HomeMy WebLinkAboutSUB200600237 Approval - County 2006-10-11$, � ALp�
R'h
County of Albemarle
Department of Communitv Development
October 11, 2006
Kurt Gloeckner
508 Dale Avenue, Suite A
Charlottesville, VA 22903 -0000
RE: SUB- 2006 -237 Farms at Turkey Run Preliminary Plat
Dear Mr. Gloeckner:
The Department of Planning and Community Development hereby grants administrative approval to the
above - referenced site plan.
The approval of the preliminary site plan is valid for (1) one year in accordance with Zoning Ordinance
Section 32.4.3.1. Therefore, the preliminary approval shall expire October 11, 2007. If the preliminary site
plan approval expires, a new application must be filed and processed.
Please address all of the requirements and conditions listed below and submit eight (8) tentative plan copies to
the Department of Planning and Community Development. This letter must be submitted with the tentative
plans, as a checklist, to document that you have addressed all requirements or conditions, or the tentative plan
will be denied. A submission and review schedule is attached for your information.
The Erosion and Sediment Control Plan and the BMP Stormwater Management Plan, with the associated
applications and fees, may also be submitted with the eight (8) tentative Plans. Failure to do so will result in a
separate application to be filed at a later date. (Note — some of these plans for this project may have been
submitted previously).
After the initial tentative plan submittal, each department/agency will contact you to discuss any remaining
conditions. After all aforementioned department /agencies have granted a tentative approval, you may submit
the final mylars (1 sets), two paper copies, final site plan application, final site plan fee, and a copy of all
written tentative approvals to the Department of Planning and Community Development. Assuming that the
final site plan mylars reflects all tentative approvals, signing of the plans will occur within one week.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section 32.6), in
addition to the following conditions.
The Community Development Department shall not accept submittal of the final site plan for signature until
tentative approvals for the following conditions have been obtained. The final site plan shall not be signed
until the following conditions are met:
Zoning & Current Development approval to include:
❑ Submittal of a final plat meeting the requirements of Chapter 14, Section 303 of the County
Code.
Please contact me at 296 -5832 x.3242 if you have questions or require additional information.
Engineering approval to include:
❑ Approval of Stormwater detention plan
Please contact Glenn Brooks at 296 -5832 x.3273 if you have questions or require additional information.
Health Department Approval:
❑ Approval of area for primary and reserve drainfield for each lot.
VDOT approval to include:
❑ All VDOT Virginia Department of Transportation comments must be addressed before final
plan approval can be granted.
Please contact John Winn or Joel Denunzio at 293 -0014 if you have questions or require additional
information.
ANY OTHER DEPARTMENT/DIVISION /AGENCY approval to include:
❑ Approval of street names.
Sincerely,
William D. Fritz, AICP
Chief of Current Development
File: SUB- 2006 -237 Farms at Turkey Run Preliminary Plat