COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road,Room 227
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
Project: WPO-2005-0013,Newcomb Mountain Lane, Private road plans
Plan preparer: Mr. Steve Driver, PE,Terra Engineering,LLC (fax 434.975.0900)
Owner or rep.: Mr. Alex Toomy,The Rocks,LLC (fax 434.296.2814)
Mr. Mike Boggs, Haley,Chisholm, Morris (fax 434.974.6849)
Date received: 13 June 2006(road and E&SC plans rev.date 12 June 2006)
Rev. 6: 26 June 2007(road plans rev. date 26 June 2007)
Rev.7: 07 August 2007 (plans rev.date 01 August 2007)
Date of Comment: 07 July 2006
Rev. 6: 31 July 2007
Rev. 7: 16 August 2007
Engineer: Allan Schuck
The private road plan for Newcomb Mountain Lane,received on 07 August 2007,has been reviewed. The
engineering review for current development recommends approval of the road plans when the following
items are adequately addressed:
A.Road plan and drainage computation comments:
1. The revision of the cul-de-sac to a hammerhead turn around is acceptable with the following
changes:
• Please revise the hammerhead design to the following standards:the radius of
pavement=30',the length of the hammerhead pavement= 50' as measured from
the centerline of Newcomb Mountain Lane.
• Please provide a temporary hammerhead turnaround at the end of proposed street
construction of Rosemont Subdivision. This is needed to provide a turnaround if
the remainder of Newcomb Mountain Lane is not bonded or built.
• Please revise the final subdivision plat that provides the 40' access easement to
include the new turnarounds for Newcomb Mountain Lane.
Rev. 7: The first two parts of this review comment have been adequately addressed
with this plan submittal. The applicant still needs to submit a revised plat for the access
easement and private street to accommodate the changes to the street plan. This comment
affects the final plat approval only. The private street plans can be recommended for approval.
2. The road bond amount is for HCM is$401,000.00. The road bond amount for The Rocks,
LLC is$83,000.00. Please contact Ms. Pam Shifflett at 434.296.5832 Ext. 3246 for more
information on the posting of this road bond.
3. The road bond needs to be posted and approved before Engineering will recommend approval
to the final subdivision plat.
File:E7_rp_ADS_WPO-05-013 Newcomb Mountain Lane
Newcomb Mountain Lane This bond is for Haley,Chisholm&Morris's portion of Newcomb Mtn Lane
ROAD Construction Bond Estimate(roads,site work,storm sewer)
Item Item No. Unit Unit Cost Cost
Number (installed)
Newcomb Mountain Lane 9+00 to 44+00 road length 3500.0 ft
1 aggregate base 6.0 in d 2020.0 ftL 16.0 ft W 598.5 cy $35.91 $21,492.80
2 asphalt surface 1.5 in d 2020.0 ft L 16.0 ft W 226.2 tons $81.90 $18,529.06
3 aggregate base 6.0 in d 1480.0 ftL 14.0 ft W 383.7 cy $35.91 $13,778.80
4 asphalt surface 1.5 in d 1480.0 ft L 14.0 ft W 145.0 tons $81.90 $11,878.78
5 street name sign 1 $65.00 $65.00
6 traffic control sign 2 $49.35 $98.70
7 guardrail 14 ES g$3700 3800.0 ft $16.80 $115,640.00
8 pipe,crnp(15 to 48") 15.0 in d 2 ES-1,2$250 1 EC-1$200 29.0 ft $23.10 $1,369.90
9 pipe,cmp(15 to 48") 18.0 in d 4 ES-1,2$250 2 EC-1$200 81.0 ft $27.30 $3,611.30
10 E&S fabric,EC-2,3 4900 ftL 4 ft W 2177.8 sy $10.50 $22,866.67
11 clear and grub(for wooded sites) 5.0 acre $10,500.00 $52,500.00
12 grading (per cy for cut or import only; 1.0 cy fill 14000.0 cy cut -13999.0 cy bal $3.15 $44,100.00
13 CBR tests (1 every 0.1 mi.per road) 3500.0 ftL 7 inc of 500' 8 $157.50 $1,260.00
14 as-built drawings(1k+price per 0.11 3500.0 ft L 0.6628788 mi. 7 $1,050.00 $8,350.00
15 survey and layout(price per 0.1 mi.) 3500.0 ft L 0.6628788 mi. 7 $525.00 $4,675.00
16 mobilization 1 $525.00 $525.00
cost sum 5320,741.00
contingency 25% $80,185.25
Total $401,000
8/16/2007
Newcomb Mountain Lane This bond is for The Rock LLC's portion of Newcomb Mtn Lane
ROAD Construction Bond Estimate(roads,site work,storm sewer)
Item Item No. Unit Unit Cost Cost
Number (installed)
Newcomb Mountain Lane 44+00 to END road length 1450.0 ft
1 aggregate base 6.0 in d 1450.0 ftL 16.0 ft W 429.6 cy $35.91 $15,428.00
2 asphalt surface 1.5 in d 1450.0 ftL 16.0 ft W 162.4 tons $81.90 $13,300.56
3 pipe,cmp(15 to 48") 15.0 in d 6 ES-1,2$250 6 EC-1$200 124.0 ft $23.10 $5,564.40
4 E8S fabric,EC-2,3 500 ftL 4 ft W 222.2 sy $10.50 $2,333.33
5 clear and grub(for wooded sites) 2.0 acre $10,500.00 $21,000.00
6 grading (per cy for cut or import only; 1.0 cy fill 500.0 cy cut -499.0 cy bal $3.15 $1,575.00
7 CBR tests (1 every 0.1 mi.per road) 1450.0 ftL 2.9 inc of 500' 4 $157.50 $614.25
8 as-built drawings(1k+price per 0.1 i 1450.0 ft L 0.2746212 mi. 3 $1,050.00 $4,150.00
9 survey and layout(price per 0.1 mi.) 1450.0 ft L 0.2746212 mi. 3 $525.00 $2,575.00
10 mobilization 1 $525.00 $525.00
cost sum $67,065.54
contingency 25% $16,766.39
Total $83,900
8/16/2007