, indoor theaters, laundromats and cleaners, day care,
restaurants, tailors, automobile service stations, medical centers, automobile repair shops, indoor
athletic facilities, and farmer's market.
The existing surrounding zoning is a mix of primarily HC — Highway Commercial and PDSC —
Planned District Shopping Center. The Fashion Square Mall and Albemarle Square developments are
zoned Planned PDSC. The quadrants at the south west and northwest corner of Route 29 and Rio
are zoned HC Highway Commercial. This classification extends roughly 400 feet to the west of 29
and north and south of the Rio intersection about 500 feet.
The applicant's proposal of retail and a restaurant, in addition to the existing bank is in keeping with
the intent of C-1 Commercial. Highway Commercial (HC) and Planned District Shopping Center
(PDSC) are also possible zoning districts which could support the desired redevelopment. C-1
Commercial is more limited that HC or PDSC.
The application plan also eliminates the current entrance to the superette on Route 29, which will
generate some improvement for the traffic flow off of Route 29 northbound onto Rio Road. Given the
highway -oriented nature of the superette and memorial dealer, staff believes that the proposed
change, in conjunction with ARB review and approval of the applicant's proposal, will yield
improvements to the aesthetics and functionality of the underdeveloped bank and corner parcel.
Anticipated impact on public facilities and services
Roads
Access to the bank parcel is provided from entrances off of Route 29 and Rio Road. Supplemental
access may be gained from Fashion Square Mall in the form of a vehicular entrance and an extension
of the rezoning plan's pedestrian network to the edge of the subject property.
ZMA 2005-00010 7
Wachovia Bank and Shops at Rio Road
Water and Sewer
Water and sewer service is adequate to serve the development.
Stormwater Management
Conceptual stormwater management issues are sufficiently resolved with the application plan and
provide better stormwater management than exists on the site. In addition, the application plan
illustrates better stormwater management than is required by the Ordinance. However, there is no
commitment to these concepts.
Anticipated impact on nearby and surrounding properties
The surrounding properties are commercially developed. The introduction of additional retail sales
and a restaurant generate minimal traffic impacts. Given the relatively small site and the constraints
of the Route 29 and Rio Road interconnection, staff suggested to the applicant that contributions
toward transit, particularly the mall bus stop, or contribution general contributions toward transit
(studies, shelters, benches) would work to enhance transit service and viability. An enhancement of
transit service may lead to a reduction in traffic and single -passenger vehicle trips. Staff cannot
identify any additional impacts that this change would generate along this commercial core.
Public need and justification for the change
The redevelopment of the bank parcel and the corner parcel to allow a restaurant and several retail
stores is a fitting use for this Land Use Plan designation. The service station / superette and memorial
dealer are less compatible with the area than when these uses were initially established on the site.
Proffers
No proffers were submitted with this rezoning request.
SUMMARY
The applicant's revisions to the plan since the applicant's initial submission, in conjunction with the
ARB's oversight on the proposal given its location, suggest the proposal will represent a
redevelopment of a prominent site that reflects principles of the Neighborhood Model. The applicant's
response to the ARB's feedback provides an application plan that is workable. However, without a
commitment to the plan submitted with the application, there is no guarantee that redevelopment of
the site as a result of this rezoning will be in general conformity with the rezoning plan submitted with
this application.
Factors favorable to this request
The placement of the building beside the Entrance Corridor conforms to the Neighborhood
Model.
The plan effectively relegates parking
The pedestrian connection to Fashion Square supports the Neighborhood Model.
The proposed stormwater management concepts for the site will provide better than currently
exists on the property and in excess of what the stormwater ordinance requires.
Factors unfavorable to this request
The applicant has not made a commitment to the key features illustrated on the rezoning plan.
ZMA 2005-00010 8
Wachovia Bank and Shops at Rio Road
Recommendation:
Staff recommends approval if a commitment to the rezoning plan, or key features contained thereon,
is made.
ATTACHMENTS
A. Location Map
B. Application Plan
C. Renderings and Perspective Illustrations
D. Illustrative Timeline for Redevelopment
ZMA 2005-00010
Wachovia Bank and Shops at Rio Road