HomeMy WebLinkAboutSDP202000035 Correspondence 2020-11-09I® COLLINS ENGINEERING
November 9, 2020
Cameron Langille
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
RE: Brookhill Block 1A Final Site Plan (SDP 202000035)
200 GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
(�434.293.3719 PH 434.293.2813 FX
www.coll ns-eng ineeri ng.com
Thank you for your comments dated August 11, 2020 on the above referenced project.
Plannin¢
Comment Response:
• In addition to addressing the following comments, all the information for the improvements of the ice rink
have been removed from the plans.
1. The TMP on sheet 1 has been updated for the new TMP # and DB/PG information. This information has been
added to sheet 4 as well. The residue TMP # has also been updated on the all the sheets.
2. Comment previously addressed.
3. Comment previously addressed.
4. Comment previously addressed.
5. Comment previously addressed.
6. Comment previously addressed.
7. Comment previously addressed.
S. Comment previously addressed.
9. Comment previously addressed.
10. Comment previously addressed.
11. Comment previously addressed.
12. The overall acreage for Block 1A has been updated for 1.24 acres on sheet 1 and sheet 4. The residue acreage
has been updated as well.
13. The overall acreage for Block 1A has been updated for 1.24 acres on sheet 1 and sheet 4. The residue acreage
has been updated as well.
14. Comment previously addressed.
15. Comment previously addressed.
16. Comment previously addressed.
17. Comment previously addressed.
18. Comment previously addressed.
19. Comment previously addressed.
20. Comment previously addressed.
21. The landscaping plan has been updated to include a section in the planting chart for the offsite landscaping.
Also, the overall canopy has been updated accordingly. See the landscaping sheet.
22. Comment previously addressed.
23. The landscaping has been updated to include the offsite landscaping, as requested. See the landscaping sheet.
24. Comment previously addressed.
25. Comment previously addressed.
26. Comment previously addressed.
27. Comment previously addressed.
28. Comment previously addressed.
New Comments:
1. The DBE PG_ has been added to the plans and this information will be filled in once the plat is recorded.
2. Sheet 3 has been updated with the approval date for the 8A, as requested.
3. Comment previously addressed.
4. Comment previously addressed.
5. The DBE PG_ has been added to the plans and this information will be filled in once the plat is recorded.
6. Comment previously addressed.
7. Comment previously addressed.
S. Comment previously addressed.
9. The landscaping plan has been updated for the parking lot landscaping and to include the offsite landscaping.
10. The density for the site has been updated for the revised lot area.
11. The developers are working on recording these portions of Archer Avenue and Stella Lane.
En¢ineerine
1. WPO has been approved.
2. Salamander road plan has been approved.
3. Comment previously addressed.
4. Comment previously addressed.
5. Comment previously addressed.
6. Comment previously addressed.
7. Comment previously addressed.
8. Comment previously addressed.
9. The tree placement has been updated and moved away from the storm structures and pipes.
10. Comment previously addressed.
11. Intersection sight distance has been updated to show the site distance from the intersection to the entrance.
This site distance is outside of the onstreet parking spaces.
Buildin¢Inspections
1. The building note has been added to sheet 1 as requested.
VDOT
Salamander Street Road plans have been approved.
ACSA
Utility plans are approved and currently being constructed.
Should you have any questions, please feel free to contact me at scott@collins-engineering.com.
Sincerely,
Scott Collins