HomeMy WebLinkAboutSUB198800212 Checklist 2020-10-30Frank and David,
Hope all is well.
As per the Tandem Farm CRD's list please find the following attached
suupport documents:
1.) Copies of recorded plats for right of way, and easements.
a.) I have attached the subdivision plats that affect the
properties along Blue Springs Lane and Ragged Ridge Lane. As
it appears most are just homidary line adjustments, as we have
found no changes to the right-of-way as shown on the original
plat recorded in Deed Book 1341, Page 121.
2.) Surveyors Letter of Certification
3.) Developers Certificate of Completion
4.) Field Lab Tests performed by ECS Mid Aflantic.
5.) I am re -sending as -built survey.
Outstanding Items (OSI) Remaining:
1.) CBR Test
2.) Stone and Pavement depth/material inspection
3.) Pipe Trench inspections
4.) Pipe Interior Inspection reports and video.
OSI #1 and #2, please verify that VDOT did not already receive these
back in 2014. The contractor making the field changes believe core
borings we completed and submitted along with the CBR Test.
OSI #3 and #4, Were pipe trench inspections and video installation
monitoring required during the construction of these roads back in the
day?
Thanks much,
Rob Cummings
Project Manager
Kirk Hughes and Associates.