HomeMy WebLinkAboutWPO201900042-97236-Full Inspection ReportV NOTICE TO COMPLY Hand delivered Project: WP0201900042 Spring Hill Village - VSMP Operator/Contractor: Goodman Excavation SPRING HILL LAND DEVELOPMENT LLC Issued Date: 12/18/2020 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the referenced project and to immediately take corrective measures to address erosion and sediment control deficiencies on this property. This Notice to Comply is being issued because of the following deficiencies: Deficiency: Stabilize as required, after 7 days if remaining dorment longer than 14 days Corrective Action: apply seed,fertilizer and mulch as required Deficiency: Stabilize as required, see above Corrective Action: Deficiency: Basin 1 has a bypass cndition occuriing from the right side, DD not rereleasing into basin, Baffles are failing. Corrective Action: make required repairs to baffles and short cut condition from DD Deficiency: See above comment. Item 30 Corrective Action: Deficiency: failure of curb inlet noted. Corrective Action: install and maintain proper IP Deficiency: No wash being used. Corrective Action: use wash on every vehicle leaving site Deficiency: Sediment release onto downstream properties. culvert outfall across Rt. 20 has sediment buildup. caused by overflow across 20 and release through pipe. Corrective Action: remove sediment by hand and re-establish groundcover as required. Deficiency: no wash in use or visible on site Corrective Action: begin use ASAP, clean roadway and CE Deficiency: install stable parking within the work area to prevent sediment transfer to ROW and waterways. Corrective Action: Unless subsequently amended in writing by this office, it is expected all of these corrective measures will be completed by. Re -inspection of this notice to verify corrective measures will incur a $150 for land disturbing under VESCP and single-family dwelling units (§ 17-207) or a $250 fee for land disturbing under VSMP (§ 17- 208). Failure to take effective corrective measures will result in a Stop Work Order upon re -inspection. County Inspector Name: Geoff Elsie County Inspector Phone Number: (434) 296-5832 OF Al.,& Inspection Result: Notice to Comply r L�eo��P COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP/VESCP PERMIT SITE INSPECTION REPORT Project Name: Spring Hill Village - VSMP Project/WPO Number: WP0201900042 TMP: 09000000002800 DEQ Permit Number (if applicable): VARlON324 Project Operator: Goodman Excavation Operator Telephone #: (540) 872-5105 Project Contact: LLC SPRING HILL LAND DEVELOPMENT Contact Telephone #: Contact E-Mail: Qualified Personnel (QP): Gregg Odonnell Inspector: Geoff Elsie Weather (Wet/Dry/Rain): Disturbed Acreage: Inspection Date & Time: 12/17/2020 1:00:00 PM Single -Family: Stage of Construction: Grading Re -Inspection: Yes COVERAGE & POSTING REQUIREMENTS Compliant? Reviewed during re -inspection? No Comments/Description 1 Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A) (9VAC25-870-310)(Alb. Co. Code §17-300, 17-302) 2 A copy of the notice of coverage letter is posted conspicuously near the main entrance of the construction activity? (CGP Part II.C) Notice of the location of the SWPPP is posted near the site's entrance, if 3 applicable, and information for public access is provided? (9VAC25-870- 54.G)(CGP Part II D.2 & 3) SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? Yes Comments/Description 4 The SWPPP is on -site or made available during the inspection? (CGP Yes Part II D.1 & 2)(9VAC25-870-54.G) 5 The SWPPP contains a signed copy of the registration statement? Yes (CGP Part II A.1.a) 6 The SWPPP includes, upon receipt, a copy of the notice of coverage Yes letter and the CGP? (CGP Part II A.1.b & c) The SWPPP includes a narrative description of the nature of the Yes 7 construction activity, including the function of the project? (CGP Part II A.1 A) The SWPPP includes a legible site plan identifying all appropriate Yes 8 measures and that includes the locations of support activities and the onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7)) Page 1 of 4 9 The SWPPP contains the name, phone number and qualifications of Yes "Qualified Personnel" conducting inspections? (CGP Part II A.6) 10 The SWPPP contains an approved erosion and sediment control plan? Yes (9VAC25-870-54.B)(CGP Part II.A.2) The SWPPP contains an approved stormwater management plan or an 11 existing construction site has a stormwater management plan that Yes ensures compliance with the water quality and quantity requirements? (9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ II.0 ❑ 12 The SWPPP contains an adequate pollution prevention plan? (9VAC25- Yes 870-54.D)(CGP Part II.A.4) The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of Yes 13 concern, exceptional waters and the additional controls measures applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b)) 14 Delegation of Authority is provided and signed in accordance with Part III Yes K? (CGP Part 11 A.7) 15 The SWPPP is signed and dated in accordance with Part III K? (CGP Part Yes 11 A.8) SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Compliant? Reviewed during inspection? No Comments/Description Is the SWPPP being amended whenever there is a change in the design, 16 construction, operation, or maintenance that has