Good afternoon,
The purpose of this email is to document Contech's review of the design and proposed application of the CMP
underground detention system for the subject project.
Based on our review of the site plans provided by the FOR on 12/1/2020
(httos://www.d ropbox.com/s/lwbzx9stphe ndae/201130%20PIeasa nt%2OG reen%2OPhase%2011%20VSM P%20PIa n. odf?d
1=0), we believe the CMP detention system is an appropriate solution for this site and the design is acceptable.
Please let me know if you have any questions, or need anything else.