HomeMy WebLinkAboutSUB202000216 Review Comments Road Plan and Comps. 2021-01-22(Z)
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
Stephen C. Brich, P.E. 1401 East Broad Street
Commissioner Richmond, Virginia 23219
January 14, 2020
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
Attn: Matt Wentland
(804) 786-2701
Fax: (804) 786,2940
Re: SUB-2020-00216 — Glenbrook at Foothills — Phase IIB — Road Plan - Review #1
Dear Mr. Wentland:
The Department of Transportation, Charlottesville Residency Transportation and Land Use
Section, has reviewed the above referenced plan as submitted by Collins Engineering, dated
October 26, 2020, and find the following:
1. Sight lines location of eye do not appear to be per RDM F-40 Intersection Sight Distance
detail and table 2-5 and RDM B(1)19 Sight Distance. Eye location will be a minimum 14.5
feet from the edge of travel lane.
2. Sight easement plats will be required for lots 165, 166, & 167 as shown on sheet 3 of the plan
submittal prior to final road plan approval. Please note sight easement plats will be required
on the adjacent phase.
3. Please provide the turn lane warrants for Eastern Ave.
4. Provide distances to nearest entrances or intersections.
5. Please show proposed entrance radii from Eastern Ave.
6. Mill and overlay for extensions/continuation of roads needs to be shown on the plans per
WP-2 detail.
7. Please show No Parking within 20 feet of any intersection measured from the curb return of
the intersection per RDM Appendix A(1).
8. There must be a 40' buffer between the cul-de-sac and parallel parking.
9. Plan sheet 3 appears to show a car parked after the "No Parking" sign location on Dunwood
Drive.
VirginiaDOT.org
WE KEEP VIRGINIA MOVING
10. "No Parking" sign appears to be missing from Claibourne Road prior to intersection with
Arboleda Drive.
11. Recommend bump -outs for parking per AASHTO Green Book 2011— 4.20 On -Street
Parking.
12. Please show and label the cross drains on the plan sheet and show how they connect to
proposed drainage structures.
13. Please provide an MOT plan in accordance with the Virginia Work Area Protection Manual.
MOT plan should be on a separate sheet and designed for this project, include the proposed
mill and overlay phase of construction.
14. Please place a note on the plan: A Traffic Maintenance Plan (TMP) is required to obtain a
permit to work within VDOT Right of Way. The TMP shall be prepared by an Advanced
Work Zone Certified person, certification card and verification number is required on the
TMP submittal.
15. Note that the final plan must show conformance with the VDOT Road Design Manual
Appendices B(1) and F, as well as any other applicable standards, regulations or other
requirements.
If further information is desired, please contact Max Greene at 434-422-9894.
A VDOT Land Use Permit will be required prior to any work within the right-of-way. The
owner/developer must contact the Charlottesville Residency Transportation and Land Use
Section at (434) 422-9399 for information pertaining to this process.
Sincerely,
Adam J. Moore, P.E.
Area Land Use Engineer
Charlottesville Residency