a significant effect on the discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870- 54.G) Has the SWPPP been amended if inspections or investigations by the 17 operator's qualified personnel, or by local, state or federal officials find that existing control measures are ineffective in minimizing pollutants in discharges? (CGP Part II B(2))(9VAC25-870-54.G) 18 Contractor(s) that will implement and maintain each control measure are identified? (CGP Part 11 B(3))(9VAC25-870-54.G) Have there been updates to the SWPPP when any modifications to its implementation have occurred, including a record of dates when major 19 grading activities occur, construction activities temporarily or permanently cease on a portion of the site or stabilization measures are initiated? (CGP Part 11 B.4(a))(9VAC25-870-54.G) 20 Is there documentation in the SWPPP of replaced or modified controls? (CGP Part 11 B.4(b))(9VAC25-870-54.G) 21 Is the SWPPP updated to indicate areas that have reached final stabilization? (CGP Part 11 B.4(c))(9VAC25-870-54.G) Is the SWPPP updated to indicate properties that are no longer under the 22 legal control of the operator and the dates on which the operator no longer had legal control over each property? (CGP Part II B.4(d))(9VAC25-870- 54.G) Does the SWPPP identify the date of any prohibited discharges, the 23 volume released, actions taken to minimize the impact of the release and measures taken to prevent the recurrence of any prohibited discharge? (CGP Part 11 B.4(e-f)) (9VAC25-870-54.G) 24 mendments, modifications, or updates to the SWPPP are signed in accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G) INSPECTIONS AND CORRECTIVE ACTIONS Compliant? Reviewed during inspection? No Comments/Description Inspections required by the SWPPP are conducted at the required 25 frequency, including a modified frequency for impaired water(s), approved TMDL(s), and exceptional waters when applicable? (CGP Part II F (2)) (CGP Part II A.5.b.3) 26 Inspection reports are completed and signed in accordance with CGP Part 11 F (3-4)? (CGP Part 11 F (3-4)) Page 2 of 4 27 Corrective actions are taken consistent with the requirements of the CGP? (CGP Part II G(1-2)) ESC AND SWM PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description 28 Have stream buffers and steep slopes been protected as shown on the yes plan? Sequencing of the project is implemented in accordance with the yes 29 approved erosion and sediment control plan and stormwater management plans? (9VAC25-870-54.B and C) Have all denuded areas requiring temporary or permanent stabilization Stabilize as required, after 7 days if remaining been stabilized, and have stabilization requirements for impaired waters, dorment longer than 14 days 30 approved TMDL(s), pollutants of concern and exceptional waters, when No applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25- 880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) Are soil stockpiles adequately stabilized with seeding and/or protected No Stabilize as required, see above 31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II A.2(c)) (9VAC25-870-54.B) A permanent vegetative cover has been established that is uniform, N/A 32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have sediment trapping facilities been constructed as the first step in land yes 33 disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have earthen structures been stabilized immediately after installation? Yes 34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.6) Are sediment traps and basins installed in accordance with MS-6 and the No Basin 1 has a bypass cndition occuriing from the right 35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II side, DID not rereleasing into basin, Baffles are failing. A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Are finished cut and fill slopes adequately stabilized to prevent or correct No See above comment. Item 30 36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1- 2)) (9VAC25-870-54.B) Is concentrated runoff down cut or fill slopes contained in an adequate yes 37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is adequate drainage or other protection provided for water seeps? Yes 38 (9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Do all operational storm sewer inlets have adequate inlet protection? No failure of curb inlet noted. 39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are stormwater conveyance channels adequately stabilized with channel yes 40 lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is in -stream construction conducted using measures to minimize channel N/A 41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are temporary stream crossings of non -erodible material installed where N/A 42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 43 Is necessary restabilization of in -stream construction complete? (9VAC N/A 25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B) Are utility trench operations conducted and stabilized in accordance with yes 44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are soil and mud kept off paved or public roads to minimize the transport No No wash being used. 45 of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 46 Have all temporary control structures that are no longer needed been N/A removed and disturbed soil resulting from their removal permanently Page 3 of 4 stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are properties and waterways downstream from development adequately Sediment release onto downstream properties. culvert 47 protected from erosion, sediment and damage in accordance with the No outfall across Rt. 20 has sediment buildup. caused by standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840- overflow across 20 and release through pipe. 40.19(a-n)) 48 Permanent control measures included in the SWPPP are in place? N/A (9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) POLLUTION PREVENTION PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description Practices are in place to prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, N/A 49 and cleaning up spills, leaks, and other releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part III G? (CGP Part II A.4.e(1))(9VAC25-870-56) Practices are in place to prevent the discharge of spilled and leaked fuels Yes 50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II A.4.e(2))(9VAC25-870-56) Practices are in place to prevent the discharge of soaps, solvents, 51 detergents, and wash water from construction materials, including the Yes clean-up of stucco, paint, form release oils, and curing compounds? (CGP Part II A.4.e(3))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from vehicle No no wash in use or visible on site 52 and equipment washing, wheel wash water, and other types of washing? (CGP Part II A.4.e(4))(9VAC25-870-56) 53 Concrete wash water is directed into a leak -proof container or leak -proof Yes settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from N/A 54 storage, handling, and disposal of construction products, materials, and wastes? (CGP Part II A.4.e(6))(9VAC25-870-56) Practices are in place to prevent the discharge of fuels, oils, and other Yes 55 petroleum products, hazardous or toxic wastes, and sanitary wastes? (CGP Part II A.4.e(7)(9VAC25-870-56) Practices are in place to minimize any other discharge from the potential Yes install stable parking within the work area to prevent 56 pollutant -generating activities not addressed above, when applicable? sediment transfer to ROW and waterways. (CGP Part II A.4.e(8))(9VAC25-870-56) Page 4 of 4 Construction General Permit Site Inspection Report Request for Correction Action Check Regulatory Citation/Legal Occur. Observation Recommended Corrective List # Requirement* Action 30 (9VAC 25-840-40.1) Stabilize as required, after 7 apply seed,fertilizer and (9VAC25-870-54.B) days if remaining dorment mulch as required (9VAC25-880-60) (CGP longer than 14 days Part I F.1(a)) (CGP Part 11 A.5.b(1)) (CGP Part 11 A.2.c (8)) (CGP 11 E(1-2)) 31 (9VAC 25-840-40.2) Stabilize as required, see (CGP Part 11 A.2(c)) above (9VAC25-870-54. B ) 35 (9VAC 25-840-40.6) Basin 1 has a bypass cndition make required repairs to (CGP Part 11 A.2.c (9)) occuriing from the right side, baffles and short cut condition (CGP Part 11 A.2(c)) DID not rereleasing into basin, from DID (CGP 11 E(1-2)) Baffles are failing. (9VAC25-870-54. B ) 36 (9VAC 25-840-40.7) See above comment. Item 30 (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54. B ) 39 (9VAC 25-840-40.10) failure of curb inlet noted. install and maintain proper IP (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54. B ) 45 (9VAC 25-840-40.17) No wash being used. use wash on every vehicle (CGP Part 11 A.2(c)) leaving site (CGP 11 E(1-2)) (9VAC25-870-54. B ) 47 (9VAC 25-840-40.19(a- Sediment release onto remove sediment by hand and n)) downstream properties. re-establish groundcover as culvert outfall across Rt. 20 required. has sediment buildup. caused by overflow across 20 and release through pipe. 52 (CGP Part 11 A.4.e(4)) no wash in use or visible on begin use ASAP, clean (9VAC25-870-56) site roadway and CE 56 (CGP Part 11 A.4.e(8)) install stable parking within (9VAC25-870-56) the work area to prevent sediment transfer to ROW and waterways. Recommended 12/28/2020 Corrective Action Deadline: Targeted Re- 12/28/2020 Inspection Date: Comments: Site has an issue with the intersection of the basin outfall, trap out fall and the roadside ditch on Rt. 20. As designed the volume of runoff can not filter quick enough and causes a flooding effect. This flooding causes a flow of water to enter the state roadway and could lead to a hazardous driving condition. A redisign of this area must be completed asap. VDOT and Albemarle County Board of Supervisors are aware of this issue and have asked for immediate correction. Please submit an amendment to the approved plan design for review by CDD Engineering. *Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Construction General Permit Site Inspection Photo Log Photos for Item 2 Photos for Item 4 Photo Description: Photos for Item 10 Photo Description: Photos for Item 35 20201217_135633.jpg.jpg 366.49KB Photo Description: Baffles falling over. Photos for Item 39 20201217_131716.jpg.jpg 388.34KB Photo Description: install and maintain IP as required Photos for Item 45 20201217_135519.jpg.jpg 316.19KB 1� Photo Description: CE loaded with mud, no wash in use. Mud continued out onto Rt. 20 X County Inspector COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 z/1 j'* Inspection Date: 12/18/2020